Tai Cheung Properties Ltd v. Cheng Wood Ming
Read the full judgment text of HCA 412/2014 on BabelCite. This High Court CFI judgment was delivered on 8 August 2018.
1. This is a claim by the employer against its former employee for damages. Interlocutory Judgment on liability has been entered against the Defendant on 16 September 2015. By an Order made by Deputy High Court Judge Kent Yee of 12 October 2017, an inquiry as to damages was set down with 5 days reserved. Before the hearing for an inquiry of damages, the Defendant who had since been acting in person wrote to Court indicating that he would not attend this hearing. I have satisfied myself that
Cites 3 cases
|
HCA 412/2014 [2018] HKCFI 1810 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO 412 OF 2014
Before : Master Thomas Leung in Court Date of Hearing : 4 June 2018 Date of Judgment : 8 August 2018 ______________________________ JUDGMENT ______________________________ 1.This is a claim by the employer against its former employee for damages. Interlocutory Judgment on liability has been entered against the Defendant on 16 September 2015. By an Order made by Deputy High Court Judge Kent Yee of 12 October 2017, an inquiry as to damages was set down with 5 days reserved. Before the hearing for an inquiry of damages, the Defendant who had since been acting in person wrote to Court indicating that he would not attend this hearing. I have satisfied myself that due notice has been given, and this hearing was to proceed in the absence of the Defendant. 2.In this inquiry as to damages hearing, I am aware of the following case, namely, SDL Hair Ltd v Next Row Ltd. [2014] EWHC 2084 (IPEC), where Hacon J. derived the following principles from authorities in relation to an inquiry as to damages:-
3.Insofar as they are applicable and bearing in mind that the present claim is a claim for breach of contract, I shall follow the above principles as much as possible in this inquiry hearing. Background 4.The Plaintiff carried on business as property developer and employed the Defendant since October 1991. In December 2013, the Defendant was employed by the Plaintiff as project manager. At that time, the Plaintiff formed the view that the Defendant had an attitude problem and decided to terminate his employment on mutually agreeable terms. The Plaintiff considered that an agreement was reached and on 14 December 2013, the Defendant served his last day of employment with the Plaintiff. 5.Very quickly thereafter on 16 December 2013, the Plaintiff discovered that certain data were deleted from the computer previously used by the Defendant. It was suspected that the Defendant deleted his working files regarding the construction project in STTL 420 situate at No.2 On Sum Street, Shatin, New Territories (“Project 420”) from his computer on the last day of his service on 14 December 2013. 6.In this action, the Plaintiff claims, inter alia, an injunction against the Defendant for using the deleted files. Further, the Plaintiff claimed, inter alia, damages to be assessed as a result of the acts of the Defendant. Liability was initially hotly contested by the Defendant. But he eventually conceded in his affirmation dated 11 September 2015 that he deleted the files by mistake. The Defendant stated that he pressed the button to empty the Recycle Bin believing that only personal stuff and unused material were deleted. He did not check the contents. He also said that he threw the external drive which contained the information of the Plaintiff into the sea on 16 December 2013. As the Defendant did not appear in this inquiry hearing, what he said in the witness statement and in his Affirmation must be taken with a grain of salt. As liability has already been conceded by the Defendant, it is not necessary for me to make any finding whether the Defendant was deleting the files from the computer by mistake. 7.The Plaintiff called 2 factual witnesses, namely, Mr Ku Yung Kan (“Mr Ku”), and Ms Maggie Lai Wai Man (“Ms Lai”). Mr Ku is employed by the Plaintiff as the head of the construction department, and the Defendant’s supervisor. He gave evidence to support the Plaintiff’s claim on quantum. On the other hand, Ms Lai was and is the Human Resources Manager of the Plaintiff. Her evidence mainly covered liability against the Plaintiff, and the Counterclaim by the Defendant with regard to his counterclaim for his termination benefits for the sum of HK$153,933.84. In the Order by Deputy High Court Judge Seagroatt dated 17 November 2015, the Defendant’s Counterclaim was discontinued. As the counterclaim as well as the liability in the main action were no longer at issue, her evidence was relatively brief. 