Maeda Kensetsu Kogyo Kabushiki Kaishaalso known as Maeda Corporation and Another v. Bauer Hong Kong Ltd
Read the full judgment text of HCCT 4/2018 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 9 April 2019 before Hon Mimmie Chan J in Chambers.
Construction contract dispute over subcontractor's claims for additional payment for unforeseen ground condition variations. The Plaintiffs, main contractors for the MTRC project, subcontracted diaphragm wall works to the Defendant. The Defendant claimed entitlement to additional payment based on variations under Clause 21 notice provisions and valuation under Clause 19 of the Sub-Contract. The court held the notice requirements in Clause 21—comprising timely notice of intention and detailed notice with the contractual basis—are strict conditions precedent. The Defendant's failure to strictly comply with Clause 21.2 invalidated entitlement to claims on a new contractual basis ('like rights'), rendering the Arbitrator's allowance of such claims legally incorrect. On valuation, the court accepted the Arbitrator's methodology valuing variation by cost plus overheads and profits, including notional costs for plant not actually used, as a fair, reasonable contractual valuation within the permissible range of arbitral decisions. The appeal was therefore allowed on the notice compliance issue and dismissed on the valuation issue. Costs were awarded 50-50 to the Plaintiffs and Defendant respectively.
Legal issues: Notice compliance under Clause 21 · Valuation of variation under Clause 19
Outcome: Appeal allowed on the first question of law concerning notice compliance; appeal dismissed on the second question of law concerning variation valuation.
Cites 3 cases
|
HCCT 4/2018 [2019] HKCFI 916 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO 4 OF 2018 ______________
______________
______________
_______________ J U D G M E N T _______________ Background 1.On 30 August 2018, I granted leave to the Plaintiffs to appeal against the Second Interim Award of the Arbitrator published on 3 January 2018, as corrected on 3 March 2018, on two questions of law:
2.The abbreviations set out in my Decision of 30 August 2018 are adopted. 3.This is the substantive appeal against the Award on the two questions of law identified. As such, the Court is to decide the questions of law on the basis of the findings of fact in the Award (section 5 (3) of the Schedule to the Ordinance). In deciding the questions of law, section 5 (4) of the Schedule expressly states that the Court must not consider any of the criteria set out in section 6 (4) (c) (i) or (ii) of the Schedule (ie the criteria of “obviously wrong” or “at least open to serious doubt”). 4.On behalf of the Defendant, it was emphasized that the Arbitrator’s findings on law, as to the construction, effect and requirements of Clause 21, are made on the basis of his findings of fact, as to the time when and the factual circumstances in which the ground conditions claims became apparent, how the impact of the ground conditions was realized by the parties, and the extent of the Plaintiffs’ knowledge of these ground conditions. An arbitrator’s findings on facts are assumed to be correct and are not to be revisited. Questions of law are to be decided on the basis of the findings of fact in the award (section 5 (3) of the Schedule to the Ordinance). The Defendant submits that the proper test on an appeal on a question of law is to consider whether interference with the arbitrator’s award is necessitated because the arbitrator had obviously misdirected himself in law, by invoking legal principles which were self-evidently incorrect, and alternatively, the Plaintiffs must establish that although the law stated was correct, the decision reached was one that no reasonable arbitrator could reach (Kwan Lee Construction v Elevator Parts Engineering [1997] HKLRD 965 at 971). 5.In Cosemar SA v Mariamararna Shipping Co Ltd (The “Matthew”) [1990] 2 Lloyd’s Rep 323, the Court held that for an appeal to succeed on a mixed question of fact and law, it has to be shown that the decision of the arbitrator was outside the permissible range of solutions which were open to him. 6.The case of Kwan Lee Construction Co Ltd v Elevator Parts Engineering Co Ltd [1997] HKLRD 965 concerned an application for leave to appeal against an arbitral award. However, in the judgment of the Court of Appeal, His Lordships referred to the function of the court to which an appeal on the question of law is brought. Both Mayo JA and Litton VP cited Pioneer Shipping v BTP Tioxide [1982] AC 724, and reference was made to the speech of Lord Radcliffe in Edwards v Bairstow [1956] AC 14:
Lord Denning’s summary in Edwards v Bairstow was also referred to, that to justify interference with an arbitrator’s award, it must be shown that the arbitrator had misdirected himself in law, or that the decision was such that no reasonable arbitrator could reach. The notice compliance question 7.By way of quick recap, the Plaintiffs in this case were the main contractors under the Main Contracts with the MTRC as Employer, to construct tunnels for the Hong Kong to Guangzhou Express Rail Link. The Plaintiffs subcontracted the diaphragm wall works under the contracts to the Defendant. Disputes arose which were submitted to arbitration initiated by the Defendant, and this led to various awards which have been made. The Defendant’s primary case in the Arbitration was that the unforeseen ground conditions gave rise to a variation of the scope of works under the Sub-Contract, so as to entitle the Defendant to claim additional payment under the express variation provisions. In the alternative, the Defendant made a “like rights” claim under sub-clause 1 of S-CC 21.1 of the Sub-Contract (“Clause 21”). 8.In the Award, the Arbitrator referred to the “ground conditions claims” made by the Defendant in the Arbitration. At paragraph 164, the Arbitrator described the Defendant’s primary case, as follows:
9.The Arbitrator rejected the Defendant’s primary claim of variation. At paragraph 177 of the Award, the Arbitrator states:
10.The Arbitrator then proceeded to consider the claims made by the Defendant to see whether the different conditions said to have been encountered differed either from the geotechnical baselines or from the conditions which could reasonably have been foreseen by an experienced contractor, and made different findings. At paragraph 321 of the Award, he concluded:
Clause 21 deals with service of notice of claims, and clause 14 deals with revision of the date for completion of the Contract Works. 11.At paragraph 300, the Arbitrator repeated the findings he had made in the First Award on the notice provisions:
12.The Arbitrator then considered Clause 21. At paragraph 322 of the Award, the Arbitrator states:
13.After considering the evidence on the meetings held on 27 and 28 July 2011, the Claim Notices sent by the Plaintiffs to MTRC on 27 July 2011, and the letters from the Defendant to the Plaintiffs of 1 August, 2 August and 10 August 2011, the Arbitrator first found that the Defendant had given the notice required under Clause 21.1. The Arbitrator considered that: (1) at the meeting on 27 and 28 July 2011, the Defendant had explained to the Plaintiff that the main cause of the slow progress of works was the additional quantity of toe-in rock which had to be excavated; (2) the Plaintiff’s Claim Notices of 27 July 2011 to MTRC had referred to the delay and disruption to the Works by adverse physical conditions, and that the event giving rise to the claim was: “The existing level of Cat 1 (c) and Cat 1 (d) rock obtained for Granodiorite rock to be encountered in the excavation … obtained from pre-drilled boreholes indicate that the levels are generally higher than the corresponding Baselines for rock levels included in the GBR”; and (3) the Defendant had referred in the letters of 1 and 2 August 2011 to an increase in quantity and quality of rock excavation, and this had to be read against the background knowledge which the Plaintiffs had at the time. 14.The Arbitrator then went on to consider whether the Defendant had given the appropriate notice under Clause 21.2. In this context, the Arbitrator pointed out that he had raised in closing submissions the question of “whether the contractual basis of the claim made under Clause 21.2 had to be the same as the contractual basis of the claim made in the arbitration”. At paragraph 332, the Arbitrator then stated:
15.The Defendant’s letter to the Plaintiffs of 1 August 2011 (held by the Arbitrator to be one of the notices under Clause 21.1) referred to the following:
16.The other letter, of 2 August 2011, which was found to comprise the notice under Clause 21.1 stated the following:
17.Essentially, the Arbitrator’s finding is that the appropriate Clause 21.2 notice had been given, despite the fact that the Defendant had made its claims in its letters of 1, 2 and 10 August 2011 on the basis of a Variation or Sub-Contract Variation (under Clause 21.1.6), and not on a “like rights” basis under Clause 21.1.1. The Arbitrator made it clear in the Award that the claim allowed in the Arbitration is a new legal basis, but that the Defendant was not precluded under Clause 21.2 to pursue a different contractual or legal basis. This is reflected in paragraphs 333 and 334 of the Award:
18.With respect, in coming to such a conclusion, the Arbitrator failed to pay heed and give effect to the express provisions of Clause 21.2, which is clearly stated to be a condition precedent for any claim to additional payment or loss and expense, and is required by the express provisions of clause 21.3 to be “strictly complied with”. 19.Clause 21 is set out below:
20.The claim pursued by the Defendant in the Arbitration, and the subject matter of the Award and the present appeal, is a claim for additional payment or loss and expense pursuant to “any circumstances or occurrence as a consequence of which the Contractor is entitled to additional payment or loss and expense under the Main Contract”, under Clause 21.1.1. Notice of intention to make such a claim must, under Clause 21.1, be given “as a condition precedent to (the Defendant)’s entitlement to such claim”. 21.Clause 21.2 expressly provides that, “as a condition precedent to any entitlement”, if the Defendant wishes to maintain its right to pursue a claim for additional payment or loss and expense under Clause 21.1, the Defendant “shall” within 28 days after giving notice under Clause 21.1 submit in writing (under clause 21.2.1) “the contractual basis together with full and detailed particulars and the evaluation of the claim”. (Emphases added) 22.Clause 21.3 clearly states that the Defendant “shall have no right” to any additional or extra payment, loss and expense, under any Clause of the Sub-Contract or at common law “unless Clauses 21.1 and 21.2 have been strictly complied with”. 23.In my view, there can be no dispute, and no ambiguity, from the plain and clear language used in Clause 21, that the service of notices of claim in writing referred to in Clause 21.1 and 21.2 are conditions precedent, must be “strictly” complied with, and failure to comply with these conditions will have the effect that the Defendant will have “no entitlement” and “no right” to any additional or extra payment, loss and expense. 24.On behalf of the Defendant, it was argued that Clause 21 is in substance an exclusion or time-bar clause, and such clauses are strictly construed. Leading Counsel for the Defendant referred to Keating on Construction Contracts:
25.As recognized in the above cited passage, it is only in the event of ambiguity that a narrower construction may be applied. As the court made clear in Waterfront Shipping Co Ltd v Trafigura AG [2007] EWHC 2482 (Comm), the words in a time-bar provision must be given their ordinary and natural meaning, notwithstanding that it must be clear and unambiguous if effect is to be given to it. At paragraph 16 of the judgment, Gloster J stated in Waterfront Shipping:
Gloster J explained at paragraph 17 of his judgment that the commercial purpose of such clauses is to achieve finality, citing The Yellow Star [2000] 2 Lloyd’s Rep 637 at 641. 26.Clause 21 of the Sub-Contract is in my view clear and unambiguous in its provision and requirement for written notices to be served as a condition precedent to any claim or entitlement of the contractor. The Defendant argued that the ambiguity or uncertainty arises in relation to the requirement under clause 21.2.1 to state “the contractual basis” of the contractor’s claim for additional payment, loss and expense. The Arbitrator appears to base his findings on the fact that notice had been adequately given to the Plaintiffs, at the meetings and in the August correspondence, of the “ground conditions” encountered by the Defendant, and the fact that there was a substantial increase in the quantity and quality of the work encountered. He made it clear that the Defendant’s claims made in the Arbitration were on a “new legal basis” or “a different contractual basis”, compared to the basis referred to in the August correspondence comprising the Clause 21.1 notice. Yet, the Arbitrator considered that as the Plaintiffs were able in this case to notify MTRC in the Claim Notices of delay and disruption to the Works by adverse physical conditions, the principal purpose of Clause 21 - to enable the contractor to know the factual basis for the claim so that it can assess it and decide what to do - had been complied with. 27.Again, with due respect to the Arbitrator, what the Defendant had done by service of the letters of 1, 2 and 10 August 2011 was simply to give notice of the ground conditions encountered at the site, and the additional quantities and quality of the rock to be excavated. At most, these form the factual basis which may, or may not, give rise to a claim under the Sub-Contract. The facts may result in different consequences and give rise to different rights and entitlement of the Sub-Contractor. Clause 21.1 itself envisages different bases for claims of additional payment or loss and expense: namely, circumstances as a consequence of which the Contractor is entitled to additional payment or loss and expense under the Main Contract; alleged breach of the Sub-Contract, delay or prevention by the Contractor; claim for discrepancy between Sub-Contract drawings and documents; any claim under common law; extension of time granted; and/or any Variation. 