China Fair Land (Qingdao) Ltd v. Lo Sum Sum
Read the full judgment text of DCCJ 1383/2014 on BabelCite. This District Court judgment was delivered on 31 May 2021.
1. By summons filed on 17 July 2020, the plaintiff ( “the Summons” ), relying on Order 45 rule 8 and Order 29 Rule 1 of the Rules of the District Court ( “RDC” ), applied, among other things, for the following order:
Cited by 1 case · Cites 3 cases
|
DCCJ 1383/2014 [2021] HKDC 646 IN THE DISTRICT COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION CIVIL ACTION NO. 1383 OF 2014 --------------------------
------------------------- Coram: His Honour Judge H. Au-Yeung (Paper Disposal) Date of Plaintiff’s Submissions: 26 April 2021 Date of Defendant’s Submissions: 3 May 2021 Date of Plaintiff’s reply submissions: 7 May 2021 Date of Decision: 31 May 2021 -------------------------- DECISION -------------------------- THE PLAINTIFF’S APPLICATION 1.By summons filed on 17 July 2020, the plaintiff (“the Summons”), relying on Order 45 rule 8 and Order 29 Rule 1 of the Rules of the District Court (“RDC”), applied, among other things, for the following order:
THE BACKGROUND 2.Before I deal with the applications, it is necessary to set out the procedural background of the present action. It will be seen that once such background is known, the plaintiff’s applications may be disposed of very quickly. 3.This is a water leakage case. 4.The plaintiff is the owner of Flat F, 25/F., Block 6, City Garden, No.233 Electric Road, Hong Kong (“the plaintiff’s Premises”). The defendant is the owner of Flat F on 26th Floor of the same building (“the defendant’s Premises”). 5.On 11 April 2014, the plaintiff filed the Writ of Summons herein and claimed against the defendant for, among other things, the following reliefs:
6.Parties reached settlement on the first day of the trial on 1 March 2016[1], and as a result a Tomlin Order was made by the trial judge (“the original Trial Judge”). In the Schedule of the said Tomlin Order, it was stipulated, among other things, that the parties shall engage their respective experts to carry out colour water ponding test at the defendant’s Premises on or before 1 May 2016, and the parties shall “procure a signed report by the experts confirming that the test has revealed no water leakage from [the defendant’s Premises] to [the plaintiff’s Premises]” within 28 days after the test was completed (by way of an inspection which would take place 7 days after the colour water was applied). 7.Although it was not spelt out expressly in the Schedule of the said Tomlin Order, it appears that there was an understanding between the parties that the defendant would carry out repair work at the defendant’s Premises before the colour water ponding test was done. According to the defendant’s Affirmation filed on 28 October 2020, such work had indeed been done. However, while colour ponding test did reveal that there was no further water seepage, infrared scan and electrical conductivity sensing test showed that the master bathroom and the guest bathroom of plaintiff’s Premises were still suffering from water seepage problem, even though the experts could not agree on the source of the water: Ms Rosanna Lau (the plaintiff’s expert) opined that water was still seeping down from the defendant’s Premises to the plaintiff’s Premises, but on the other hand, Mr Andrew Kung (the defendant’s expert) could not tell the exact source of the water[2]. 8.Despite the opinion of the defendant’s expert, the defendant’s solicitors, by letter dated 29 September 2016, agreed to the plaintiff’s proposal (which was made by letter dated 22 September 2016), that, among other things, the defendant shall, on or before 22 November 2016:
9.On 14 November 2016, the defendant’s solicitors wrote to Ms Rosanna Lau, the plaintiff’s expert, and gave her notice about the completion of renovation work. The defendant’s solicitors further invited Ms Lau to carry out necessary tests so as to confirm that the water seepage problem had been solved. 10.4 days later, on 18 November 2016, the defendant’s solicitors wrote to the plaintiff’s solicitors. This letter reads:
11.On 28 November 2016, parties filed a consent summons and asked for the following order: “Judgment on admission be entered against the Defendant for damages to be assessed”. The consent summons was passed to the original Trial Judge for disposal. The learned Judge decided to fix a hearing to deal with the consent summons rather than making an order in terms on paper. The hearing was eventually fixed to be heard on 27 February 2017. 12.On 20 December 2016, the defendant’s solicitors wrote to the plaintiff’s solicitors further. It reads:
13.On 22 February 2017, parties’ solicitors wrote a joint letter to the court. In the said letter, they set out the background of the case as follows:
14.The joint letter dated 22 February 2017 then continued:
15.The hearing was then re-fixed to be heard on 16 May 2017. 16.On 8 March 2017, Ms Rosanna Lau issued her expert report, in which she concluded that “there is sign and evidence to indicate that water seepage was still found on the ceiling and pipe ducts of master bathroom, guest bathroom and corridor of the [plaintiff’s Premises]”, and that the water was coming from the defective drainage of the master bathroom and the guest bathroom of the [defendant’s Premises] respectively.[4] 17.On 16 May 2017, the original Trial Judge made the following orders:
18.Pausing here, it is necessary for me to make a few observations:
19.On 28 June 2019, parties filed a consent summons and sought a number of expert directions which may be summarised as follows:
20.A Master subsequently approved the consent summons and made an order in terms thereof on 3 July 2019. 21.With greatest respect to the learned Master, the consent summons should not have been approved as it was, because no expert directions on liability should have been given, given the fact that judgment on liability had already been entered. 22.A joint expert report dated 3 February 2020 was subsequently prepared pursuant to the said order of the learned Master. While the experts agreed that the plaintiff’s Premises were still affected by water seepage problem, they could not agree on the extent of such a problem nor the source of the water. 23.As the plaintiff maintained that the defendant had failed to comply with the order made pursuant to the Judgment on Liability, it filed the Summons on 17 July 2020 and sought the following order:
DISCUSSION Order 45 rule 8 of the RDC 24.Mr Wong for the plaintiff submitted that this application made pursuant to Order 45 rule 8 of the RDC is necessary for the enforcement of the Judgment on Liability. 25.Order 45 rule 8 of the RDC reads:
26.It can be seen that Order 45 rule 8 of the RDC only empowers the court to order someone other than the disobedient party to do the required act, but at the expense of the disobedient party. This rule does not empower the court to order the disobedient party to do the act. 27.Indeed, if judgment had already been entered, why is it necessary to make another order of similar effect? 28.In support of this application, Mr Wong for the plaintiff had referred this court to The Incorporated Owners of Champion Court v Pang Ping Fan Peter & Another (HCMP 359/2011, unreported, 27 April 2011) and Ever International Investment Holdings Limited v Lee Wah (DCCJ 886/2014, unreported, 1 February 2016). Suffice for me to point out that neither of these authorities concerns any application for the disobedient party to do any act. Hence, these cases do not assist the plaintiff. 29.In his reply submissions, Mr Wong submitted that the court may appoint a contractor to be nominated by the plaintiff and/or the defendant to carry out the rectification work “so as to tackle the defendant’s literal and technical objection to the application of O.45, r.8”[8]. With respect, Mr Wong is not permitted to depart from the terms of the Summons. If the contractor is going to be appointed by the plaintiff, then it would be taken as if it is the plaintiff which is doing the act. This is not what the plaintiff is applying for. On the other hand, if the contractor is going to be appointed by the defendant, then it would be taken as if it is the defendant who is doing the work, and such an order is not covered by Order 45 rule 8 as explained. 30.Furthermore, the drafting of the Summons is also problematic in that it is prayed that the repair work stipulated thereunder has to be done “to the satisfaction of the plaintiff’s expert”. There is no such requirement pleaded in relief (b) of the Statement of Claim (which, as aforesaid, is treated as an order made by the court on 16 May 2017). The defendant’s obligation should only be limited to that which is ordered by the court. There is no reason why an additional requirement should be permitted to be inserted at this stage. 31.In my view, the plaintiff’s application made pursuant to Order 45 rule 8 is totally misconceived and should be dismissed. Order 29 rule 1 of the RDC 32.In the event the plaintiff’s application made under Order 45 rule 8 of the RDC failed (which it did), Mr Wong sought to rely on Order 29 rule 1 as an alternative. He explained his fall-back position in the following way:
33.Mr Wong then went on to persuade the court that:
34.As mentioned above, judgment on liability had already been entered against the defendant, and it is taken as if an order in terms of relief (b) as pleaded in the Statement of Claim had already been made. This is a final order on liability. 35.In such circumstances, the application for an interlocutory mandatory injunction is totally misconceived. It is also difficult to understand why the plaintiff still tried to persuade the court that it had a “high assurance of success” when it had already succeeded by virtue of the Judgment on Liability. 36.I have not forgotten the fact that the parties are now in disagreement as to whether water is still finding its way from the defendant’s Premises into the plaintiff’s Premises. However, that would only have bearing on the question of whether the defendant has breached the order made on 16 May 2017 as opposed to the question of liability which has already been resolved by way of a judgment on admission. ORDER 37.By reasons of the aforesaid, the Summons is hereby dismissed. COSTS 38.I make a cost order nisi that the plaintiff shall bear the costs of the defendant of the Summons, to be taxed if not agreed. To avoid any doubt, I certify the engagement of counsel as being proper in this application. The above order nisi shall become absolute in the absence of application to vary (which shall be made by letter, if any) within 14 days hereof. Any application to vary the costs order nisi shall be dealt with on papers.
Mr Paul Wong, instructed by Ong & Chung, for the plaintiff Ms Pauline Leung, instructed by Lam & Lai, for the defendant [1] The trial was initially scheduled for 4 days [2] Joint Experts’ Report dated 19 May 2016 [3] Letter of the plaintiff’s solicitors dated 22 September 2016 [4] Paragraphs 6.1 to 6.3 of the expert’s report dated 8 March 2017 [5] The consent summons reads: “Judgment on admission be entered against the Defendant for damages to be assessed” [6] Paragraph 3 of the defendant’s written submissions [7] Paragraph 3 of the Consent Summons filed on 28 June 2019 [8] Paragraph 9 of the plaintiff’s reply submissions [9] Paragraph 53 of the plaintiff’s written submissions [10] Paragraph 54 of the plaintiff’s written submissions [11] Paragraph 55 of the plaintiff’s written submissions | ||||||||||||||
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under DCCJ 1383/2014