8.It is not in dispute that the Plaintiff was the registered owner of the industrial building at No.2, On Sum Street, Shatin, New Territories (“Building”). Project 420 was to carry out certain renovation works to the Building so as to convert this industrial building into a commercial building. After completion, it would consist of 390 units and some 190 car park spaces. The Plaintiff intended to sell the commercial units after its completion of all renovation works. 9.In order to carry out Project 420, the Plaintiff appointed Jaco Limited, its subsidiary, as the employer in the building contract to manage Project 420. According to Mr Ku, Project 420 was in contemplation since June 2012. On 6 May 2013, a building contract was signed between Jaco Limited and Wang Yip Construction Co., Ltd (“Wang Yip”) (“Building Contract”), another subsidiary of the Plaintiff herein, as the main contractor. Both Jaco Limited and Wang Yip were not a party in this action. 10.The Building Contract provides that : ‑
11.It can be seen that renovation work in Project 420 was initially agreed to be completed within 29 months (from 1 July 2013 to 30 November 2015). The daily liquidated and ascertained damages of HK$15,000 per day would be payable by Wang Yip to Jaco Limited if any work shall remain incomplete by 30 November 2015. 12.Mr Ku stated in his witness statement that after signing the Building Contract, in October 2013 the Plaintiff decided to accelerate Project 420 with the aim to complete by May 2014. He said that there might be documents to confirm that the Project 420 be accelerated and the date for completion be pushed forward to May 2014. But the Plaintiff did not disclose any of those documents in this action. This is extremely unusual because: -
13.In this hearing for inquiry of damages, there were 12 lever arch files of documents running to 2,279 pages. However, apart from Mr Ku’s witness statements and his oral testimony, I was unable to find any documents which throw lights on the target date of May 2014 as the completion date in Project 420. It is not the Plaintiff’s case that all those documents confirming the acceleration of Project 420 to complete in May 2014 were deleted by the Defendant. I approach this aspect of the Plaintiff’s evidence with the greatest reservation. In the absence of documentary evidence to corroborate Mr Ku’s bare assertion, I do not accept the Plaintiff has proved that Project 420 was planned to accelerate the completion to finish in May 2014 on the balance of probabilities. I however find that the Plaintiff did accelerate the completion of the renovation work in Project 420, with the full knowledge that substantial extra costs would be incurred in so doing. Issues 14.The first issue which can be quickly disposed of is the date of assessing the parties’ contemplation for the purpose of measuring damages. In Chen & Another v Lord Energy Ltd (2002) 5 HKCFAR 297, the parties were involved in a dispute over the sale and purchase of a property and the trial judge ordered specific performance directing the vendors to assign the property to the purchaser within 28 days of the order. The vendors applied for stay of execution pending appeal, which the trial judge granted the application. Further stay was granted to the vendor by the Court of Appeal and Court of Final Appeal. Eventually, the Court of Final Appeal dismissed the vendor’s appeal, and the issue before the Court of Final Appeal was how the loss which the purchaser has suffered as a result of the stay of the order for specific performance granted by the Court of Appeal is to be assessed. It was held that: -
15.Accordingly, I form the view that the date on which the Defendant deleted the files, that is, 14 December 2013, would be the date on which the parties’ contemplation should be ascertained for measuring damages. 16.Another issue would turn on whether such damages as claimed by the Plaintiff are recoverable from the Defendant, which I shall come to below. Legal Principles 17.From the Statement of Claim, the Plaintiff’s claim is based on breach of contract. The basis of measuring damages for breach of contract is that the claimant is, as far as money can do it and subject to certain limitations, to be placed in the same position as if the contract had been performed. (Chitty on Contracts – Vol.1, General Principles, 32nd edition, § 26‑001). 18.The basic principle was recently authoritatively stated by the Court of Final Appeal in Richly Bright International Ltd v. De Monsa Investments Limited (2015) 18 HKCFAR 232. In order to do justice to this issue I quote extensively from page 242 thereof, as follows:-
19.Accordingly, insofar as remoteness of damages is concerned, I shall approach each of the heads of damages as claimed by the Plaintiff by applying the test set out in the Richly Bright International Ltd. decision. As explained above, I shall apply the test by adopting 14 December 2013 as the date for such purpose. 20.The Plaintiff’s claim for damages broadly consists of the following heads : ‑
