P v. C
Read the full judgment text of HCCT 27/2019 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 29 October 2019 before Hon Mimmie Chan J in Chambers.
Arbitration — Extension of Time (EOT) — Condition precedent notice requirement — Contract construction — Risk allocation for defective building fabric — The Plaintiff applied for leave to appeal against certain legal questions arising from an Interim Award in an arbitration concerning renovation works on a Wanchai building. The three issues were whether the Defendant was entitled to EOT for delay during the KC period, whether the Defendant’s loss and expense claim was time-barred for non-compliance with clauses 28.1 and 28.2 of the Contract, and the proper construction of contract provisions allocating responsibility for window openings and their reconstruction. The Court held the arbitrator’s findings on EOT were not obviously wrong, as factual findings on overlapping delays and liability by the Plaintiff were conclusive. On the time bar question, the Court found the arbitrator properly construed the notice requirements broadly, accepting the Defendant’s letters complied with Clause 28, making the appeal ground untenable. On risk allocation, the Court found the arbitrator reasonably interpreted contract language limiting the Defendant’s design responsibility to removal and making good existing openings, placing risk of fragile and deteriorated building fabric on the Plaintiff. The Court refused leave to appeal on all questions, ordering the Plaintiff to pay costs with certificate for counsel.
Legal issues: EOT Question · Time Bar Question · Risk Allocation Question
Outcome: The Plaintiff’s application for leave to appeal on the three identified questions is refused.
Cited by 4 cases · Cites 3 cases
|
HCCT 27/2019 [2019] HKCFI 2625 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO 27 OF 2019 ______________
________________________
________________________
______________ D E C I S I O N ______________ Background 1.This is an application made by the Plaintiff for leave to appeal against the Interim Award of the Arbitrator published on 10 April 2019 (“Award”), in an arbitration in Hong Kong relating to the renovation and conversion of a building in Wanchai (“Arbitration”). The application is made pursuant to s 6 (1) (b) of Schedule 2 (“Schedule”) to the Arbitration Ordinance (“Ordinance”), and 3 questions of law are identified for the intended appeal. There is no dispute that the Schedule applies, as the agreement between the parties provides for the Arbitration to be domestic, and for the HKIAC Domestic Arbitration Rules to apply to the Arbitration. 2.Under s 6 (3) of the Schedule, the Court “must” determine an application for leave to appeal without a hearing unless it appears to the Court that a hearing is required. Under s 6 (4), leave to appeal is to be granted only if the Court is satisfied that (a) the decision of the question will substantially affect the rights of one or more of the parties; (b) the question is one which the arbitral tribunal was asked to decide; and (c) on the basis of the findings of fact in the award, the decision of the tribunal on the question is “obviously wrong”; or the question is one of general importance and the decision of the tribunal is “at least open to serious doubt”. 3.Pursuant to directions of the Court, written submissions were filed on behalf of the parties in support of and in opposition to the application. The Court further directed that no hearing is required, all in line with the objectives set out in s 3 of the Ordinance. 4.It has to be borne in mind that an application for leave to appeal on a question of law arising out of an award is a filtering process. As highlighted in the decision of Mustill J (as His Lordship then was) in Vinava Shipping Co Ltd v Finelvet AG (The “Chrysalis”) [1983] 1 Lloyd’s LR 503, the court at the first stage, of the application for leave, gives effect to the policy whereby “the interests of finality are placed ahead of the desire to ensure that the arbitrator’s decision is strictly in accordance with the law.” As His Lordship explained:
5.The judgment in The Chrysalis also contains a helpful summary on the 3 stages of an arbitrator’s process of reasoning, with the reminder that only the second stage of the process is the proper subject matter of any appeal on law:
6.The Plaintiff and the Defendant in this case had entered into an agreement (“Contract”), whereby the Plaintiff engaged the Defendant as the main contractor to carry out renovation and alteration works (“Works”) for a building in Wanchai, Hong Kong. Commencement of the Works was on 1 November 2012, with a date for completion of 26 September 2013 under the Contract. The Works were significantly delayed and handed over to the Plaintiff on 31 March 2015, at which point the Defendant vacated the site. 7.The disputes referred to arbitration pursuant to the Contract related to the Defendant’s claims of payment for work done and materials supplied under the Contract, extensions of time, and loss and expenses or alternatively damages arising from delay. By way of counterclaim in the Arbitration, the Plaintiff sought damages for defects, contra charges, liquidated damages for the Defendant’s failure to complete the Works within a reasonable time, and to open up and revise an extension of time (“EOT”) granted by the project manager. 8.The questions for which leave to appeal is currently sought, as identified in this application for leave, relate to:
EOT Question 9.Neither party has raised issue as to whether decisions on the questions on which leave to appeal is sought will substantially affect the rights of one or more of the parties, which is one of the conditions to be satisfied under s 6 (4) of the Schedule. As the Award dealt with claims and counterclaims for substantial amounts in the Arbitration, I accept that if the arbitrator is shown to have erred in his decision on the questions, the Award would be reduced by a significant sum, to substantially affect the rights of both parties. 10.The EOT Question is whether the Defendant is entitled to any EOT under the Contract for the relevant period of delay. According to the Plaintiff, the issue on this question is whether there was evidence before the tribunal to support the arbitrator’s findings on the cause of the delay involved, and the fact that the relevant delay was a continuation of the issues afflicting the condition of the brickwork infill panels. 11.First, this issue as framed is a determination on the facts of this case, and is a one-off event dependent on the particular facts. It is not a question of general importance, and under s 6 (4) (c) of the Schedule, leave to appeal will only be granted if, on the basis of the findings of fact in the Award, the decision of the tribunal is “obviously wrong”. 12.The Plaintiff has identified paragraph 656 of the Award, where the arbitrator states his finding “as a matter of fact that the substantial delay within the KC period was a continuation of the issues afflicting the condition of the brickwork infill panels”, and that all the critical delays are the liability of the Plaintiff. 13.In context, the arbitrator stated earlier, from paragraph 655 of the Award, thus:
14.The Plaintiff has emphasized that it is not challenging the arbitrator’s findings of fact. It only claims that there was no evidence to support the findings of the arbitrator, that the work of removing the loose brickwork infill panels and the work of repairing the window surrounds (“Repairs”) were proceeding concurrently with the installation of windows, and that the Repairs caused critical delays. 15.The Plaintiff highlighted the fact that the event of the Repairs being a concurrent and critical delay was not so asserted by the Defendant. The Plaintiff further claims that there was no evidence adduced to support the arbitrator’s findings that the Repairs were continuing and critical until 14 August 2014, when KC was in delay in the window installation, and in fact, there was evidence to contradict any such assumption by the arbitrator. 16.The Plaintiff also referred to the post-award letter from the arbitrator dated 29 April 2019, in which he explained that it was the “more logical conclusion” to take the activities (of the ordering, repair and installation of the windows) to overlap, and accepted that there had been no submissions that all window surrounds were completed prior to the window installation, and that was why he had taken those activities to overlap. 17.Whilst an appeal on points of law may, in limited circumstances, involve the court on appeal intervening in areas of law buried beneath conclusions of fact (see discussion in Kwong Mile Services Ltd v Commissioner of Inland Revenue (2004) 7 HKCFAR 275), it must be borne in mind that under s 6 of the Schedule, leave to appeal is to be granted only if the Court is satisfied that, “on the basis of the findings of fact in the award”, the decision of the tribunal on the question of law is obviously wrong. 18.It is trite, that as the fact finding tribunal, the arbitrator is master of the facts (Mustill and Boyd (2nd edition) p 596). The tribunal’s findings of fact are conclusive (para 8-057, Russell on Arbitration, 21st edition). On an appeal, the Court decides any question of law arising from an award on the basis of a full and unqualified acceptance of the findings of fact of the arbitrator, and it is irrelevant whether the Court considers those findings of fact to be right or wrong. 19.In the case of Ha Hau Kwan Fong Mary v IO of Golden Plaza [2002] HKCU 645, Ma J (as he then was) observed:
20.Viewed in this light, I fail to see how it can be said in this case that the arbitrator was obviously wrong in his findings as to the EOT to which the Defendant is entitled, on the evidence which was before him, and on the facts as he found. 21.The arbitrator set out his summary and analysis of the evidence on the period of delay and EOT entitlement, in paragraphs 645 to 655 of the Award. He referred to the experts’ assessment and computation of time, noting the evidence of the Plaintiff’s expert that the window trade was on the critical path and was subject to “massive and persistent delays in its early phases”, causing a delay of 400 out of the total 551 days. At paragraph 652 of the Award, the arbitrator expressed the view that the “predominant matters causing delay” were the mismatch over the window openings and structure coupled with the replacement of the 2 contractors. The arbitrator then set out his findings and assessment of periods of delay in paragraphs 654 to 657 of the Award. At paragraph 655 (cited in paragraph 13 above), the arbitrator referred to the different periods of delay and the experts’ evidence. In particular, at paragraphs 656 and 657, the arbitrator classified the total EOT entitlement of 392 days, making the following observations:
22.The arbitrator also explained in his post-Award letter of 29 April 2019 (to which the Plaintiff has referred):
23.It therefore appears that the arbitrator had considered all delays within the windows trade collectively, as a continuum, and not in isolation, and found that as the responsibility for all these delays lay with the Plaintiff, there was no necessity to separate them. 24.In my view, it was open to the arbitrator to consider the evidence in the manner which he did, and his findings on the EOT entitlement cannot in any way be said to be “obviously wrong”, or such that no reasonable arbitrator could have made. The arbitrator was considering the available evidence on the different work and the delays involved in the window trade, and their possible effect on one another, to conclude the overall effect and total delay. As the court explained in the judgment of Weldon Plant Ltd v The Commission for the New Towns [2000] BLR 496:
25.Any complaint that the arbitrator had based his finding on an alleged error in his understanding of the evidence, or an erroneous assumption, that there was overlap between the reconstruction work on the window surrounds and the window installation work, is in essence an allegation of a mistake of fact having been made by the arbitrator. A finding of fact, be it right or wrong, cannot be challenged and the Plaintiff cannot circumvent the rule, that such a finding is conclusive, by alleging that there was no or insufficient evidence to support the finding. 26.For these reasons, I refuse leave to the appeal on the first question. The Time Bar Question 27.I accept that this question substantially affects the rights of the parties. However, the Plaintiff’s intended appeal is not on the proper construction of GCC 28 (“Clause 28”) of the Contract, only that the arbitrator had erred in his finding that the Defendant had, on the facts of the case, given adequate notice and particulars of its claim as required under Clause 28, such that the condition precedent for the Defendant’s entitlement to additional payment under Clause 28 had been complied with. This is a one-off event turning on the facts of the case, and not a question of general importance. Accordingly, leave to appeal is to be granted only if the decision of the arbitrator on this question is “obviously wrong”. 28.The relevant part of Clause 28.1 states that if the Contractor (i.e. the Defendant) intends to claim any additional payment under the Contract, it “shall give notice” to the Architect of its intention to do so, “within 28 days of it becoming apparent to the Contractor that an event has occurred which gives rise to a claim and he shall include in the notice the contractual provisions upon which the claim is based”. 29.The material part of Clause 28.2 provides as follows:
30.Under Clause 28.3, the Contractor’s compliance with the provisions of Clauses 28.1 and 28.2 is stated to be a condition precedent to the Contractor’s entitlement to additional payment, and if the Contractor fails to comply with these provisions in respect of any claim, that claim “will be deemed to have been waived by the Contractor”. 31.The arbitrator found (in paragraph 559 of the Award) that the Defendant validly gave notice under Clause 28 of its intention to claim loss and expense under Clause 27, by its letters of 17 September 2014 and 12 November 2014. He noted (in paragraph 541 of the Award) that the Defendant was required under Clause 28 to give notice within 28 days of it becoming apparent that an event has occurred which gives rise to a claim, and that Clause 28.2 required the Defendant to keep such records as may reasonably be necessary to support the claim, and to submit particulars within a further 60 days (paragraph 542). 32.As the Plaintiff highlighted, the arbitrator recognized, and was in no doubt, that compliance with the notice provisions of Clause 28 is a condition precedent to payment claimed under Clause 27, and that the issue in dispute was whether the Defendant had failed to comply with such provisions (paragraph 544 of the Award). 33.Whilst rejecting the Defendant’s letters of 2 July and 11 July 2013 and 31 August 2013 as notices which were compliant with Clauses 28.1 and 28.2, the arbitrator accepted that the Defendant’s letter of 17 September 2014, consolidated by its letter of 12 November 2014, did comply with Clause 28 (paragraph 549) of the Award. 34.The letters of 17 September 2014 and 12 November 2014 state a list of the alleged delaying events, the sums claimed, and the clause relied upon, and the letter of 12 November 2014 enclosed a detailed “Extension of Time and Additional Payments Application Interim Submission”, with details and the alleged basis of the claim. The 2 letters, and the details submitted with the 12 November 2014 letter, had been considered by the arbitrator, when he found that some of the events set out in the letter were time-barred, whilst others were not, and on that basis, firstly made his findings as to the extension of time entitlement for the delay events which were validly notified, and secondly, assessed the compensable delays. 35.The arbitrator set out his analysis of the letters and their contents, at paragraphs 549 to 558 of the Award:
36.The Plaintiff complains that the Defendant’s September letter and November letter did not state when the relevant events occurred and became apparent to the Plaintiff, such that there was no evidence before the arbitrator to make his findings. I do not agree that the Defendant was required, under Clause 28, to state when a relevant event had occurred, or when it became apparent to the Defendant that a relevant event which gave rise to the claim had occurred. All that the Defendant was required under Clause 28.1 to do was to give notice of its intention to claim any additional payment, within the period of 28 days of it becoming apparent to the Defendant that an event which gives rise to a claim had occurred, and to state the contractual provisions upon which the claim is based. 37.It was for the arbitrator to find, on the evidence adduced in the Arbitration, whether the notice given by the Defendant was within the time specified, which he did, as pointed out in paragraphs 545, 546 and 552 of the Award. The arbitrator pointed out (at paragraphs 552 and 553) that he had not received submissions on whether the September letter and November letter were validly relevant to delaying events which were occurring in 2014, but he had been directed to the relevant correspondence to consider whether entitlements that arose from the letters were valid in terms of time. 38.In his post-award letter of 26 April 2019, the arbitrator further highlighted (in answer to the parties’ requests for correction and clarification of the Award) the following:
39.It is accordingly clear, from the arbitrator’s analysis set out in the Award, and as explained or amplified in his letter of 26 April 2019, that the arbitrator had carefully considered the letters of 17 September 2014 and 12 November 2014 and the particulars and submission enclosed, together with the entirety of the documents and evidence placed before him in the Arbitration, in finding that the information and particulars furnished to the Plaintiff were sufficient to comply with Clause 28.1 and 28.2, adopting the broad construction of the clause as he did, and having been satisfied that the letters had achieved the purpose of placing the Plaintiff on notice of a potential problem. 40.The fact that the arbitrator rejected the adequacy of other, earlier letters of purported claims, on the basis of the absence of particulars of claim having then been submitted, cannot mean that the arbitrator must reject claims which he analyzed and accepted to have been validly served within time by the September letter and the November letter, on the basis of the particulars and information set out in the September letter, the November letter and its enclosure. 