Chun Wo Construction & Engineering Co Ltd and Others v. The Hong Kong Housing Authority
Read the full judgment text of CACV 338/2018 on BabelCite. This Court of Appeal judgment was delivered on 27 March 2019 before Hon Lam VP, Cheung JA, Yuen JA.
Civil procedure — Arbitration — Appeal on question of law against arbitral award — Leave to appeal under Arbitration Ordinance (Cap. 609) Schedule 2 s.6 — Tests for granting leave: 'obviously wrong' vs 'serious doubt' — 'One-off' contract vs standard terms — Contractual construction — Schedule of Rates dispute — Door window hinge replacement valuation — Arbitrator’s detailed reasoning upheld — Leave to appeal properly refused — Appeal against leave decision incompetent without leave — Satellite litigation discouraged. The plaintiffs challenged an arbitrator’s award favoring the defendant housing authority in valuing maintenance works replacing aluminium window hinges. Dispute centered on whether valuation should apply only certain rates (Rates 1 to 3) or all five contested rates (Rates 1 to 5) under the contract Schedule of Rates (SOR). The arbitrator found replacement work did not include ancillary repairs and limited payable rates to 1 to 3. The Court reviewed the test for granting leave to appeal under Cap. 609 Schedule 2 s.6, clarifying that for 'one-off' contracts like here, the 'obviously wrong' test applies and found no error in arbitrator’s award or Judge’s refusal of leave on that basis. A subsequent appeal by defendant against Judge’s grant of leave was held incompetent as no leave to appeal was obtained, and no statutory basis for such appeal existed. The Court emphasized deference to experienced arbitrators in contractual construction, the high threshold for leave, and discouraged satellite appeals that add costs without utility. Ultimately, both appeals were dismissed with costs ordered accordingly.
Legal issues: Appropriate test for granting leave to appeal under Section 6(4)(c) of Schedule 2 Arbitration Ordinance · Whether the Judge conflated the tests for leave to appeal · Application of principles of contractual construction on the arbitration award · Whether the monetary values of the rates were improperly ignored in the award · Competency of appeal against the judge’s leave decision under section 6(5) Arbitration Ordinance
Outcome: Both appeals dismissed; CACV 431/2018 dismissed for want of jurisdiction; CACV 338/2018 dismissed on merits
Cited by 4 cases · Cites 9 cases
|
CACV 338/2018 & CACV 431/2018 (HEARD TOGETHER) [2019] HKCA 369 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO. 338 OF 2018 (ON APPEAL FROM HCCT NO. 54 OF 2017) ________________________
________________________
________________________ IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO. 431 OF 2018 (ON APPEAL FROM HCCT NO. 54 OF 2017) ________________________
________________________
________________________ (HEARD TOGETHER)
________________________ J U D G M E N T ________________________ Hon Lam VP : 1.I respectfully agree with the judgment of Cheung JA and for the reasons he shall give, both appeals are dismissed and a costs order nisi as per [10] in this judgment. For my part, I wish to highlight the futility of CACV 431 of 2018. The subject matter of this appeal concerns the leave granted by the judge under Section 6(5) of Schedule 2 for an appeal to be brought to this Court. Whilst as a matter of jurisdiction in cases other than those brought under the statutory regime of the Arbitration Ordinance (for which different rules apply, see [9.5] and [9.6] below) it is open to this Court to re-visit a leave granted by the judge below (e.g. in a case where this Court dismissed a renewed application for leave on specific ground and revoked leave already granted below on some other grounds, see Chan Lap Kit v Yushun Technology Ltd [2018] 1 HKLRD 192), in most cases it would not be appropriate for an appeal to be brought against such grant of leave. In addition to the requirement of Section 14AA leave as discussed by my Lord at [9.4] below, arguments in an appeal of that nature are most likely to be overlapped with arguments to be canvassed in the appeal which had been brought pursuant to leave granted by the judge in the Court of First Instance. The two appeals are likely to be heard together and no advantage is gained by having the second appeal. In such circumstances, bringing another appeal against the grant of leave to appeal to this court only adds overall costs to the litigation process and rarely serves any good. In most cases, appeals of such nature are in substance satellite litigations which our Civil Justice Reform sought to discourage. Legal practitioners should reflect on the utility of a process before they advise their clients to embark on the same. Hon Cheung JA : I. The two appeals 2.1The arbitrator, Professor Reyes SC, gave an arbitral award in favour of the defendant. The plaintiffs sought leave to appeal on a point of law against the arbitral award from Mimmie Chan J. The Judge refused to grant leave (‘the refusal decision’). The plaintiffs then sought leave from the Judge to appeal against the refusal decision. The Judge granted leave (‘the leave decision’). 