Costs of Recovering deleted files: HK$5,586,680 21.Mr Ku stated in his statement dated 27 October 2015 that after the Defendant’s act, the Plaintiff was minded to appoint 5 persons to work together as a team to recover the deleted files. He explained in the witness box that these persons might be different persons, but they must be of the stated ranks. The number of months were also required, because the Plaintiff has planned Project 420 as early as June 2012 so he envisaged that 30 months would be required in order to recover the deleted files. The team to recover the deleted files would consist of the following: ‑
22.Mr Ku explained that this was the basis of the Plaintiff’s position in order to recover the deleted files. This was the Option A described in his witness statement of 27 October 2015. In this witness statement, Mr Ku postulated another method to claim the Plaintiff’s loss which he called Option B. However, when he gave evidence in Court, he explained that Option B was subsequently proven to be unworkable and the Plaintiff did not claim Option B as the viable alternative. Up to the date of this hearing, nothing has been done by the Plaintiff for the recovery of the deleted files. However, the Project 420 has since been completed on 22 October 2014, as certified by the Buildings Department’s letter bearing the same date. In other words, the Project 420 could be completed without the recovery of any of the deleted files. 23.When giving evidence in Court, Mr Ku confirmed that the deleted files by the Defendant would contain documents including building plans, tenders, drawings, minutes and emails communications at different stages. Some of the agreements with sub‑contractors were made orally and recorded in the files stored in the computer only. 24.As to the claim for the salary of 5 staff members, according to Mr Ku’s evidence, the idea to run Project 420 was formed in June 2012. The Defendant deleted the files in the Plaintiff’s computer on 14 December 2013. Taking the Plaintiff’s complaint to the highest, the Defendant could only have deleted the files which were contained in the Plaintiff’s computer for a period of not more than 19 months, from the date of having the idea of Project 420 in June 2012, to the date of the Defendant’s act in December 2013. Those documents were historical records, and save for the purpose of good housekeeping, the usefulness of recovering those data in the deleted files would be extremely little, now that the Project 420 had been completed without the recovery of the deleted files. When asked whether this is the Plaintiff’s case, Mr Ku maintained that it would be the Plaintiff’s position to employ 5 staff members to reconstruct all of the files deleted by the Defendant, 3 of them would have to work for 30 months and 2 of them for 3.5 months. 25.Mr Ku further explained in his evidence that the Plaintiff could have recovered the site meeting minutes from Jaco Limited as the employer, the drawings from the Buildings Department and the architect, and all site meeting minutes and variation orders from Jaco Limited. After all, it would be common sense that the computer could only store copies. Even if the computer files were deleted by the Defendant, copies would simply be reproduced by original documents kept by other parties working on Project 420 at the time. Whilst Mr Ku confirmed all this, he did not explain how the deletion of the files in the computer by the Defendant would necessitate the re‑construction of the deleted files by deploying the number of people to do the work, as claimed or at all. 26.Mr Chan, Counsel for the Plaintiff, cited the Aerospace Publishing Ltd. v. Thames Water Utilities Ltd. [2007] Bus LR 726. By the negligence of the defendant, the plaintiff’s premises was flooded with water causing irreparable loss to the archive and disrupted the claimant’s further plans for collating and publishing the archive. However, it has been noticeably clear that the Aerospace Publishing Ltd. decision was a case based on tort of negligence, and not on breach of contract as in the present case. The archive of photographs, documents and antiquated records relating to aviation and military history were unique of its kind. However, in the present case, the Plaintiff could have completed Project 420 without the exact 2200 odd deleted files. The Plaintiff could not state that those deleted files were unique of its kind which could not be obtained, replaced or reproduced from another sources. Rather, the contrary is confirmed by Mr Ku: the deleted files could indeed be made available from main contractor, architect and Buildings Department. Hence, the principles laid down in the Aerospace Publishing Ltd. decision that the appropriate measure of damages was the cost of reinstatement, and the costs of staff in salvaging and reorganizing the archive would be recoverable, are not applicable. 