Air Charter Service (HK) Ltd v. 美拓国际物流(上海)有限公司(also known as Mega-transporter Shanghai Co., Ltd.)
Read the full judgment text of HCA 974/2018 on BabelCite. This High Court CFI judgment was delivered on 8 January 2021.
1. This is the trial of an action brought by the Plaintiff (“ P ”) against the Defendant (“ D ”), in which P claims various sums allegedly due under an Aircraft Charter Contract dated 23 Feb 2018 (the “ Contract ”) and/or damages for breach of the Contract.
Cited by 3 cases · Cites 7 cases
|
HCA 974/2018 [2021] HKCFI 56 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO 974 OF 2018 ____________
____________ Before: Deputy High Court Judge Dawes SC in Court Date of Hearing: 14 December 2020 Date of Judgment: 8 January 2021 _______________ JUDGMENT _______________ Introduction 1.This is the trial of an action brought by the Plaintiff (“P”) against the Defendant (“D”), in which P claims various sums allegedly due under an Aircraft Charter Contract dated 23 Feb 2018 (the “Contract”) and/or damages for breach of the Contract. 2.D was originally represented by Messrs. Christine M Koo & Ip (“CKI”). Shortly before trial, CKI applied for and was granted leave to cease to act for D upon compliance with the requirements of O. 67 r. 6(1) of the Rules of the High Court (“RHC”) by an Order of Master Dick Ho dated 13 May 2020. 3.As it happened, CKI encountered difficulties serving its Notice of Cessation to Act on D in the Mainland as a result of the COVID-19 pandemic. Nonetheless, it was clear from the correspondence that they no longer had authority to act on D’s behalf and that D was at all times aware of CKI’s cessation to act. As such, CKI was excused from attendance at the trial shortly prior to its commencement. 4.D did not appear at the trial. As D was undoubtedly aware of the trial dates (having previously applied unsuccessfully to adjourn the trial for three months by letter dated 22 September 2020), I directed that the trial proceed in its absence pursuant to O. 35 r. 1 RHC. 5.P called one witness at the trial, namely its cargo director, Mr Tam Kwai Kuen. D had filed and served a witness statement of Weiting Shen dated 3 January 2019, but as it did not call Mr Shen as a witness at the trial, Mr Shen’s witness statement is not to be regarded as evidence at this trial by virtue of O. 38 r. 2A(6) RHC. The facts 6.The factual background of the action is relatively straightforward and largely undisputed. 7.P is a company incorporated in Hong Kong carrying on an aircraft chartering business. 8.In or around late March 2018, P and D entered into the Contract pursuant to which D agreed to charter a total of 107 flights between Zhengzhou Xinzheng International Airport and Chicago O’Hare International Airport between 1 May 2018 and 4 February 2019 (the “Flights”)for a total price of US$49,336,000. 9.The Contract included, inter alia, a Schedule (the “Schedule”)and a set of General Conditions (the “General Conditions”). 10.The Schedule set out the times and dates of each of the Flights, the first of which (the “1st Flight”) was scheduled to depart from Chicago O’Hare International Airport on 1 May 2018 at 00:30 UTC. The Schedule provided that the Charter Price for each Flight was US$458,000 per flight, except for the flights on 2, 7 and 9 May, 4, 6, 11 and 13 June, 2, 4, 9 and 11 July 2018 for which the Charter Price was US$488,000 per flight. 11.The Schedule also contained, inter alia, the following terms:
12.The General Conditions provided, inter alia, that:
13.On 24 March 2020, P entered into a Charter Agreement dated 14 March 2018 with Kalitta Air LLC (“Kalitta”) (the “Kalitta Contract”) pursuant to which P arranged for Kalitta to operate the Flights. The Kalitta Contract provided that the rate payable by P for each Flight was US$450,000, except for the flights on 2, 7 and 9 May, 4, 6, 11 and 13 June, 2, 4, 9 and 11 July 2018 for which the rate was US$480,000 per flight. 14.The only relevant provision of the Kalitta Contract for present purposes is cl. 5.3 of the Terms and Conditions, which is as follows:
15.On 4 April 2018, P issued Invoice No. 6452 to D (the “Invoice”) for the sum of US$488,000, being the Charter Price for the 1st Flight (the “1st Charter Price”). The Invoice stated that the 1st Charter Price was “Due By 24/4/2018”. 16.Towards the end of April, D indicated on several occasions that it had doubts about proceeding with the Flights as scheduled and was considering postponing the contract. P thus sent multiple chaser emails to D reminding them to pay the 1st Charter Price in the days leading up to 24 April. 17.D did not pay the 1st Charter Price on 24 April 2018. Instead, by an email sent at 12:44 on 25 April 2018, Mr Shen made a request on D’s behalf to cancel the 1st Flight and postpone the Contract by two months. 18.In a reply email sent at 13:04 on 25 April 2018, Mr Stephen Fernandez of P indicated that P would be willing to ignore D’s late payment of the 1st Charter Price if it paid the cancellation fee for the 1st Flight that day, failing which P would terminate the Contract:
19.Despite Mr Fernandez’s email, D did not make any payment on that day. As a result, P purported to terminate the Contract by a letter dated 25 April 2018, which Mr Fernandez sent to Mr Shen in an email at 01:43 on 26 April 2018 (the “Termination Letter”). The Termination Letter provided that:
20.P terminated the Kalitta Contract on the same day. 21.By an email sent at 14:57 on 28 April 2018 on D’s behalf, Mr Shen also purported to terminate the Contract. 22.P’s two pleaded claims in this action are as follows:
The 1st Charter Price 23.P’s case in this regard is straightforward: it says that D became obliged to pay the full amount of the 1st Charter Price 5 working days before the scheduled time of departure, ie. 24 April 2018. As D has failed to pay any part of the 1st Charter Price to date, P is entitled in this action to payment thereof. 24.D accepts that the Contract obliged it to pay the 1st Charter Price by 24 April 2018.[1] D also does not dispute that it has so far failed to pay the 1st Charter Price, the 1st Cancellation Charge or any portion thereof. It contends, however, that on a true construction of the Contract (in particular the Payment Clause and the Cancellation Clause) it was entitled to cancel a Flight at any time before its scheduled time of departure subject to the payment of a cancellation charge, and that once it had cancelled the Flight, it was only required to pay the relevant cancellation charge instead of the Charter Price. As D cancelled the 1st Flight by its email sent at 12:44 on 25 April 2018, it was no longer obliged to pay the 1st Charter Price but only obliged to pay the 1st Cancellation Charge. 25.Mr Ng, who appeared on behalf of P, argued that the Cancellation Clause should not be read as qualifying or varying D’s obligation under the Payment Clause to pay 100% of the 1st Charter Price by 24 April 2018. He submitted as follows:
26.I accept Mr Ng’s submissions. In my view, there is a further reason why D’s interpretation is to be rejected. The Cancellation Clause obliges D to “pay” 90% of the Charter Price “forthwith” if it cancelled a Flight within 7 days of the scheduled departure time. This language of “payment forthwith” only makes sense if the Cancellation Clause is understood as applying only to the period before D became obliged to pay the Charter Price in full. 27.In the circumstances, I find that P is entitled to the sum of US$488,000, being the 1st Charter Price. The Liquidated Sum 28.Mr Ng submitted that P’s entitlement to the Liquidated Sum arose in the following manner:
29.D, on the other hand, contended that:[2]
30.At the outset, I agree with Mr Ng that P was entitled to, and did in fact terminate the Contract pursuant to cl. 9 of the General Conditions. As mentioned above, there is no dispute that D became obliged to pay the 1st Charter Price by 24 April 2018 and that this sum was outstanding as at that date. As such, D had “default[ed] in the payment of [an] amount payable [under the Contract] on due date” within the meaning of cl. 9.1, entitling P to terminate the Contract immediately upon notice to D. As P’s letter dated 25 April 2018 makes clear, P then terminated the Contract “in accordance with cl. 9”. 31.However, I am unable to agree with Mr Ng’s contention that the Cancellation Clause and cl. 10 read together entitle it to liquidated damages in the amounts specified in the Cancellation Clause upon termination of the contract pursuant to cl. 9. In my judgment, his proposed interpretation misreads the two clauses in several respects.
