Tam Hoi Pong v. Town Planning Board
Read the full judgment text of CACV 540/2020 on BabelCite. This Court of Appeal judgment was delivered on 30 March 2022.
1. On 4 September 2020, Au JA (sitting as an additional judge of the Court of First Instance) allowed an application for judicial review of a decision (“ the Decision ”) made by the Rural and New Town Planning Committee (“ RNTPC ”) of the Town Planning Board (“ TPB ”) on 22 November 2013, in which planning permission was granted in relation to a development project at Lot 1457 RP in DD 123 and Adjoining Government Land at Fung Lok Wai, Lau Fau Shan, Yuen Long. The development site is in the Deep
Cited by 1 case · Cites 2 cases
|
CACV 540 /2020 [2022] HKCA 462 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO 540 OF 2020 (ON APPEAL FROM HCAL NO 20 OF 2014) ________________________
________________________
________________________ J U D G M E N T ________________________ Hon Kwan VP: Introduction 1.On 4 September 2020, Au JA (sitting as an additional judge of the Court of First Instance) allowed an application for judicial review of a decision (“the Decision”) made by the Rural and New Town Planning Committee (“RNTPC”) of the Town Planning Board (“TPB”) on 22 November 2013, in which planning permission was granted in relation to a development project at Lot 1457 RP in DD 123 and Adjoining Government Land at Fung Lok Wai, Lau Fau Shan, Yuen Long. The development site is in the Deep Bay area, which is an internationally renowned wetland habitat of recognised high conservation value. 2.Planning permission was granted subject to inter alia Conditions (o) and (p), which are as follows:
3.The applicant of the judicial review is the chief executive of an environmental concern group. The developer who made the application for planning permission (“the Application”) under section 16 of the Town Planning Ordinance, Cap 131 (“the TPO”), although named as the interested party, was absent in the hearing below. 4.By his judgment (“the Judgment”), Au JA held that the Decision was tainted with illegality as the TPB had acted ultra vires in approving the Application by imposing Condition (o) (“the Illegality Ground”) and that it was made in breach of the applicant’s legitimate expectation in that the TPB did not adhere to the relevant policy in approving the Application by imposing Condition (o) (“the Legitimate Expectation Ground”). He therefore ordered the Decision be quashed and remitted it to the TPB to be reconsidered in accordance with the findings of the court. 5.In essence, the judge found that “the 2011 NNCP Arrangements” (a funding and land management framework set up by the Environmental Protection Department (“EPD”) in June 2011 under the New Nature Conservation Policy Public-Private Partnership Scheme (“the NNCP PPP Scheme”) to sustain the long-term management of the ecologically sensitive portion of priority sites[1]) had been adopted by the TPB as part of its own policy under the private-public partnership approach (“the PPP Approach”). He arrived at this finding on the proper construction of the TPB policy and the planning intention. He also found that objectively viewed, the TPB must have adopted the 2011 NNCP Arrangements as part of the requirements for its own PPP Approach when it expressed support for the 2011 NNCP Arrangements at the TPB meeting held on 15 July 2011. By imposing Condition (o), the TPB had acted ultra vires as it had deferred its own duty to satisfy itself that the Application met the PPP Approach (with the 2011 NNCP Arrangements) to the Director of Environmental Protection (“DEP”) and the Director of Agriculture, Fisheries and Conservation (“DAFC”), and had breached the legitimate expectation in not requiring the 2011 NNCP Arrangements to be met. 6.The TPB has appealed against the Judgment. The applicant adopts a neutral stance in this appeal. Directions were given for this appeal to be dealt with on paper without an oral hearing. Background 7.The relevant background matters, taken mainly from the Judgment as well as from the affidavits filed by the TPB[2] and the documents exhibited, may be stated as follows. (1) The development site 8.The town planning of the development site was governed by the Lau Fau Shan and Tsim Bei Tsui Outline Zoning Plan No S/YL‑LSF/7 (“OZP”) approved in June 2001. The development site is designated in the OZP for “Other Specified Uses (Comprehensive Development and Wetland Enhancement Area)” (“OU(CDWEA)”). 