27.Mr Chan also relied on Harbutt’s Plasticine Ltd. v. Wayne Tank & Pump Co. Ltd. [1970] 1 QB 447. The factory was burnt down by flames through the tortious act of the defendant. The factory owner sued the defendant, was awarded with the full costs of restatement of the factory by the trial judge. On appeal, this award was affirmed. Nevertheless, the dicta of Lord Denning clearly stated that there should be a distinction between the subject matter being a factory and a second‑hand car. The claimant can go into the market and get another second‑hand car to replace it. For the destruction of the factory, the costs of replacement shall be allowed. For the reasons given above, this decision does not shed any lights to the present case as it is clear that the data in the deleted files from the computer can be sourced elsewhere as confirmed by Mr Ku. The cost of replacement principle expounded in Harbutt’s Plasticine Ltd. decision did not assist the Plaintiff in the circumstances. 28.I apply the test laid down in the Richly Bright International Ltd. decision. I am unable to accept that objectively speaking, it would be within the reasonable contemplation of the parties that the Defendant herein as of 14 December 2013 knew or ought to have known that the Plaintiff would have to incur costs in the tone of HK$5,586,680 to hire 5 staff members to reconstruct the files deleted by him, notwithstanding that copies of the deleted files could be made available through other sources, and that Project 420 had already been completed without those files. I formed the view that this claim as presented by the Plaintiff too remote and is therefore not recoverable, and I so find. Additional Manpower Costs 29.The Plaintiff’s claim under this head is initially for the sum of HK$1,666,595 as stated in Mr Ku’s First Witness Statement of 7 November 2014. At §8 thereof, he stated that the claim of HK$1,666,595 was based on the delay of 2.5 months and the average labour costs was HK$666,638 per month. He relied on a Manpower Expenditure Summary to support this. [C1/467] 30.In the Plaintiff’s Opening Submission, Mr Chan confirmed that the Plaintiff’s additional manpower costs was revised to HK$12,582,603. He then referred to certain parts of the 2nd Witness Statement of Mr Ku, from which the following could be deduced as the breakdown of the Plaintiff’s claim under this head :-
31.I shall deal with each of these items individually. HK$1,053,360.81: Staff Costs Increase 32.Mr Ku relied on a table [C1/536] in which he stated that during the period from January 2014 to November 2014, the Plaintiff employed 4 trainee engineers, 2 part‑time clerks and 2 safety officers to accelerate the renovation work in Project 420. He stated that the 4 trainee engineers were engaged solely because of the destruction of the files from the computer deleted by the Defendant. These trainee engineers were working solely on the recovery of the deleted files. In the table, it showed that there were wage payments each month for 4 trainee engineers ranging from HK$13,227 to HK$65,926.25. There is no further breakdown as to which trainee was entitled to wages individually. The period in which each of the trainees were employed was not stated. No employment contracts with any of the trainee engineers were produced. From the table it is not difficult to work out the calculation that the total salary paid to trainee engineers from January 2014 to November 2014 were HK$518,332.35, and the costs of part time clerks were at HK$22,230. 33.Mr Ku explained that part‑time staff and trainee engineers were required because of additional works to recover the time for the delay caused by the Defendant’s acts. He further explained that additional safety officers were required, because more workers (in the tone of 100 workers more) were engaged, therefore more safety officers would be required to ensure the safety of these additional workers. 