2.2Pursuant to the leave decision, the plaintiffs lodged their notice of appeal (CACV 338 of 2018). In the meantime, the defendant lodged an appeal against the leave decision (CACV 431 of 2018). Both appeals were listed for hearing before us. We dealt with CACV 431 of 2018 first and dismissed it. We reserved our decision in CACV 338 of 2018. I will now first give our decision in CACV 338 of 2018 and then my reasons for judgment in CACV 431 of 2018. II. The arbitration 1) Background 3.1The defendant managed various housing estates. It entered into 21 contracts with the plaintiffs by which the plaintiffs were required to carry out maintenance improvement and refurbishment works in the housing estates. From time to time, Work Orders would be issued by the defendant instructing the plaintiffs to carry out specific tasks. The tasks which were the subject matter of the arbitration were Work Orders for the replacement of the sliding window hinges which were used to affix aluminum window sashes to the window frames of the flats in the housing estates (‘the Relevant Works’). These hinges had to be replaced as a result of accidents of window sashes falling onto passing pedestrians. The hinges had become worn and fatigued by usage. 3.2The four steps in the procedure involved in replacing the window hinges were as follow :
3.3The contracts between the parties contained a Schedule of Rates (‘SOR’). The parties agree that the Work Orders should be valued pursuant to the SOR, but there is disagreement as to which specific rates in the SOR should be used in valuing the work. The plaintiffs consider that they should be valued by SOR Items 10183B, 10183C, 10184B, 10146A and 10147A (‘Rate 1’, ‘Rate 2’, ‘Rate 3’, ‘Rate 4’ and ‘Rate 5’) which are as follows :
3.4The defendant considered that only Rates 1, 2 and 3 are applicable. The arbitrator agreed and held that only Rates 1, 2 and 3 are applicable. 2) Contentions of the parties 3.5As summarised by the Judge, the contentions of the parties are as follows :
3.6The evidence adduced at the arbitration was that until November 2013, the defendant had applied Rates 1 to 5 in the valuation of the Relevant Works. The defendant, however, stated that the application of Rates 4 and 5 prior to November 2013 had been a mistake. It also stated that although different combinations of Rates 1 to 5 had been adopted, there is no evidence that all Rates 1 to 5 had been applied and paid in any one case. 3) The arbitrator’s decision 3.7The arbitrator identified Rates 1, 2 and 3 as falling under the section of the SOR headed ‘Ironmongery and fittings to metal windows and doors’, and that Rates 4 and 5 are in a section headed ‘Repairs, etc to metal windows and doors’. The section of the SOR which sets out ‘ironmongery and fittings to metal windows and doors’ specifically states that items of the metal windows include all ironmongery and fittings, and further states specifically that ironmongery and fittings to metal windows include ‘all drilling, tapping, riveting, welding, providing screws, rivets, cutting holes, mortices, slots, etc in metal frames’. 3.8The arbitrator gave three main reasons in favour of the defendant’s approach : (1) The Relevant Works are replacement rather than repair; (2) The removal and brief storage of the window sash in the course of such operation are merely temporary works which are not to be measured and valued separately. (3) There are anomalies in the plaintiffs’ construction of the SOR. 3.9The arbitrator explained :
3.10The arbitrator also dealt with other issues but these three reasons formed the foundation of his decision. III. Appeal on a point of law 1) The Arbitration Ordinance (Cap. 609) 4.1Section 5(1) of Schedule 2 of the Arbitration Ordinance (Cap. 609) provides that, subject to section 6 of Schedule 2, a party to arbitration proceedings may appeal to the Court on a question of law arising out of an award made in the arbitral proceedings. Section 6 of Schedule 2 provides that :