32.All in all, the two clauses properly understood operate in separate spheres. The Cancellation Clause provides for payment of cancellation charges in the event that “[D] wishes to cancel any Flight or Flights”, and cl. 10 provides that P is to be indemnified for its actual losses in the event that it terminates the contract under cl. 9. There is nothing in cl. 10 which requires payment of the cancellation charges listed in the Cancellation Clause upon termination, nor is there anything in the Cancellation Clause which states that it applies to a termination pursuant to cl. 9. 33.At the hearing, Mr Ng sought to defend P’s interpretation of the Cancellation Clause on the basis that they were intended as a mirror of the cancellation provisions in the Kalitta Contract. Essentially, his argument was that the parties did not intend for P to be left out of pocket in the event that P terminated the Kalitta Contract following its termination of the Contract and became liable to pay cancellation charges to Kalitta. 34.I accept, of course, that one must construe the Cancellation Clause and cl. 10 in context. I also accept that the cancellation terms of the Kalitta Contract were within the contemplation of both parties at the time of contract and as such form part of the relevant background. However, I do not see how P’s potential liability to pay cancellation charges to Kalitta militates in favour of P’s proposed construction of the Contract which entitles it to the Liquidated Sum. That is because P is fully protected even in the absence of such a right. Having validly terminated the Contract under cl. 9, P is straightforwardly entitled to an indemnity under cl. 10 for any cancellation charges which it is thereby obliged to pay Kalitta under the Kalitta Contract.[3] In fact, cl. 10 specifically provides that the losses, damages, costs, expenses, claims or liabilities for which D must indemnify “includ[es] in particular but [is] not limited to any and all cancellation charges payable by [P] to [Kalitta]”. 35.For these reasons, I reject P’s claim to the Liquidated Sum. In these circumstances, it is unnecessary for me to deal with D’s subsidiary contentions that the Liquidated Sum was a penalty and/or incorrect and excessive. Damages for loss of bargain 36.As an alternative to its claim for liquidated damages, P claimed damages for loss of bargain resulting from D’s repudiatory breach of contract. 37.As noted above, cl. 2.3 of the General Conditions expressly makes time of payment of the Charter Price of the essence of the Contract. As such, the Payment Clause was a condition which D breached by failing to pay the 1st Charter Price. D thus committed a repudiatory breach of the contract which entitled P to terminate the Contract at common law. 38.However, an innocent party is only entitled to damages for loss of bargain for repudiatory breach if it in fact terminated for this reason: Phones 4U Ltd v EE Ltd [2018] EWHC 49 (Comm) [2018] 2 All ER (Comm) 315, §128 (Andrew Baker J). On the face of things, this presents an obstacle for P, as its letter dated 25 April 2018 only referred to cl. 9 of the General Conditions as the basis for termination of the contract. As Christopher Clarke J explained in Dalkia Utilities Services Plc v Celtech International Ltd [2006] EWHC 63 [2006] 1 Lloyd’s Rep 599 at §§143-144, the exercise of a contractual termination right may in certain circumstances show that the innocent party did not intend accept the contract breaker’s repudiatory breach:[4]
39.However, on the facts of the present case, I am satisfied that P did exercise both its contractual right to terminate the Contract and its common law right to accept a repudiatory breach. The remedies available to P following a termination under cl. 9 are not inconsistent with those available following a termination for repudiatory breach. It is true that cl. 10 only entitles P to an indemnity for losses suffered and not damages for loss of profits upon termination in accordance with cl. 9, but importantly, it does not exclude a claim for the latter. 40.The facts of this case are distinguishable from those in Dalkia, where Christopher Clarke J reached the opposite conclusion. The contract concerned the provision of energy and steam to a paper mill by way of an energy plant. Dalkia served a notice terminating the contract under cl. 14.4, and an issue arose as to whether it had also terminated for Celtech’s repudiatory breach. The judge held that there was no repudiatory breach, but in any event, the service of the contractual termination notice did not amount to an acceptance of repudiatory breach at common law. This was because had Dalkia validly terminated the contract at common law, it would have been entitled to, inter alia, keep the energy plant. On the other hand, the contract provided that upon a termination pursuant to cl. 14.4, Celtech would have been entitled to keep the plant and obliged to pay a termination sum. Those two sets of consequences were simply impossible to reconcile. 41.I also note that in its termination letter dated 25 April 2018, P referred to “clause 2.3 of the [Contract] which makes it clear that payment is of the essence of the [Contract]”, and reserved its right to recover its losses arising out of D’s actions from D,“including but not limited to the rights available under the [Contract]”.This suggests that P did have its common law right to terminate in mind, and did not intend to rely only on cl. 9 of the General Conditions when terminating the Contract. 42.P is thus entitled to damages for loss of bargain. P claims two heads of damages:
43.I do not think there can be any objection to P’s claim for its legal costs. In relation to the claim for loss of profits, however, I note that the Free Cancellation Clause in the Schedule (set out in §11(3) above) entitles D to cancel up to 8 flights over the duration of the contract (with a maximum of 2 flights per month) free of charge provided that it provides 15 days’ notice. In light of the well-established principle that damages for breach of contract are assessed on the basis that the contract-breaker would have performed the contract in the way which minimizes the cost to itself (sometimes referred to as the minimum performance rule),[5] it seems to me that P is only entitled to loss of profits for 98 flights. 44.When I raised this point at the hearing, Mr Ng submitted that I should disregard the Free Cancellation Clause for the reason that D never exercised this right during the (brief) lifetime of the contract. However, I do not think that is quite right. The minimum performance rule does not require proof that the defendant did or would have exercised the option; it deems that he would have done so: see Maredelanto Compania Naviera v Bergbau-Handel (The Mihalis Angelos) [1971] 1 QB 164, 196H (Lord Denning MR). 45.For the reasons above, I am of the view that P is entitled to damages in the sum of US$8,000 x 98 flights + US$1,732.50 = US$785,732.50. Interest 46.Relying on the Default Interest Clause in the Schedule, P claims both pre-judgment and post-judgment interest on the 1st Charter Price at the rate of 10%p.a above the base rate of Barclays Bank plc calculated on a daily basis, compounded monthly. 47.I am satisfied that the Default Interest Clause (set out at paragraph 11(4) above) entitles P to pre-judgment interest at the rate above: see Chitty §26-289. As for post-judgment interest, the proper analysis is that set out by Lord Bingham in Director General of Fair Trading v First National Bank plc [2002] 1 AC 481 at §3:[6]
48.In the present case, I consider that the Default Interest Clause (insofar as it provides for post-judgment interest) is a freestanding covenant which is not merged into the judgment for the 1st Charter Price and interest: after all, its express stipulation of post-judgment interest would be rendered nugatory otherwise. As such, P is entitled to charge post-judgment interest on the 1st Charter Price at the contractual rate: see Freeway Finance v Tam Chuen On [2010] 4 HKC 448 §§16-21 (DHCJ L Chan), Honip Credit §§21-22; Top Winton Ltd v Lam Chun Man [2018] HKDC 864 [2018] 3 HKLRD 636 at §§12–19 (Deputy Judge Alfred Cheng). 49.P also claims interest on the amount of damages awarded above pursuant to sections 48 and 49 of the High Court Ordinance (Cap. 4). I award interest at the conventional rate of prime plus 1% from 26 April 2018 (being the date the Contract was terminated) until judgment, and interest at the judgment rate from the date of this judgment until payment: see Kyocera Corporation v W Haking Enterprises Co Ltd [2020] HKCA 817 CACV 554/2019 (unrep, 9 Oct 2020) at §58 (Yuen JA), Chow How Yeen Margaret v Wex Pharmaceuticals Inc [2018] HKCA 344 [2018] 3 HKLRD 163 §§45-59 (Lam VP). Conclusion 50.For the above reasons, I grant judgment to P in the sum of US$1,273,732.50 and interest at the rates set out in §§47–49 above. 51.Costs should follow the event. 52.Mr Ng asked for costs to be assessed on an indemnity basis in light of cl. 10 of the General Conditions. 53.The relevant principles are well-established. Where a contract provides for costs to be payable on an indemnity basis, it provides the starting point for the court’s discretionary exercise and the court should be slow to disturb the parties’ agreement: Bank of China (Hong Kong) Ltd v Twin Profit Ltd (2012) 15 HKCFAR 560 at §21 (Ribeiro PJ). The question is whether cl. 10 so provides. 54.I note that cl. 10 does not use the words “indemnity basis” and instead simply provides for D to indemnify P for “all […] costs”. However, the weight of authority suggests that the phrase “all costs” is to be read as importing taxation on an indemnity basis: see Tele-Art Inc v Bank of China (Hong Kong) Ltd [2012] 1 HKLRD 484 at §§51-53 (Barma J).[7] In any event, I agree with Barma J (as he then was) that this is the appropriate construction to be placed on the phrase “all costs” as a matter of ordinary language. 55.Accordingly, I make an order nisi that D pay P’s costs of this action on a party and party basis, to be taxed if not agreed.
Mr Michael Ng, instructed by Holman Fenwick Willan, for the plaintiff Attendance of Christine M Koo & Ip, for the defendant, was excused [1] Amended Defence §9. [2] Amended Defence §§11.1A–11.4, [3] In fact, P has not been required to pay any cancellation charges to Kalitta so far. [4] This analysis, while obiter, has been treated as representing the law since: see Phones 4U Ltd §126 and the cases cited therein. [5] Chitty on Contract (33rd ed) §26-083, McGregor on Damages (20th ed) §10-106 [6] Cited with approval by G Lam J (delivering the judgment of the Court of Appeal) in Honip Credit Ltd v Asia China Tea Export Company Ltd HCMP399/2016 (unrep, 2 Jun 2016) at §21. [7] Appeal on other grounds dismissed: see [2012] 5 HKLRD 399, §§11, 24. |
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under HCA 974/2018