34.According to the Plaintiff’s own case, the Plaintiff was driven to accelerate the completion of the Project 420 before the Defendant’s act. The additional manpower, especially the costs of the safety officer, strongly pointed towards the direction that these were caused by the Plaintiff’s eagerness to hasten the completion of the Project 420. As the Plaintiff had admitted through Mr Ku that the site meeting minutes, plans and drawings which were deleted by the Defendant’s act could be recoverable by alternate means, I am not convinced that the additional manpower costs as claimed was entirely caused by the Defendant’s act. 35.Applying the test in the Richly Bright International Ltd, decision, I find that viewing the matter objectively, it would be within the reasonable contemplation of the Plaintiff and the Defendant that on 14 December 2013, by deleting the files of the Plaintiff, the Defendant must have been aware that there would be inconvenience by the Defendant’s act of deleting files in the computer, and the Plaintiff would have to engage some extra manpower to work on Project 420 in the absence of the deleted files by contacting other involved parties such as the architect, the main contractor, the sub‑contractors, the site foreman, or even the Buildings Department. 36.However, I do not believe that the Plaintiff would have to engage 4 trainee engineers and 2 part‑time clerks to work full time for 11 months as claimed, just because of the Defendant’s acts. In the absence of the contracts of the trainee engineers and clerks, and without further evidence from any one or each of them as to what they did at the relevant time, I find that only certain parts of their works during the period would be attributable to the Defendant’s act. Taking a broad‑brush approach, I find that the Plaintiff suffered loss for the worth of HK$150,000 as a result of the Defendant’s act in hiring trainee engineers and part-time clerks. I make no award as to the costs of employing the safety officers, as I find that the Plaintiff would have to engage safety officers in the construction site anyway, especially when the Plaintiff had decided to accelerate the completion of Project 420. I find that the Plaintiff did not show by evidence that the Defendant’s act caused any delay for substantial period of time so that substantial amount of manpower to hire safety officers would be required as claimed. HK$1,440,000: Costs of Quantity Surveyor 37.Mr Ku explained that the Plaintiff originally employed quantity surveyors themselves. Because of the delay caused by the Defendant’s act, they needed to deploy additional quantity surveyors to work on Project 420 on an urgent basis. The quantity surveyors working on the Repulse Bay Project were sent to work on Project 420. The Plaintiff would have to engage Messrs. W T Partnership (HK) Limited (“W T Partnership”), the external quantity surveyor firm to carry out the quantity surveying work in the Repulse Bay Project. 38.The Plaintiff produced a copy of the agreement in writing to engage W T Partnership [C1/538]. But this was a letter with the letterhead of Winfield Investments Limited dated 20 October 2014, where the terms of the letter were agreed on 22 October 2014. Nowhere in Mr Ku’s witness statement did he try to explain the relationship between the Plaintiff and Winfield Investments Limited, and how the Plaintiff and the Defendant had a relationship with this company. Worse still, there is no evidence to connect the costs of appointing quantity surveyors with the Defendant’s act. 39.On Mr Ku’s own evidence, because the Plaintiff needed to accelerate the renovation work, there were plans for them to incur extra costs in order to drive the Project 420 forward. For reasons given in §§12 and 13 herein, I do not accept that Project 420 was targeted to be finished in May 2014. Further, even if the Plaintiff were to accelerate the completion in Project 420, that did not mean that they could place all expenses together and conveniently claim these as expenses for which the Defendant should be held responsible. The Plaintiff simply failed to prove how the sum of HK$1,440,000 was causally linked to the breach of contract on the part of the Defendant. I find that the Plaintiff would have to incur the fees to appoint quantity surveyors in order to accelerate the completion of Project 420 in any event. Such expenses for appointing quantity surveyors for another project would have no causal connection with the acts of the Defendant. 40.Further, I apply the test in Richly Bright International Ltd. decision and I find that viewing the matter objectively, it was not within the contemplation between the Plaintiff and the Defendant that because of the breach, the Defendant had to bear the costs of employing quantity surveyors by Winfield Investments Limited in another construction project. I do not accept that the Defendant, as of 14 December 2013, would have realized that such loss was sufficiently likely to result from the breach of contract to make it proper to hold that the loss flowed naturally from the breach or that loss of that kind should have been within his contemplation. I find that this item is therefore too remote and is not recoverable. HK$470,000 Electrical and Mechanical Consultant Costs 