4.2The plaintiffs’ application for leave to appeal against the award on a question of law was made pursuant to section 6(1)(b) of Schedule 2. The question of law identified is whether on the proper construction of the SOR, the Relevant Works should be measured and valued under Rates 1 to 3 only, or under Rates 1 to 5 inclusive. 4.3The construction or interpretation of contract is traditionally classified as a point of law. As Lord Diplock pointed out in Pioneer Shipping Ltd v. BTP Tioxide Ltd. (The Nema) [1982] AC 724 at page 736, this classification is too well entrenched to be disturbed. 4.4In the present case, in respect of section 6(4), there is no dispute that criteria (a) and (b) have been satisfied. The issue before the Judge is in respect of criterion (c), namely, whether the decision of the arbitrator on the question is obviously wrong (‘the obviously wrong test’) or the question is one of general importance and the decision of the arbitrator is at least open to serious doubt (‘the serious doubt test’). 2) The cases 4.5The Judge referred to Swire Properties Ltd v Secretary for Justice(2003) 6 HKCFAR 236 on guidance for questions which are considered to be ‘of general importance’ and for the phrase ‘obviously wrong’ :
4.6The Nema is a case concerned with the United Kingdom Arbitration Act 1979. Section 1(3) provided for appeal to the High Court on any question of law arising out of an award on an arbitration agreement either with the consent of all the parties to the reference or with the leave of the Court. Section 1(4) further provided that :
4.7The discussion of a ‘one-off contract’ is found in the speech of Lord Diplock at 736 C :
4.8In respect of standard terms, Lord Diplock at 737 F explained :
4.9The Arbitration Act 1979 was replaced by the Arbitration Act 1996 where the provisions for leave to appeal against an arbitral award are similar but not identical to our current Arbitration Ordinance which came into effect on 1 June 2011. Section 69 of the Arbitration Act 1996 provides for appeal to the Court on the question of law arising out of an arbitration award on the agreement of the parties or with the leave of the Court. Section 69(3) provides for the criteria that are required for the granting of leave :
4.10As one can see from these provisions, the wording of the ‘obviously wrong’ test is the same as the Hong Kong provision of section 6 of Schedule 2. However, in respect of the ‘serious doubt’ test, our section 6(4)(c)(ii) omits the word ‘public’. The Hong Kong provision also does not have the words of section 69(3)(d). 4.11In CMA CGM SA v Beteiligungs‑KG MS “Northern Pioneer” Schiffahrtsgesellschaft mbH & Co and others (‘The Northern Pioneer’)[2003] 1 WLR 1015, Lord Phillips of Worth Matravers MR construed section 69(3)(c)(ii) of the Arbitration Act 1996. He held :
4.12Dealing with the strong prima facie case that Lord Diplock had advocated in The Nema, Lord Phillips held :
4.13Bokhary PJ in Swire Properties Ltd referred to what Lord Phillips said about the difference. He held that :
4.14Earlier, in Ha Hau Kwan Fong Mary v The Incorporated Owners of Golden Plaza, HCCT 9/2002, a case dealing with the repealed Arbitration Ordinance (Cap. 341), Ma J (as he then was) held that :
IV. The Judge’s refusal decision 5.The Judge held :
V. Principles on construction of contract 6.1The parties before the arbitrator agreed that operative principles for construing a contract are found in the judgment of Lord Neuberger PSC in Arnold v Britton [2015] UKSC 36 where he held :
6.2The arbitrator held that of the seven factors articulated by Lord Neuberger, the first four are relevant :
6.3In Arnold, Lord Hodge JSC further held :
6.4In Secretary for Justice v Joseph Lo Kin Ching (2015) 18 HKCFAR 169, Lord Walker of Gestingthorpe NPJ discussed the iterative process and at [31] he adopted the speech of Lord Mance in Re Sigma Finance Corp [2010] 1 All ER 571 at [12] :
6.5Lord Walker further held :
VI. The plaintiffs’ grounds of appeal 7.Mr Coleman SC (together with Mr Eric Chung and Ms Sheena Wong) for the plaintiffs advanced four grounds of appeal, namely, 1) the Judge wrongly found that the question was not one of general importance, and therefore wrongly held that the applicable test was whether the arbitrator’s decision was ‘obviously wrong’ instead of ‘at least open to serious doubt’; 2) she failed to apply the correct test for whether the arbitrator’s decision was ‘at least open to serious doubt’; 3) she failed to apply the correct principles for contractual interpretation in construing the five Rates in the contracts and failed to give consideration to the ‘values’ provided as part of the description of Rates 1 to 5 against the overall purpose, relevant background facts and commercial common sense; and 4) as a result, she failed to find that the arbitrator’s decision was ‘obviously wrong’ or ‘at least open to serious doubt’. VII. My view 8.1I will now discuss these grounds. 