28.Clause 21.2 requires the Defendant, again as a condition precedent, to submit “the contractual basis”, together with the detailed particulars and evaluation of the claim which the Defendant wished to pursue after the service of the Clause 21.1 notice. The sub-clause refers not only to the submission of the detailed factual particulars, but “the contractual basis” together with the full detailed particulars. What is required under Clause 21.2 therefore must be the basis which the Defendant claims it is entitled under the Sub-Contract to maintain and pursue its claim, by reason or as a result of the factual circumstances which have arisen. There may be one, or more, contractual bases, which can be stated in the Clause 21.2 notice, but the “contractual basis” under Clause 21.1 is one or more of the different causes or events set out in Clause 21.1.1 to Clause 21.1.6 as giving rise to a claim. 29.The August letters found by the Arbitrator to constitute the notices under Clause 21.1 state the factual basis of changed ground conditions, and further state the contractual basis of the Defendant’s claims to be Variations. There is no basis to find that the Defendant had complied strictly with Clause 21.2.1, in relation to any “like rights” claim made under Clause 21.1.1 and maintained under Clause 21.2. As such, by operation of Clause 21.3, the Defendant should have no right to the additional extra payment, loss and expense claimed. 30.The Arbitrator pointed out that it was unrealistic to expect a party to finalize its legal case within a relatively short period of time and to be tied to that case through to the end of an arbitration. As Leading Counsel for the Plaintiffs pointed out, the Defendant had 42 days from the event or occurrence giving rise to the claim to serve the notice required under Clause 21.2. That is not an unrealistic timeframe to identify the contractual basis of a claim. 31.In any event, however much sympathy the contractor may deserve, Clause 21 employs clear and mandatory language for the service and contents of the notices to be served, with no qualifying language such as “if practicable”, or “in so far as the sub-contractor is able” (cf Multiplex Construction (UK) Ltd v Honeywell Control Systems (No 2) [2007] 111 Con LR 78). As the passage in Keating on Construction Contracts recognizes, exemption clauses in construction contracts should be seen as part of the contractual apparatus for distributing risk. There is commercial sense in allocating risks and attaining finality by designating strict time limits for claims to be made and for the contractual basis of claims to be specified. In particular, the language used in Clause 21.1 is in my view clear on its plain reading, and the decisions in Rainy Sky SA v Kookmin Bank [2011] UKSC 50 and Arnold v Britton [2015] AC 1619 highlight the importance of the language used in the provision to be construed, notwithstanding the need to read such language in the proper factual and commercial context. There is no basis for a court or tribunal to rewrite the Sub-Contract or Clause 21 for the parties after the event. 32.If, on the facts of a particular case, a claim of waiver or estoppel may be made as a result of the way in which the parties had conducted themselves in relation to a claim or claims made and notified, that may well be pleaded and raised in the Arbitration but it should not affect the construction of a contractual provision which is clear and unambiguous on its face as to its requirements and the effect of non-compliance with its requirements. 33.I come to the conclusion that on proper construction of Clause 21 of the Sub-Contract, the Defendant had failed to give proper notice under Clause 21.2, and that the Arbitrator’s decision to allow the Defendant’s claim of “like rights” was wrong in law. The valuation of variation question 34.The Defendant contended in the Arbitration, and the Arbitrator accepted, that the deferment of the Area 1a panels for the diaphragm wall constituted a variation under the Sub-Contract (“Variation”). The Arbitrator proceeded to assess the value of the Variation, including the Defendant’s claim for standby of the plant and equipment required for the diaphragm wall for the period from 19 May to 4 July 2012. 35.The relevant contractual provision for valuation is S-CC 19 of the Sub-Contract (“Clause 19”), which is set out below.