41.Mr Ku claimed that the Plaintiff hired the Electrical and Mechanical Engineer Consultant, JCL Consultants Limited (“JCL”) in early 2014 to assist the Plaintiff to assess thoroughly all the claims relating to electrical and mechanical (“E&M”) works, owing to the lack of the deleted files. He referred to a letter with the letterhead of Jaco Limited dated 15 March 2014 with enclosure to JCL. [C1/566] 42.The Plaintiff did not explain why the engagement fees for electrical and mechanical consultants were caused by the Defendant’s act. Mr Ku had already confirmed that the files deleted by the Defendant could be obtained by alternate means. If the Plaintiff’s case were that the E&M works were additionally required being extra costs as a result of the delay caused by the Defendant’s act, then the Plaintiff would know best how to present its case in order to discharge its burden of proof. The costs of retaining JCL were incurred on the face of it by Jaco Limited but the Plaintiff did not show that how such costs were related to and paid for by the Plaintiff. The Plaintiff did not show how the Defendant’s act would have caused delay, and thereby necessitated additional expenses of the E&M consultants fees. I find that the Plaintiff failed to discharge the burden of proof that the sum of HK$470,000 has causally linked to the breach of contract on the part of the Defendant. Further, I find that viewing the matter objectively, as of 14 December 2013 it was not within the reasonable contemplation of the parties for the Defendant to be held responsible for the fees engaging JCL and this claim is too remote by applying the test laid down in the Richly Bright International Ltd. decision. HK$1,635,132.60: Costs for Demolition Work 43.Mr Ku claimed that the Plaintiff incurred HK$1,970,130 being the extra costs paid for acceleration of works in his 2nd Witness Statement dated 27 October 2015. When he was giving evidence in the witness box, he submitted a table [C2/597‑A] to replace the previous one. He explained that he checked the figures again and amendments to the claim would be required. 44.Mr Ku set out in §42 of the 2nd Witness Statement of 27 October 2015 the following explanation: ‑
45.Mr Ku gave evidence to explain that in October 2013 the Plaintiff had decided to accelerate the Project 420 and they had the preparation to increase the budget by engaging more manpower in order to complete the Project 420 as soon as possible. The costs of demolition works as referred to in Mr Ku’s 2nd Witness Statement as Attachment “KYK‑17” [C2/596-605] were tables, certificates of completion of demolition work, and some receipts issued by Tak Shing Construction & Engineering Company presented to Wang Yip. The Plaintiff did not explain how these expenses incurred by Wang Yip would be the Plaintiff’s losses caused by the Defendant’s act apart from Mr Ku’s bare assertion. Mr Ku failed to explain how the files deleted by the Defendant would have caused the Plaintiff to engage additional expenses as claimed, and not by the Plaintiff’s own decision to accelerate the completion of Project 420. 46.I am unable to find how the files deleted by the Defendant would have caused delay, thereby necessitated acceleration of the work and hence additional expenses paid by the Plaintiff as claimed under this item. I refer to my previous finding that the Plaintiff had determined to accelerate the completion of the Project 420 and with the full knowledge that by doing so, there would be additional expenses for demolition. I find that the Plaintiff would have incurred the additional expenses for demolition work because of its decision to accelerate the completion of Project 420, which would have no causal connection with the Defendant’s act. 47.Further, I find that the Plaintiff’s claim for the costs of demolition work too remote in law by applying the test laid down in the Richly Bright International Ltd. decision, and is therefore not recoverable. I hold that viewing the matter objectively, the costs of demolition were not a loss of sufficiently likely to result from the breach of contract as of 14 December 2013 to make it proper to hold that the loss flowed naturally from the breach or that loss of that kind should have been within the Defendant’s contemplation. HK$6,791,152: Costs for Toilet fit‑outs 48.Mr Ku claimed in the 2nd Witness Statement of 27 October 2015 that the Plaintiff incurred HK$6,791,152 being the costs for toilet fit‑outs. Apart from his bare assertion, Mr Ku’s 2nd Witness Statement did not elaborate how this sum were the losses caused by the Defendant’s act. I find that the Plaintiff would have to incur the costs for the toilet fit‑outs, with or without the Defendant’s acts. The Plaintiff failed to prove that the costs for