1) Ground 1 8.2The plaintiffs’ case is that the Judge was wrong to apply the ‘obviously wrong’ test instead of the ‘serious doubt’ test and in respect of the latter test, the Judge had adopted the wrong approach by requiring the presence of a ‘strong prima facie case’ as advanced in The Nema. 8.3To start with, the Judge considered both tests because the plaintiffs’ case below was that they could satisfy both tests for leave to be granted. I accept that it is no longer appropriate to rely on the strong prima facie case approach for the ‘serious doubt’ test as it was held in The Northern Pioneer to be inconsistent with the wording of the 1996 Arbitration Act. But even on that basis, this Court still needs to consider whether the Judge’s decision is plainly wrong as this Court had said in Maeda Kensetsu Kogyo Kabushiki Kaisha (also known as Maeda Corporation) v. China State Construction Engineering (Hong Kong) Limited and others (‘Maeda Corporation’), HCMP 1342/2017 :
8.4In the present case, I do not consider that the Judge had been plainly wrong on the result of the ‘serious doubt’ test because it is clear that the Judge in [22] of her judgment had accepted the correctness of the arbitrator’s decision although she did not have to go as far as that for the purpose of considering whether leave should be granted. On such basis, according to her judgment, the plaintiffs must have failed to satisfy the threshold of either of these two tests. This is what Mr Pennicott SC described as the ‘realty check’ of the case. 8.5However, as this is not an appeal proper of the arbitrator’s award but rather an appeal on the correctness of the refusal decision, I will first discuss whether this is a ‘one‑off’ contract situation for which the ‘obviously wrong’ test is relevant or whether it is a standard term situation for which the ‘serious doubt’ test is relevant. 8.6Mr Coleman emphasised that this dispute is not a ‘one‑off’ case but concerns the construction of ‘standard terms’ which could affect the valuation of tens of thousands of Works Orders, undertaken by the eight claimants under the 26 contracts the subject of the arbitrations (seven of them are plaintiffs in this appeal), as well as at least 13 other contractors (not party to the arbitration proceedings) under 30 other contracts, from 2003 to 2013 across major public housing districts in Hong Kong. 8.7Mr Coleman argued that the relevant SOR provisions and items ‘Take down and set aside for re‑use’ and ‘refix only’ under General Regulations (‘GR’)‑XI and GR‑XIII are found in all editions of the defendant’s SORs, and also apply to the valuation of the Works Orders undertaken by the 13 non‑party contractors in 30 other contracts. The Judge has also wrongly disregarded the factual finding of the arbitrator that even though the arbitrations referred only to a ‘relatively small number of Works Orders’, the difference in the parties’ valuation approaches may lead to ‘exceedingly large’ differences when the totality of the Works Orders (including those which are not the subject of this arbitration) are taken into account. 8.8He further argued that, in any event, prior to November 2013, the defendant had itself, in fact, applied each of Rates 1 to 5 the valuation of certain Works Orders: Yu 2nd paragraph 9.2. The defendant now states that its own previous applications of Rates 4 and 5 were a ‘mistake’ and seeks to counterclaim for repayment of all such sums: RA paragraphs 16 to 17. The correct determination of the question is, therefore, of great importance to the claimants and non‑party contractors. 8.9In my view, this is a ‘one‑off’ situation. I find the words of Lord Diplock on ‘one‑off contract’ to be instructive and apposite. The relevant contractual provisions in the present dispute do not possess an already established meaning for which each party was entitled to assume the other knew when he entered into the contract. Furthermore, it is also unlikely to be used in future by any other parties because the relevant provisions had been changed since early 2014 and the arbitrator’s award does not have any relevance to this specific type of contract after the change. While the arbitrator recognized that there may be a larger monetary value implication, this is only pertinent to the first criterion of section 6(4)(a) of Schedule 2, namely, it ‘will substantially