Ng Cheuk Hang v. Wams Design Ltd
Read the full judgment text of DCCJ 171/2018 on BabelCite. This District Court judgment was delivered on 13 January 2022.
1. There are two summons before the court:-
Cited by 4 cases · Cites 1 case
|
DCCJ 171/2018 [2022] HKDC 27 IN THE DISTRICT COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION CIVIL ACTION NO 171 OF 2018 ---------------------------------------
--------------------------------------- Before: His Honour Judge Harold Leong in Chambers Date of Hearing: 20 September 2021 Date of Decision: 13 January 2022 ----------------------- DECISION ----------------------- 1.There are two summons before the court:-
2.The court will deal with the defendant’s summons first. Background 3.This is a contractual dispute case for a renovation project. There were a large amount of documents including quotations, variations, invoices, design plans etc and many items were in dispute. 4.The judgment was handed down on 17 September 2020 but not sealed as yet. The defendant’s summons was raising issues that some of the disputed items were not mentioned in the judgment. 5.The defendant has identified 3 issues regarding the judgment, namely, the omission of some “undercharged” items in the Quotation, the omission of some “undercharged” items in a variation order, and the methodology of calculation of net balance used by the court. Adjustment of work done under items 6.9 (sensors), 12.11 and 12.26 of the Quotation version R4 dated 20 August 2017 6.There is no dispute that the Quotation signed was for budget estimation subject to final measurements (thus possible findings of both “overcharging” and “undercharging” in the Quotation). The court was involved in determining such having consideration of the experts’ opinion. 7.The final assessment by the defendant’s expert was that there were “undercharging” of these 3 items for a total of HK$13,749 and there was no contrary opinion or evidence produced by the plaintiff or his expert. 8.But these items omitted in the calculation in the judgment. Adjustment of work done in VO26 9.In the judgment, the court has omitted to take into account some items (items 9 and 10) of VO26 which were adjustments due to re-measurements of works (the light troughs in the false ceiling). These items were assessed by experts from both sides and both agreed that there were “undercharging” and therefore there should be upward adjustments. The plaintiff’s expert opined this should be HK$43,650 and the defendant’s expert HK$118,350. In either case, there was no dispute that adjustment on these items was necessary but the court did not take account of these in the calculation in the judgment. The methodology calculation of the net balance due and payable 10.The court has adopted a simplified version of the calculation which showed a different result than if the court has followed the calculation used by the experts using the same figures. Legal principles 11.Order 22 Rule 11 of the Rules of the District Court is known as the “slip rule” which provides that “Clerical mistakes in judgments or orders, or errors arising therein from any accidental slip or omission, may at any time be corrected by the court on summons without an appeal.” 12.Beyond correcting any “slips or omission”, before an order for the judgment has been drawn up or perfected, the court has a wider power to rectify mistakes in the judgment. In Tim Lee Construction Engineering Co Ltd v Kwong Wah t/a Super King Engineering Co, HCCT 18/2010, unreported (10 May 2010), it was stated:-
13.I am of the view that, in the current case, the matter does not even go as far as “reversing” a plainly mistaken decision. There is no mistake as far as the finding of accountability of each party on the issue of liability is concerned. 14.The first 2 issues raised by the defendant only concerned with the calculation of quantum regarding certain items (out of the rather voluminous numbers of items). 15.Paragraph 77 of the judgment had plainly stated that the court would, whenever assisted by experts’ report, account for any “overcharging” and “undercharging” in the renovation work. The first two issues were items which both experts agreed as being “undercharged” but yet omitted in the calculation of quantum. 16.As far as issue 2 is concerned, from reading of paragraphs 92 to 94 of the judgment, it was clear that the court was criticising that an attempt by the defendant to tease out individual structures in the design of the false ceiling and to charge each separately was “over-billing”. But there was no mention of the re-measurement of the length of the light trough which both experts agreed was “undercharged”. The physical length of the light trough had nothing to do with “overbilling the design”. As such, I do not agree with the defendant that issue 2 must necessary be the subject for an appeal. 17.Therefore, issues 1 and 2 were obviously data omitted from the calculation of quantum by mistake. They were simple omission and would not even go as far as “reversal” of a mistaken decision. 18.For the last issue, the concern was that the methodology of calculation on quantum was mistaken given the same factual findings on the figures. This would be a plain simple mistake in arithmetic. 19.As such, I cannot see why the first two issues cannot be resolved under the “slip rule”, and the third issue, if not under the “slip rule”, would have been covered by the general jurisdiction as stated in the precedents above. Bearing in mind that the gist of the judgment was that the costs and time involved in this claim was totally disproportionate to the actual size of the claim involved, it was clearly a very strong reason in the interest of justice that the plain arithmetic error be corrected without imposing further costs and time for an appeal. 20.As such, I cannot see why the issues cannot be dealt with in a corrigendum and so I would allow the application for additional judgment on all 3 issues. Plaintiff’s application to vary the cost order nisi 21.The plaintiff’s application was based upon a claimed Sanctioned Offer in a letter dated 29 April 2020 which stated:-
22.In the original judgment before the additional judgment in form of the corrigendum, the defendant would have failed to beat the claimed sanctioned offer. On this basis, the plaintiff was seeking to vary the costs order nisi to that the defendant do pay costs of the action after 30 May 2020 on an indemnity basis etc. 23.During the hearing, the court heard arguments on whether the wordings on plaintiff’s offer conformed to the requirement of a Sanctioned offer and whether the court should exercise any discretion regarding costs under the circumstances of this case. 24.However, in view of the additional judgment now putting the quantum at HK$10,588, the defendant has beaten the plaintiff’s offer so this argument is largely irrelevant. 25.The plaintiff’s application should therefore be dismissed. Costs 26.As for costs, in view that the court was not entirely with the defendant (regarding the necessity for an appeal on issue 2), that the plaintiff’s application failed only upon the additional judgment and recalculation, and, importantly, the overall circumstances of this case especially regarding proportionality of time and costs, I would give an order nisi that there be no order as to costs for both the defendant’s and the plaintiff’s applications.
Mr Forest Fong Lum Hoi, instructed by Hau, Lau, Li & Yeung, for the plaintiff Mr Yan Kwok Wing, of Fung Wong Ng & Lam LLP Solicitors, for the defendant | ||||||||||||||
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under DCCJ 171/2018