9.The development site comes within the Deep Bay Area and the Mai Po Nature Reserve (“MPNR”). Deep Bay is an internationally renowned wetland habitat for a variety of species of waterfowl and a stopover point for thousands of migratory birds. The Inner Deep Bay, Mai Po Marshes and its adjacent area have been listed as a “Wetland of International Importance” (“Ramsar Site”) under the Convention on Wetlands of International Importance especially as Waterfowl Habitat (also known as the Ramsar Convention) since 1995. 10.Given the ecological importance and significance of the Deep Bay Area and the MPNR, the TPB has over time devised its own guidelines for considering applications for planning permissions for development in these areas. Separately, the Government has also announced a nature conservation policy generally for Hong Kong, which also covers the areas. It is important to have regard to how various guidelines and policies were adopted and administered by a statutory body (the TPB)[3] and a government agency (the EPD) over time, as this could have material bearing on the question whether the 2011 NNCP Arrangements had been adopted by the TPB as part of its own policy. (2) The TPB guidelines for planning applications in the Deep Bay Area 11.As far back as 1989, a set of administrative guidelines was endorsed by the Deep Bay Environmental Management Committee under the chairmanship of the DEP. The guidelines comprised the establishment of two buffer zones in the Deep Bay Area. New development would not be allowed in “Buffer Zone 1” unless it was required to support the conservation of the area’s natural features and scenic qualities. Areas further away were delineated under “Buffer Zone 2”, where new development would not be considered unless the applicant could demonstrate no significant adverse impacts on the environment, traffic and drainage in the area including the MPNR. 12.In September 1992, the administrative guidelines were presented to the TPB. The TPB formally endorsed the guidelines and issued a press release setting out the principles in considering section 16 planning applications in the Deep Bay Area. 13.On 6 August 1993, the TPB formalized the principles for considering section 16 planning applications in the Deep Bay Area in a set of TPB Guidelines, namely TPB PG-No 12. TPB PG-No 12 was revised on three occasions, in 1994, 1999 and 2014. 14.The first revision made in 1994 (TPB PG-No 12A) mainly related to the imposition of a requirement to conduct a 12-month ecological survey and the adoption of a “precautionary principle”. This is to “ensure that any proposed development which might have a threat to the environment and ecology of the area would not be allowed even if there is no conclusive scientific proof linking that particular development to the environmental or ecological damage”. 15.The second revision in 1999 (TPB PG-No 12B; referred to in the Judgment as “the TPB Guidelines”) was adopted on 19 March 1999. This laid down the cornerstone for development control in the Deep Bay Area, and came about in this way. 16.In 1997, a consultancy study commissioned by the Government on the fish ponds in the Deep Bay Area was completed, which confirmed the ecological value of the fish ponds in the Deep Bay Area and made various recommendations on conservation and land planning strategy for the same (“the Fish Pond Study”), being the continued adoption of the “precautionary principle” and a new “no‑net‑loss in wetland” principle. Buffer Zones 1 and 2 were replaced with Wetland Conservation Area (“WCA”) and Wetland Buffer Area (“WBA”) respectively. All existing and contiguous active or abandoned fish ponds should be conserved within the WCA where no new development would be permitted unless it is required to support the conservation of the area or it is an essential infrastructure project with overriding public interest. A buffer area of about 500m along the landward boundary of the WCA is designated as WBA within which developments are possible but would require an ecological impact assessment (“EcoIA”) to be carried out. 17.In taking forward the recommendations of the Fish Pond Study, the TPB adopted the Planning Department (“PlanD”)’s “Modified Option” as proposed in the TPB Paper No 5022 considered by the TPB on 18 December 1998. The boundaries of the WCA and WBA were modified. Under this option, instead of blanket conservation of all fish ponds (as one of the proposals made in the Fish Pond Study), an alternative private‑public partnership approach (“the PPP Approach” mentioned earlier) permitting limited development in the WCA areas, adopting a “precautionary approach” and “no‑net‑loss in wetland principle”, in exchange for a long‑term and better management for the conservation of fish ponds was accepted. The PPP Approach was explained in the TPB Paper No 5022 at §§30 and 31:
18.Thus, TPB PG‑No 12B incorporated the PPP Approach, the “precautionary approach” and the “no‑net‑loss in wetland principle”. It has since represented the TPB’s policy for considering planning permission applications concerning developments in the Deep Bay Area. The PPP Approach was addressed in §6.3 of TPB PG‑No 12B in these terms:
19.The TPB’s aforesaid policy relating to the PPP Approach, the “precautionary approach” and the “no‑net‑loss in wetland” was later reflected in and incorporated into the OZP in the Note to the OZP (“the Note”) and the Explanatory Statement of the OZP (“the Explanatory Statement”). 20.Insofar as the Note is concerned, the PPP Approach is referred to in the “Planning Intention” in relation to OU(CDWEA) as follows:
21.The Explanatory Statement relevantly provided in paragraphs in §§9.8.2 and 9.8.3:
22.The last revision to TPB PG-No 12 was made in 2014 (TPB PG‑No 12C). This revision mainly involved the amendment to the WCA and WBA boundaries to cover the fish ponds and associated wetland and the landward vegetated land in Hoo Hok Wai. The substance of TPB PG‑No 12B remained unchanged. (3) The 2011 NNCP Arrangements 23.Separately, the Government has a nature conservation policy which applies to Hong Kong as a whole. Following a public consultation exercise in 2003, the Government revised its nature conservation policy which became the New Nature Conservation Policy (“NNCP”) in 2004. In November 2004, the NNCP was presented to the Legislative Council Panel on Environmental Affairs in the paper entitled LC Paper CB(1) 214/04‑05 (01) (“the NNCP LC Paper”), prepared by the then Environment, Transport and Works Bureau. 24.In the NNCP LC Paper, the policy statement of the NNCP is stated at §10 as follows:
25.In summary, under the NNCP and the related implementation programme:
26.It is further stated at §§36 and 37 of the NNCP LC Paper that:
27.In June 2011, the EPD set up a funding and land management framework under the NNCP PPP Scheme to sustain the long‑term management of the ecologically sensitive portion of the priority sites (“the 2011 NNCP Arrangements” mentioned earlier). These were presented and explained to members of the Legislative Council in a paper prepared by the EPD in May 2011 entitled ECF Paper 14/2011-12 (“the ECF Paper”). As stated in the ECF Paper, the arrangements specifically applied to Fung Lok Wai, which covered the development site, and the relevant funding arrangement that should be set up under the 2011 NNCP Arrangements was further stated at §§6 and 7 as follows:
28.The 2011 NNCP Arrangements were then presented by the EB to the TPB by way of the TPB Paper 8869 at the 987th meeting of the TPB held on 15 July 2011. At the meeting, the Deputy Director (Environmental Protection) of the EPD, Mr Albert Lam, covered the main points of the 2011 NNCP Arrangements detailed in the paper as stated in §22 of the minutes of the meeting:
29.Mr Lam then answered questions raised by the meeting, at the end of which the Chairman concluded that the TPB “supported the new funding and land management arrangements to take forward the conservation and development proposals for the PPP schemes on the priority sites.” (§28 of the minutes). (4) The Application 30.The development site covers an area of 80 hectares and the proposed development involves conversion of about 76 hectares of fish ponds (95% of the development site) into a Wetland Nature Reserve (“WNR”) and 4 hectares (5% of the development Site) into a residential development. The proposed residential development under the Application comprises 19 blocks for 1,958 units with a gross floor area of 147,985m2 located at the southern landward fringe of the development site. The WNR comprises an area of 61.6 hectares retained and ecologically enhanced fish ponds and a created freshwater marsh habitat of about 14.4 hectares. The existing 31 ponds will be consolidated to form 18 large ponds. The interested party proposes to enhance the ecological values and functions through re-profiling pond bunds to form larger ponds with shallow sloping and irregular margin to increase feeding opportunities for water birds as well as active ongoing management. A potential alternative egretry (a nesting colony for egrets and other birds) of approximately 2,000m2 to replace an abandoned egretry near Shing Uk Tsuen is also proposed. 