affect the rights of one or more of the parties’ which is not an issue in dispute. There is no evidence as to the stand of the other parties who had not joined the arbitration. It is speculative to say that they would necessarily adopt the same views of the plaintiffs. Further, the arbitrator’s interpretation is only applicable to the replacement of aluminum window hinges and does not have a wider industrial application. In the words of Bokhary PJ in Swire Properties Ltd [29], this is a ‘dispute “in which the general market and the Commercial fraternity has no interest”. The resolution of a “one‑off” question of construction merely affects the rights and liabilities of the parties to the contract concerned. It will be of no general legal interest.’ 8.10This being the case the applicable test is the ‘obviously wrong’ test. 2) Ground 2 8.11The plaintiffs argued that the Judge had wrongly conflated the two tests. The plaintiffs criticised the following passage of her judgment as being wrong :
8.12As I agree with the Judge that the ‘obviously wrong’ test is the appropriate test, the argument now raised is academic. In any event, I do not regard the Judge had wrongly conflated the two tests. All that she meant is that the threshold for the ‘serious doubt’ test remains to be high by referring to Maeda Corporation at [18]. 3) Grounds 3 and 4 8.13Mr Coleman referred to Arnold and Joseph Lo Kin Ching and argued that the Judge had failed to undertake the requisite iterative process of contractual construction, and failed to realise that any reasonable man to whom the contracts were addressed would have understood the Relevant Works to be payable under Rates 1 to 5 inclusive (as opposed to Rates 1 to 3 only), and the arbitrator’s decision was obviously wrong or at least ‘open to serious doubt’. He argued that this is as a result of the Judge’s wrong application of the ‘serious doubt’ test, and therefore being wrongly confined to a ‘mere perusal of the award’ and wrongly thinking she was required to consider the award ‘quickly and easily, without meticulous legal argument’. 8.14I disagree. How a judge conducts the iterative process of contractual interpretation must be considered in the context of the case. This is not a case where the Judge was required to carry out the contractual interpretation afresh as if she was dealing with the matter for the first time. She already had the benefit of the analysis of a very experienced arbitrator who is also a former High Court judge. The arbitrator had set out the detailed arguments of the plaintiffs as to why Rates 4 and 5 should apply as well as the counter arguments of the defendant and he gave reasons for rejecting the plaintiffs’ arguments. The arbitrator was in as good a position as any judge to carry out the interpretation exercise. The words of Lord Diplock in The Nema at 736 D on giving recognition to the decision of an experienced arbitrator are again apposite. In the circumstances, in the context of this case, it is not necessary for the Judge to set out the full arguments of the parties afresh and carry out a detailed analysis of their respective cases. This is clearly not the function of a judge who presides on a leave application. The Judge clearly is entitled to give weight to the arbitrator’s analysis. 8.15Mr Coleman advanced three detailed arguments on why the arbitrator’s three reasons are obviously wrong (or at least open to serious doubt) (paragraphs 14 to 16 of the plaintiffs’ written submission). I have to say immediately that the plaintiffs’ arguments of the contractual provisions are repetitions of what had already been presented before the arbitrator which he had set out in detail in section III, Part A of his award. The arguments may be differently phrased but the substance is the same. The Judge addressed these issues in [22], [23], [24] and [25] of her judgment. I agree with her view. 8.16I will only need to address Mr Coleman’s argument that both the arbitrator and the Judge had ignored the monetary value specified for each of the five rates. He argued that by agreeing with the defendant’s interpretation, the arbitrator and the Judge’s decisions would lead to the result that: (i) when a contractor is ordered to take down and set aside a window sash (say, during ‘repairs’ work), he would be paid HK$45.22 under Rate 4; (ii) but if he were ordered to take down and set aside the sash and remove a pair of window hinges attached to the sash, he would only be paid HK$15.22 (HK$7.61 x 2) under Rate 2; (iii) and if he were instructed to take down and set aside the sash, and remove just one window hinge (say, because the other hinge is still in working condition), he would only be paid HK$7.6l under Rate 2. This is commercially absurd and could not be what a reasonable person would have understood the parties to mean when entering into the contracts. 