toilet fit‑outs would have any causal connection with the Defendant’s act. Apart from Mr Ku’s bare assertion, there is no evidence that the Plaintiff would have paid anything extra on toilet fit-outs caused by the Defendant’s act. 49.Further, I find that the Plaintiff’s claim for the costs of toilets fit‑outs too remote by applying the test laid down in the Richly Bright International Ltd. decision in law and is therefore not recoverable. I hold that viewing the matter objectively, the costs of toilets fit-outs as claimed were not a loss which the Defendant would, as of 14 December 2013, have realised that such loss was sufficiently likely to result from the breach of contract to make it proper to hold that the loss flowed naturally from the breach or that loss of that kind should have been within his contemplation. HK$857,961 Costs for drainage work 50.Mr Ku claimed in the 2nd Witness Statement of 27 October 2015 that the Plaintiff incurred costs for drainage work in the sum of HK$857,961. Mr Ku explained when he gave evidence in the witness box by saying that in Attachment 19 [C2/622], the Plaintiff contracted with and finally paid HK$4,483,164 to a plumbing sub‑contractor called Wing Fat Plumbing Limited (“Wing Fat”). The Plaintiff committed to contract with Wing Fat as they were in a hurry and without comparison. Later, the Plaintiff obtained better quotation from other sub‑contractor who offered to complete the same plumbing work for HK$3,625,204. The difference was HK$857,961 (HK$4,483,164 - HK$3,625,204). Mr Ku explained that the Plaintiff was making decision in short span of time because of the delay caused by the Defendant’s act. Therefore, the mistake made by the Plaintiff was caused by the Defendant’s act. 51.However, the Plaintiff did not elaborate how the Defendant’s act caused delay, thereby causing the Plaintiff to have incurred the difference. The Plaintiff could not blame the Defendant for his bad bargain, without ever showing how these 2 events were causally connected. I find that the Plaintiff failed to prove the difference for the costs of plumbing and drainage would have any causal connection with the Defendant’s act. Further, I find that the Plaintiff’s claim for the difference of the costs of plumbing and drainage as claimed too remote in law by applying the test laid down in the Richly Bright International Ltd. decision, and is therefore not recoverable. In my view, the difference of the costs of the drainage work which the Plaintiff claimed to have overpaid was caused by the Plaintiff’s own volition and was not a loss which the Defendant would, as of 14 December 2013, have realised that such loss was sufficiently likely to result from the breach of contract to make it proper to hold that the loss flowed naturally from the breach or that loss of that kind should have been within his contemplation. HK$1,873,670: direct financial loss 52.Mr Ku’s 2nd Witness Statement referred to a table [C2/708] setting out the calculation of interest actually received by the Plaintiff as from December 2014 to November 2015. Based on the same rate of income he made on the assumption that the Plaintiff could have completed the Project 420 as scheduled for June 2014. Mr Ku then compared the interest earned had the Project 420 been completed in June 2014 at HK$2,724,916, with the actual interest earned by the Plaintiff from December 2014 up to November 2015 at HK$851,246. Accordingly, the difference being the loss of interest would be HK$1,873,670 (HK$2,724,916 - HK$851,246). 53.For reasons given in §12 and §13 above, I rejected the Plaintiff’s claim that the target completion was accelerated to finish in May 2014, and this claim for interest based on completion in May 2014, and the units available for sale in June 2014, should fail. The original completion as set out in the Building Contract was scheduled for November 2015 and to put forward the completion by 18 months for a project which originally planned to last 28 months would be very significant changes. The Plaintiff simply failed to place any credible evidence to causally connect such changes to the Defendant’s act allegedly caused delay. 54.There are a number of assumptions made in the Plaintiff’s calculation for loss of interest. It has assumed that the Plaintiff could have sold the same number of properties in May 2014 for the units in the Building under Project 420 for the same price and at the same speed as they were sold in December 2014. It is assumed, as there is no evidence, on the price of the properties for sale set in May 2014 would have been the same in December 2014. The Plaintiff also made the assumption that even if the Project 420 could be completed in May 2014, the approval by the Buildings Department could also be obtained contemporaneously. In the volatile Hong Kong property market, these assumptions are simply rhetorical more than real. I am unable to accept that this is the proper basis to allow a claim based on such assumptions which the Plaintiff failed to lead sufficiently credible evidence to prove on the balance of probabilities. 