41.In criticizing the arbitrator’s decision as to the adequacy of the notice of claims and his consideration of when an event might “become apparent”, the Plaintiff sought to place reliance on the arbitrator’s statement, in paragraph 551 of the Award, that “hypothetically, events can materialize and manifest themselves before they became apparent although no evidence of that was adduced here”. The Plaintiff seems to suggest that the arbitrator was admitting that there was no evidence of when the events became apparent, or otherwise that he had made findings on the basis of a hypothesis. I cannot see how the arbitrator’s statement can assist the Plaintiff’s case. On my reading, the arbitrator was only referring to a hypothetical situation, and the reference to absence of evidence was a reference to events materializing and manifesting before they became apparent, as opposed to the absence of evidence as to when events became apparent. In any event, it was a hypothetical situation stated by the arbitrator, which did not affect or form a part of his reasoning. On a proper reading of paragraph 551, the arbitrator’s emphasis was that the 28 days for notice to be given run from when the event “becomes apparent”, as opposed to the hypothetical possibility of events manifesting and materializing before they become apparent, or when they first occurred or actually subsisted. 42.Overall, the arbitrator was in the best position to consider and analyze in detail the documents and evidence placed before him by the witnesses in the Arbitration, to decide whether the notice was given in time, whether sufficient particulars were given, and whether the condition precedent had been satisfied, and this Court is entitled to give weight to the analysis made of such evidence by the arbitrator, in its consideration of whether his decision in the Award is obviously wrong, or open to serious doubt, or not. On my review of the Award, I do not find the arbitrator’s analysis of the evidence and his findings on the Time Bar Question to be obviously wrong. Risk Allocation Question 43.The third question of law relates to the arbitrator’s construction of the relevant provisions of the Contract, in determining that the Plaintiff was responsible for the condition of the window openings to the building, which extends to the condition of the fabric of the external panels of the building, and their reconstruction to meet the installation of the new windows (paragraph 216 of the Award). This in fact follows from the arbitrator’s finding, in paragraph 135 of the Award, that the Defendant had no design responsibility under the Contract for the window and cladding works (“Window Works”). These 2 issues together formed Issue 3 in the Arbitration: “What is the Claimant’s design responsibilities, if any, under the Main Contract, and particularly whether the Claimant has any design responsibility in respect of the window and cladding works.” 44.The relevant contract provisions considered and construed by the arbitrator, in deciding the Risk Allocation Question, include in particular clause 4.05 of the Specification Preliminaries (“SP 4.05”), and Technical Specification Clause 18.1.1 of Section 18 - Window Works of the Contract (“TS 18.1.1”) (as identified in the Originating Summons). 45.As in the case of the EOT Question and Time Bar Question, I accept that the arbitrator’s decision on the Risk Allocation Question substantially affects the rights of both parties. 46.According to the evidence of the Plaintiff, SP 4.05 and TS 18.1.1 were inserted in the tender documents to cater for the Contract, and to address any potential or contingent condition of the existing window openings of the building. As pointed out by the Defendant, these provisions were bespoke for the project which was the subject matter of the Contract. The decision on the Risk Allocation Question turns on the particular language of SP 4.05 and TS 18.1.1 as applied to the facts of this case, turning on the condition of the building and the works to be carried out in the project. It is a one-off event, and the threshold of “obviously wrong” is therefore applicable, for leave to appeal to be granted. 47.The issue of the Defendant’s design responsibility for the Window Works under the Contract was an important question with significant bearing on the issues in dispute in the Arbitration. The risks to be borned by the condition of the building and its impact on the Window Works, and the party to bear such risks, are questions closely related to the Defendant’s design responsibility. Together, they form Issue 3 for the Arbitration. 48.The Contract was for the conversion of an existing 50 year old building into a serviced apartment. The renovation work involved substantial alterations, additions and upgrading of the layout and finishes of the residential tower, the building services installations and the façade of the whole building. In particular, the pertinent project works included the replacement of the windows to the building. 