31.Before going on to the details of the Application, it is pertinent to note that because the proposed development falls within designated projects as defined in the EIAO, an environmental impact assessment (“EIA”) was required to be carried out. The EIA report was submitted under the EIAO with a funding proposal and was approved by the DEP with conditions in November 2009. This was before the 2011 NNCP Arrangements were set up by the EPD. 32.According to TPB PG-No 12B, the development site falls within WCA. As stated in the Schedule of Uses in the Note for the “OU(CDWEA)” zone, any development and filling of land/pond or excavation of land require planning permission from the TPB under the PPP Approach and the “no‑net‑loss in wetland” principle. Further, as stated in §9.8.3 of the Explanatory Statement, the development proposal to the TPB should include an EcoIA with an acceptable and feasible wetland enhancement and management scheme and a mechanism to ensure that the long-term management of the wetland could be practically implemented and monitored. 33.The interested party first submitted the Application to the TPB on 4 August 2011, with a supplementary planning statement, technical appendices including an EcoIA, Further Analysis of the Ecological Impacts of the Refined Development Layout, draft Habitat Creation[4] and Management Plan (“Draft HCMP”) for the WNR, Management Proposal for the Wetland Nature Reserve, Traffic Impact Assessment, Tree Survey and Master Landscape Submission, Environmental Monitoring and Audit Manual, Visual Impact Assessment, Environmental Assessment and Sewerage and Drainage Impact Assessment. The documents were submitted in accordance with the requirements in Remark (a) in the Schedule of Uses and §9.8.3 of the Explanatory Statement. 34.From August 2011 to November 2013, the interested party submitted further information providing clarification, revised or updated technical assessments, and responses to departmental comments on 20 occasions. The Application was circulated to relevant government departments for comment. It was also published for public inspection and comment on nine occasions between September 2011 and September 2013. All of the further information submitted by the interested party had also been made available for public inspection. A total of 745 public comments were received, with 663 objecting to and 82 in support of the Application. 35.The interested party’s submissions, the departments’ views, public views as well as the PlanD’s views were then consolidated into a RNTPC Paper No A/YL‑LFS/224F (“the RNTPC Paper”) prepared by the PlanD for the consideration of the RNTPC of the TPB at the meeting held on 22 November 2013 (“the Meeting”). (5) The RNTPC Paper 36.As set out in the RNTPC Paper, most of the departments circulated with the Application were satisfied with the technical details therein and had no objection to it. Relevant for present purpose, the DEP had the following comments. 37.The DEP confirmed that the environmental issues and findings mentioned in the Environmental Assessment were in line with the EIA Report approved under the EIAO by the DEP in 2009. However, the implementation arrangement for the WNR proposed by the interested party did notcomply with the funding and land arrangement under the 2011 NNCP Arrangements in that under the 2011 NNCP Arrangements, funding of the conservation plan is to be arranged through the ECF established pursuant to the Environment and Conservation Fund Ordinance, Cap 450 (“the ECFO”). The DEP took the view that the proposed long‑term maintenance and management plan of the interested party using a private trust arrangement did not provide for a comparable assurance on long‑term viability of the conservation plan as compared to the use of the ECF, and hence from “a nature conservation policy point of view”, she had reservation on this aspect of the Application. 38.Despite the above concern, the DEP made clear that she would have no objection to the Application if the interested party was to follow the land and funding arrangement in the 2011 NNCP Arrangements and recommended the following approval conditions for the consideration of the TPB:
39.Based on its assessment of the 2011 NNCP Arrangements, the PlanD expressed agreement with the DEP and stated as follows:
40.The PlanD then set out the suggested approval conditions for the reference of the RNTPC in §13.2 of the RNTPC Paper. Conditions (o) and (p) proposed by the PlanD were subsequently adopted by the RNTPC at the Meeting without any change when it decided to grant the Application subject to conditions. Condition (o) is a slightly simplified condition, corresponding to condition (i) put forward by the DEP[7]. Condition (p) is in the same terms as condition (ii). (6) The Meeting and the Decision 41.The Application was considered by the RNTPC of the TPB at the Meeting. A detailed presentation was made by Mr Ernest Fung, the Senior Town Planner/Tuen Mun and Yuen Long, on (among other things) the proposal and the departmental comments. In respect of the long-term funding and management, Mr Fung stated as follows:
42.Mr Fung also repeated the views of the PlanD in the RNTPC Paper mentioned earlier[9]. 43.Members raised questions with representatives of the PlanD, the Agriculture, Fisheries and Conservation Department (“AFCD”) and the EPD on issues including the NNCP PPP Scheme and the EPD’s views on the proposed funding arrangement of the interested party. 44.In response to a member’s questions on the proposed funding arrangements, it was explained by the AFCD and the EPD that the annual management fund for the WNR of about $3 million was estimated by the project proponent several years ago, that the funding arrangement had yet to be agreed between the applicant, the AFCD and the EPD, and that the amount of the annual management fund would be discussed in the submission by the interested party in future[10]. 45.As for the pros and cons of the funding arrangements proposed by the Government in the 2011 NNCP Arrangements and by the interested party, the EPD said as compared with the private foundation proposed by the interested party, the funding under the Government proposal (ie the ECF) was “more centralised and systematic, which would be more reliable and better guarantee adequate resources for the long-term conservation of the wetland.”[11] 46.During the deliberation session, a member raised objection to the Application and expressed reservation on the proposed conservation arrangement by the interested party. The minutes recorded this objection as follows:
47.In response, the Chairman said that the interested party had already submitted all the necessary technical assessments which were acceptable to relevant government departments. The Secretary to the RNTPC referred members to the precedent established in the Wo Shang Wai case in which the RNTPC granted planning permission subject to approval conditions which were the same as Conditions (o) and (p)[13]. 48.Members agreed that approval conditions (o) and (p) should be imposed as a package to ensure that the funding arrangement of the project would be implemented to the satisfaction of the EPD and the AFCD. After deliberation, the RNTPC made the Decision to approve the Application subject to 17 conditions, including Conditions (o) and (p)[14]. This appeal 49.The central issue in this appeal is whether the 2011 NNCP Arrangements of the EB constituted part of the requirements under the TPB’s PPP Approach, either generally or specifically for the development site within Fung Lok Wai, such that the TPB is bound by the 2011 NNCP Arrangements in considering the Application. The judge held in the affirmative, both generally and specifically, as a matter of construction and because the TPB must objectively be regarded to have adopted the 2011 NNCP Arrangements when these arrangements were supported by the TPB at its meeting of 11 July 2011. 50.The argument concerns the funding and management mechanism which should be put in place to ensure that the long-term management of the wetlands could be practically implemented and monitored. There are two outstanding issues. The first relates to the amount of $3 million for the annual management fund for the WNR. This does not appear to be much of an issue, as it was recognised at the Meeting that this amount was proposed several years ago and it would be discussed in the submission by the interested party in future. The other is whether the maintenance fund to be donated by the interested party should be provided to the ECF and managed thereunder or to an independent foundation as proposed by the interested party. There is no other outstanding issue in respect of the other aspects of the development site. 51.As mentioned earlier, the DEP had approved the funding proposal in the EIA report in November 2009 before the 2011 NNCP Arrangements were implemented. The funding proposal submitted in the Application followed the earlier proposal. The interested party proposed to provide the seed money to an independent, non-profit making foundation which is to take over the long-term management of the WNR and that the interested party would take sole responsibility for the management of the WNR until a designated successor is identified to the satisfaction of the Government. Further, in any event, it was required by the DEP when the EIA report was approved under the EIAO in 2009 that the interested party should submit the final funding proposal to the Advisory Council on Environment for approval before the application for the Environmental Permit is to be made. The Government would remain the final gatekeeper of the environmental aspect of the development through the grant or withholding of the Environmental Permit, so if the funding and management mechanism is not set up in a manner totally to the satisfaction of the DEP, the matter would be resolved in the application for the Environmental Permit. 