L v. M and Another

Read the full judgment text of HCCT 6/2021 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 27 October 2021 before Hon Mimmie Chan J.

Costs — Stay of proceedings — Arbitration agreement — Costs order nisi — Variation of costs order — Whether indemnity basis costs appropriate — Case management stay involving a party without arbitration agreement — Late provision of undertaking — Section 20 of the Ordinance — Application for stay of action to arbitration. The Plaintiff commenced proceedings against the 1st and 2nd Defendants. The 2nd Defendant applied for a stay based on an arbitration agreement in its Contract with the Plaintiff, and also for a case management stay regarding claims against the 1st Defendant, which has no arbitration clause. The 1st Defendant provided a late undertaking to abide by any arbitral award related to the 2nd Defendant's liability. Costs order nisi initially made in favour of the 2nd Defendant. The Plaintiff applied to vary costs order to no order, while 2nd Defendant sought indemnity costs. The Court held that indemnity costs were not justified given the absence of arbitration agreement with the 1st Defendant and late undertaking, and as much evidence filed was unnecessary. The order was varied to allow 2nd Defendant 50% of costs of the Summons, with the balance in the cause. Costs for variation applications follow this order.

Legal issues: Costs order variation for stay application

Outcome: Order nisi varied to allow 2nd Defendant 50% of costs of and incidental to the Summons, balance in the cause; costs of applications for variation follow this order.

Cited by 3 cases

Case No.HCCT 6/2021[2021] HKCFI 3206
Court
高等法院原訟法庭
Date27 Oct 2021
JudgeHon Mimmie Chan J
Case Document
100%Judiciary

HCCT 6/2021

[2021] HKCFI 3206

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CONSTRUCTION AND ARBITRATION PROCEEDINGS

NO 6 OF 2021

________________________

BETWEEN

  L Plaintiff
  and  
  M 1st Defendant
  N 2nd Defendant

________________________

Before:  Hon Mimmie Chan J in Chambers
Dates of Written Submissions:  12, 19 and 22 October 2021
Date of Decision:  27 October 2021

________________________

D E C I S I O N

________________________

1.A costs order nisi was made in the Decision handed down on 21 September 2021, whereby the costs of the application for stay of the action to arbitration were to be paid by the Plaintiff to the 2nd Defendant as the successful applicant.

2.The abbreviations used in the Decision are adopted below.

3.Since the stay was made not only in respect of the Plaintiff’s claims against the 2nd Defendant pursuant to the arbitration agreement contained in their Contract, but also in respect of the Plaintiff’s claims against the 1st Defendant under the Bond which contains no arbitration clause, the order nisi did not provide for costs on indemnity basis as would normally be ordered in respect of an unsuccessful challenge of an arbitration agreement.

4.The Plaintiff seeks variation of the costs order, that there be no order as to costs. The 2nd Defendant also seeks variation, for the costs to be on indemnity basis.

5.Having considered the parties’ submissions, I will vary the order nisi, to allow to the 2nd Defendant only 50% of the costs of and incidental to the Summons, with the balance of the costs to be in the cause. The following are my reasons.

6.As the Plaintiff has highlighted, the application for stay was made by the 2nd Defendant, for effectively a case management stay of the action against the 1st Defendant as well as a stay of the action against itself pursuant to the arbitration agreement. In the absence of an arbitration agreement between the Plaintiff and the 1st Defendant, there are no special circumstances or other basis for costs to be ordered against the Plaintiff on indemnity basis in respect of the case management stay sought. It was only on the day before the hearing of the Summons that the 2nd Defendant produced the undertaking by the 1st Defendant, to abide by any award made in the Arbitration as to the 2nd Defendant’s liability under the Contract, and this was an important consideration in the Court’s grant of the case management stay. I accept the Plaintiff’s submissions, that its costs in preparation for the stay application had been incurred on the basis that no such undertaking was provided, and that the associated costs should not be awarded to the 2nd Defendant. Without the application under section 20 of the Ordinance, the case management stay, even if granted, would in all probability have been granted with costs in the cause.

7.As for the stay under section 20 of the Ordinance, the authorities have made it clear that a party takes the risks of an indemnity costs order against it in the event of an unsuccessful challenge of an arbitration agreement or an arbitral award made pursuant to such agreement. The principles for the grant of a stay have been clearly set out in the authorities, and it is sufficient if a prima facie case of the existence of an arbitration agreement is established. I agree with the Plaintiff that it was unnecessary for the 2nd Defendant to file evidence on the details of the underlying disputes, and much of the evidence was totally ignored at the hearing of the Summons.

8.Bearing in mind that the Plaintiff should not be penalized by an order to pay for the 2nd Defendant’s costs which were unnecessarily incurred for the application made under section 20 of the Ordinance, and the unexplained delay in the 2nd Defendant’s production of the 1st Defendant’s undertaking in support of its application for the case management stay, a broadbrush approach warrants an order that the 2nd Defendant should only be allowed 50% of the costs of the Summons, with certificate for Counsel, on party and party basis.

9.The costs of the applications for variation follow the above order.

  (Mimmie Chan)
  Judge of the Court of First Instance
High Court

Mr Jose Maurellet SC and Mr Brian Fan, instructed by Hogen Lovells, for the plaintiff

Mr Peter Clayton SC, instructed by MinterEllison LLP, for the 2nd Defendant

Other Judgments in This Case

Further hearings and rulings under HCCT 6/2021