49.The issues for determination in the Arbitration included the design obligations of the parties in relation to the Window Works, whether the specialist window subcontractor was a nominated or a domestic subcontractor, and what was the liability for the condition of the structural openings in which to fit the windows, and the making good of such openings. 50.The Defendant was the main contractor, and there was a specialist window subcontractor. Much of the problems encountered in the project related to the appointment of the specialist subcontractor, the original specialist subcontractor abandoning the works, delay in the appointment of a replacement, the problems encountered as a result of the condition of the building and the window openings, and the difficulties of designing the new windows to suit the existing condition of the building. Hence, an important issue was whether the Defendant, as the main contractor, should be liable for the design of the windows, and (in gist) whether the Defendant, or the Plaintiff as the employer and owner of the building, should bear the risks arising from the different conditions actually encountered on site. 51.It is clear from the Award that in deciding on the Risk Allocation Question, the arbitrator had carefully considered the relevant contract provisions, and the submissions made by both the Plaintiff and the Defendant, firstly on the questions of design liability generally, and specifically in respect of the Window Works, and secondly on the responsibility for the condition of the window openings in the building and their reconstruction to meet the installation of the windows under the Contract. It is important that the arbitrator’s decision on the Risk Allocation Question has to be considered in the light of his decision on the Defendant’s responsibility and scope of work under the Contract, and his finding that the Defendant had no responsibility for designing the Window Works. 52.The relevant TC 18.1.1 provides as follows:
53.In relation to design responsibility, the arbitrator considered “the starting point” to be the position under the Contract, which expressly stated that the Defendant’s responsibility for design is as provided for in GCC 2.1 (e), (d) and (2): essentially, to carry out “any work involved in the development of the Architect’s design”. At paragraphs 114 to 118, the arbitrator stated:
54.The arbitrator then considered the respective submissions made on behalf of the Plaintiff and that Defendant, as to the responsibility of a main contractor (such as the Defendant) for the design obligations of a named domestic subcontractor, or a nominated subcontractor. His conclusion was set out in paragraph 133 of the Award:
His conclusion and finding, in paragraph 135 of the Award, was that the Defendant had no design responsibility under the Contract for the Window Works. 55.In proceeding to determine the key issue of the responsibility for the condition of the window openings, the arbitrator referred to the evidence on the condition of the building and the window openings, the fact that the building was constructed as a reinforced concrete frame, but the panels forming the external walls, between columns, slabs and beams were in brickwork with a rendered finish. In brief, the Defendant’s position was that the Contract was not a design and build contract, and that its responsibility was simply to remove the old windows and make good the openings, and not to design, supply or install the new windows. The Plaintiff’s position was that the Defendant should be liable for whatever material in the building fabric which it encountered, notwithstanding that forming or creating new openings in brickwork would be much more time-consuming than fitting windows to existing reinforced concrete surrounds. There is no dispute that the brickwork to the infill panels surrounding the windows was, in reality, in a very fragile state with large parts becoming loose. The brickwork fell away in places upon removal of the old windows, such that the façade brick panels had to be reconstructed, before windows could be measured and manufactured. 56.In construing TS 18.1.1 and the scope of the Window Works which was the responsibility of the Defendant under the Contract, the arbitrator considered the words used: namely “removal of the existing windows”, “preparation” of external wall, and “formation and making good of external wall openings”. At paragraph 180 of the Award, the arbitrator stated:
57.The Plaintiff argued that the arbitrator was wrong, in focusing on the “imprecise” and the “ambiguous” words used in the Contract, instead of considering the commercial and factual context and the commercial purpose of the contract provisions. 58.Having considered the Award, and the arbitrator’s analysis, I cannot disagree with his construction of the provisions of SP 4.05 and TS 18.1.1, and GCC 2.1 (e), (d) and (2) of the Contract. I refer again to the decision of Lam VP in Maeda Kensetsu Kogyo Kabushiki Kaisha (also known as Maeda Corporation) and China State Construction Engineering (Hong Kong) Limited v Bauer Hong Kong Limited HCMP 1342/2017, 4 September 2017, where His Lordship pointed out that the assessment of whether the decision of a tribunal is at least open to serious doubt (the test applicable in that case) can be subjective, and different judges can reasonably come to different views. Such reminder illustrates that particularly in a matter concerning the construction of a contractual document, the Court dealing with an application for leave to appeal may well have a different view as to the possible meaning of a provision, but it does not follow from that, that the meaning ascribed by the tribunal to that provision was either “open to serious doubt”, or “obviously wrong”. The “obviously wrong” threshold is high. 59.I do not agree that the arbitrator can be criticized, for having approached the interpretation of the contractual provisions incorrectly, in failing to undertake a “unitary” exercise, or in failing to consider the commercial context and purpose of the relevant provisions. As the decisions in Rainy Sky SA v Kookmin Bank [2011] UKSC 50 and Arnold v Britton [2015] AC 1619 have highlighted, the language used in the provision to be construed is important, notwithstanding the need to read such language in the proper factual and commercial context. The arbitrator obviously considered that on its plain reading, “formation” and “making good” as used in the provisions exclude the duty to reconstruct the window openings, and do not extend to requiring the Defendant to reconstruct the infill panels, or to substantially modify the window surrounds. 60.From his analysis of SP 4.05 and the technical specifications which include TS 18.1.1, TS 18.1.3, TS 18.1.6 and 18.3.1, the arbitrator concluded that the new window system had to be designed to fit with the existing window openings, and that under SP 4.05, the contractor had to accept the risks only of unfavorable or difficult working conditions and obstructions which might impede the progress of its works, but that SP 4.05 does not render the contractor liable for the physical condition of the building. 61.The relevant provisions of SP 4.05 are as follows:
62.On a review of paragraphs 159 to 218 of the Award, it is clear that the arbitrator had considered the Contract in its entirety, and all the relevant provisions, in a “unitary exercise”, in reaching his decision on the apportionment of the risks arising from the structure and the unforeseen condition of the building, and of the window openings. He bore in mind the fact that the problems faced by the parties were of a building design, rather than arising from the design of the windows, or was a combination of both. At paragraphs 212 to 216 of the Award, the arbitrator concluded:
63.From paragraph 217, it would appear that the arbitrator had considered the commercial purpose and consequences of the relevant clauses construed. In any event, as the court sought to explain in Arnold v Britton (paragraphs 17, 19-20 of the judgment), commercial common sense should not be invoked to undervalue the importance of the language of the provision to be construed, and commercial common sense should not be invoked retrospectively, as it is not the function of the court when interpreting an agreement to relieve a party from the consequences of an imprudent term or arrangements which are ill advised, nor to rewrite the contract for the parties to achieve a result which the court considers more desirable. Here, the arbitrator had considered the plain meaning of the language used in the Contract, the context of the building project and the Window Works, as well as the commercial sense of the construction he placed on the provisions. I do not agree that the arbitrator’s interpretation of the Contract is one which does not make commercial sense, or one which no reasonable arbitrator could have made. 64.In all, the arbitrator was not “obviously wrong” in reaching the conclusion which he did on the Risk Allocation Question. Even if the threshold of “open to serious doubt” should be applicable, I do not consider that this threshold is met. Disposition 65.The Plaintiff’s application for leave to appeal on the 3 questions identified is refused. The order nisi is that the costs of the application are to be paid by the Plaintiff to the Defendant, with Certificate for Counsel.
Mr Eric Chung, instructed by Deacons, for the plaintiff Mr Simon Westbrook SC, instructed by Norton Rose Fulbright Hong Kong, for the defendant | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Cases cited in this judgment
Other judgments that cite this case