36.Notwithstanding the fact that, as the Arbitrator found (in paragraph 672 of the Award), the plant and equipment in question was in storage during the relevant period and was not in use, the Arbitrator valued the Variation on the basis of “cost plus OH&P (overheads and profit)” (paragraph 679 of the Award), and accepted the cost, OH&P figure of HK$3,991,333 on the expert evidence adduced by the Defendant. 37.According to the Plaintiffs, the Arbitrator was in error to include as “cost” an amount not actually incurred by the Defendant, when the Arbitrator stated that he was using a “cost plus” valuation approach (paragraph 679 of the Award). 38.The Plaintiffs pointed out that Clause 19 provides in essence for “fair valuation”, but allowing the Defendant to recover a considerable sum for the value of the plant which the Defendant did not own and did not actually incur any costs nor make any payment for, together with overheads and profit, results in a windfall for the Defendant which is not fair to the Plaintiffs. The Plaintiffs emphasized that the equipment was in storage, was not operating at all, and that it would not cost anything to the Defendant, for the purposes of valuation. 39.Both the Plaintiffs and the Defendant referred to various legal authorities and text books in support of what they contend to be the correct method of valuation, but it appears from these authorities that there is no fixed rule as to how variations should be valued. 40.The Plaintiffs rely on Max Abrahamson’s Engineering Law and the ICE Contracts, 4th Edition, and contend that a “fair valuation” normally means cost plus a reasonable percentage for profit. Reliance is also placed on the judgment in Henry Boot Construction v Alstorm Combined Cycles Ltd [1999] BLR 123 at 137, where it is stated:
41.In Floods of Queensferry Ltd v Shand Construction Ltd [1999] 319 at 324, the same judge stated:
42.It should be borne in mind that under the contractual framework provided for in Clause 19, for any work added which is not the same or of a similar character or is not executed under similar conditions to work priced in the Sub-Contract, the value of the variation is to be ascertained at “a rate or price based on the Contract Rates so far as may be reasonable, failing which, at a rate or price agreed between the parties as being a fair and reasonable rate or price”. Under Clause 19.1.2, if the parties are unable to agree “a fair and reasonable rate or price”, the final rate or price is to be agreed or determined under the dispute determination. 43.At paragraph 4-037 of Keating on Construction Contracts 10th Edition, the learned author stated, in the context of assessment of “a reasonable sum”:
44.In the case of Laserbore Limited v Morrison Biggs Wall Limited [1993] Lexis Citation 2055 25th of August 1993, the Court construed an agreement to “reimburse” the contractor “fair and reasonable payment for all works executed and agreed” as meaning a liability to pay the contractor costs plus profit and overheads. On assessment of the amount payable, the plaintiff-contractor’s expert attempted to assess “reasonable rates” while the defendants’ expert considered the matter on a “costs plus” basis. In deciding the “fair and reasonable payment” to which the contractor is entitled, the court referred to the statement in the 10th edition of Hudson’s Building and Engineering Contracts:
45.In Laserbore, the judge considered that the better approach (citing Keating on Building Contracts and Greenmast Shipping Co v Jean Lion et Cie (The Saronikos) [1986] 2 Lloyd’s Rep 277 at 279) was to ask, “What would be a fair commercial rate for the services provided?” Referring to the “reasonable rates” basis and the “costs plus” basis of the experts, the judge then stated:
46.Leading Counsel for the Defendant emphasized that valuation, as opposed to assessment of damages, is a contractual entitlement and does not require proof of loss. He referred to paragraph 298 of the judgment in Floods of Queensferry, where the judge stated:
47.The Defendant further relies on Sergeant and Wieliczko’s Construction Contract Variations, 2014 Edition, where the authors state at paragraphs 11.78:
48.The learned authors conclude at paragraph 11.90 as follows:
49.I accept the submissions made on behalf of the Defendant, that the Arbitrator’s decision on the valuation of the Variation is a mixed question of law and fact. The Arbitrator received and considered evidence from the parties and their experts on the nature of the work involved, and the costs and value asserted by the Defendants and examined by the Experts, and concluded on all the evidence available before him that the quantification of HK$3,991,333 represents the “fair and reasonable rate” to be decided and allowed under Clause 19. He stated at paragraph 684 of the Award:
50.On review of the authorities, it cannot be said that the Arbitrator had misdirected himself in law, or that his decision was outside the permissible range of solutions which were open to him (Cosemar SA v Mariamararna Shipping Co Ltd (The “Matthew”) [1990] 2 Lloyd’s Rep 323). Disposition 51.The appeal on the first question of law on notice compliance is allowed. The appeal on the second question of law on variation valuation is dismissed. 52.A fair costs order nisi would be for the Defendant to pay to the Plaintiffs 50% of the costs of the appeal.
Mr Peter Clayton SC, instructed by Pinsent Masons, for the 1st and 2nd plaintiffs Mr Anthony Houghton SC and Mr James Niehorster, instructed by Bryan Cave Leighton Paisner LLP, for the defendant | |||||||||||||||||||||||||||||||
Cases cited in this judgment
Further hearings and rulings under HCCT 4/2018