55.More importantly, I apply the test in the Richly Bright International Ltd. decision, and I find that the Plaintiff failed to prove that viewing the matter objectively, it was within the Defendant’s contemplation that such loss should be the losses for which the Defendant should be held liable. I find that this head of claim is too remote and is therefore not recoverable. I hold that as of 14 December 2013, the Plaintiff’s claim for loss of interest was not a loss that the Defendant knew or ought to have known which flowed naturally from the breach or that loss of that kind should have been within his contemplation. HK$1,125,000: Third Party’s Claim and Indemnity 56.In Mr Ku’s first witness statement of 7 November 2014, he stated in §11 that the Plaintiff is obliged to pay a liquidated sum of HK$15,000 per day, should there be any delay beyond the completion date. The liquidated sum is thus HK$1,125,000 (HK$15,000 × 30 days × 2.5 months). 57.Under §22 of the Building Contract, it does provide the basis for payment of damages for non‑completion:‑
58.The appendix of the Building Contract set out the liquidated and ascertained damages under clause 22 was at the rate of HK$15,000 per day. 59.However, this sum of HK$15,000 per day of delay for liquidated and ascertained damages is payable by the main contractor, Wang Yip to the employer, Jaco Limited. This clause therefore did not support the Plaintiff’s claim that HK$15,000 per day is payable by the Plaintiff to the main contractor, or indeed to any other parties, should there be any delay. The Plaintiff would have no part to play under the Building Contract. Both Wang Yip and Jaco Limited are not parties in these proceedings. I find that this claim has not been proved. 60.In the opening, Mr. Chan indicated that the basis of the Plaintiff’s claim is to seek an indemnity against any claim by the third party for the delay caused by the Defendant. As illustrated in the preceding paragraph, the Plaintiff was not liable in the Building Contract for any liquidated or ascertained damages to any party. It was only the main contractor which should be responsible for any delay and pay liquidated or ascertained damages to Jaco Limited, the employer. The Project 420 had completed over 3 years and no documents were ever produced to this Court by the Plaintiff that there is any party who would make a claim against the Plaintiff, or for argument sake, Jaco Limited or Wang Yip. I am unable to think how the Plaintiff would be held liable to anyone under the Building Contract. At the end of his submission, Mr. Chan urged me to consider the losses of Wang Yip, Jaco Limited and the Plaintiff as the same entity as they were pretty much under the same “boss”. I am unable to accept this contention. I find that this claim for indemnity does not take off the ground. 61.Further, the Plaintiff’s claim for indemnity for third party claim also failed on the ground that it was too remote by applying the test laid down in the Richly Bright International Ltd. decision, in that viewing the matter objectively, the Plaintiff’s claim for indemnity against third party claim was not a loss that the Defendant knew or ought to have known which flowed naturally from the breach or that loss of that kind should have been within his contemplation. General Damages – loss of reputation 62.Very sensibly, at his opening Mr Chan confirmed that the Plaintiff no longer pursued its claim for any loss of reputation. Conclusion 63.I have come to the view that the Plaintiff is only successful in part for its claim against the Defendant for the reasons given above. Judgment is awarded in favour of the Plaintiff against the Defendant for the sum of HK$150,000. Interest is awarded on the Judgment sum at the rate of 1% above the prime rate announced by the HSBC for the period from the date of Writ of Summons to the date of Judgment, and thereafter at the Judgment rate until payment. As the Plaintiff is only successful in part in this inquiry, I make a costs order nisi that the Defendant do pay half of the Plaintiff’s costs in the inquiry as to damages and all costs previously reserved, with Certificate for Counsel, to be taxed on a party and party basis if not agreed, to be made absolute within 14 days. 64.I am thankful to Mr Chan for his assistance.
Mr Frederick H.F. Chan, instructed by Hon & Co., for the plaintiff The defendant was unrepresented and did not appear |
Cases cited in this judgment