8.17In respect of this specific argument that a relevant component, namely, the monetary value had been ignored by the arbitrator, it is plain that the plaintiffs had consciously decided at the hearing of the arbitration not to rely on the monetary value as a relevant part of their argument. This can be seen from the detailed submission of the plaintiffs summarised by the arbitrator in his award where the specific monetary value of the rates was not relied upon by the plaintiffs. The plaintiffs were represented by very experienced specialists in arbitration. If this matter had been raised and relied upon, one would have expected the arbitrator to have dealt with it in his award. This was not the case here. 8.18Bokhary PJ has given guidance in Swire Properties Ltd on how the Court should deal with new points of law not taken in the arbitration :
8.19The argument on monetary value was raised before the Judge. Plainly she did not consider it would have made any difference to the outcome of the case. She specifically rejected the notion that it would not make commercial sense if the plaintiffs are only to be paid under Rates 1, 2 and 3 because the core issue is whether the Relevant Works comprised of replacement and not repair :
8.20The Judge’s reference at [22] to the defendant’s argument on lack of commercial sense is in respect of the evidence of the defendant’s expert Mr Battersby on commercial valuation which the arbitrator had considered and decided to be not relevant. As such this is not a point that affects this appeal or the decision below. 8.21Accordingly, I would dismiss CACV 338/2018. Reasons for Judgment (CACV 431/2018) 9.1This can be dealt with shortly. 9.2Notwithstanding the refusal decision, the Judge gave leave to appeal. It is pertinent to remind ourselves of what Lord Phillips said in The Northern Pioneer :
9.3Lord Phillips at [15] also recognised that this is subject to the qualification that there may be situations where elucidation of the manner of the application of the statutory guidelines may call for leave to appeal to be granted. The present appeal does not fall within those situations. 9.4The defendant appealed against the leave decision. It did not obtain leave from the Judge or this Court before it lodged the appeal. In my view, the appeal is incompetent. The leave decision is an interlocutory judgment. Section 14AA of the High Court Ordinance (Cap. 4) mandates that leave be obtained in order to appeal against an interlocutory judgment (Bright Shipping Limited v Changhong Group (HK) Limited, CACV 576/2018 [2019] HKCA 246). Applying the ‘application approach’, the leave decision does not finally determine any issue on the substantive rights between the parties (Shell Hong Kong Ltd v Yeung Wai Man Kiu Yip Co Ltd (2003) 6 HKCFAR 222 and B + B Construction Ltd v Sun Alliance & London Insurance (2000) 3 HKCFAR 503). 9.5What is more important is that there is simply no provision for an appeal against the decision of a judge granting leave to appeal against the earlier decision where she had refused leave to appeal on the arbitral award. Section 14(3)(ea)(viii) of the High Court Ordinance (Cap. 4) provides that :
9.6Section 6 of Schedule 2 is the comprehensive provision on granting leave to appeal against an arbitral award on a question of law. Whilst section 6(5) allows an appeal (by leave) from a decision of the Court granting or refusing leave to appeal from such an arbitral award, there is no provision for an appeal against the further leave decision made in respect of the earlier decision of granting or refusing leave to appeal against the arbitral award. In the absence of any express statutory provision, there is no jurisdictional basis for an appeal under CACV 431/2018 to be lodged. VIII. Costs 10.I would give an order nisi that the plaintiffs are to pay the defendant’s costs of the appeal in CACV 338 of 2018 and the defendant is to pay the plaintiffs’ costs of the appeal in CACV 431 of 2018 with a certificate for two counsel. Hon Yuen JA : 11.I agree with Cheung JA’s judgment and Lam VP’s observations.
Mr Russell Coleman SC, Mr Eric Chung and Ms Sheena Wong, instructed by Pinsent Masons, for the 2nd, 3rd, 5th and 7th Plaintiffs Mr Ian Pennicott SC, instructed by Holman Fenwick Willan, for the Defendant | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under CACV 338/2018