52.It is apparent from the stance taken by the EPD and the PlanD at the Meeting that whilst the Government’s preference was to make use of the ECF and the mechanism under the ECFO, this was not regarded as a sticking point or a matter of principle that should stand in the way of the TPB granting planning permission for the Application. It was clearly stated in the RNTPC Paper that the DEP “has no objection to the project” provided that certain approval conditions were adopted dealing with the submission and implementation of a funding proposal in accordance with the 2011 NNCP Arrangements. Condition (o), which was imposed by the TPB at the Meeting, is the slightly simplified version of the condition proposed by the DEP. As it transpired, by accepting Condition (o) as recommended by the Government as an approval condition, the TPB had taken into consideration and given substantial weight to the 2011 NNCP Arrangements. 53.Mr Johnny Mok, SC, who appeared for the TPB[15], submitted that there is no inherent inconsistency between the TPB’s PPP Approach and the 2011 NNCP Arrangements of the EB. The two regimes apply to different stages of the developer’s application process. Submissions under the NNCP PPP Scheme would be considered by a special task force of the EB and selected proposals would be submitted to the Executive Council for approval. Thereafter, to implement the proposal, the developer would still be required to fulfil the requirements in an application for planning permission in accordance with the TPO. Whilst the TPB was entitled to, and did, take into account the 2011 NNCP Arrangements in considering the Application, the TPB was entitled to give the 2011 NNCP Arrangements such weight it considered appropriate, subject only to rationality. There was no rationality challenge in this application for judicial review. 54.Three broad contentions were raised by the TPB in this appeal:
55.These contentions will be considered in the order set out above. If the TPB had adopted the 2011 NNCP Arrangements as part of the PPP Approach under its own policy 56.In construing the documents relating to the TPB policy and the planning intention (mainly TPB PG‑No 12B, the Note and the Explanatory Statement) in the relevant context (that as the Deep Bay Area is of recognised important ecological and conservation value and thus of significant public interest, it should be protected and conserved on a long-term basis), the judge identified two objectives to be achieved:
57.Based on these objectives, the judge took the view that when the TPB expressed its support of the 2011 NNCP Arrangements when they were presented to the TPB by the EB at the meeting on 15 July 2011, objectively viewed the TPB must have adopted the 2011 NNCP Arrangements to constitute part of the requirements under the PPP Approach. This is particularly so as the PPP Approach in the TPB policy and the NNCP PPP Scheme which includes the 2011 NNCP Arrangements serve the same objective to secure the long-term conservation and enhancement of the ecological value and functions of the protected sites[17]. Alternatively, at the very least, the TPB must have adopted the 2011 NNCP Arrangements as part of the requirements under the PPP Approach for the specific purpose of considering planning application at Fung Lok Wai, which included the development site, as it was stated in EB’s presentation to the TPB at the meeting on 15 July 2011 that the 2011 NNCP Arrangements were promulgated for the development proposal at Fung Lok Wai and Sha Lo Tung[18]. 58.In respect of the first objective identified by the judge, I am inclined to agree with Mr Mok whilst it may be desirable that the TPB and the EB should co-operate with each other to conserve and enhance the ecological value and functions of the existing fish ponds or wetlands on a long-term basis, the pursuit of common objectives does not require the adoption of shared policies. As to the second objective, I also agree with Mr Mok that a development proposal can still be carefully and meaningfully scrutinised by the TPB without adopting the 2011 NNCP Arrangements as part of the requirements under the PPP Approach. What is required under §6.3 of TPB PG‑No 12B is that “The proposal should also include a mechanism to ensure that the long-term management of the wetland could be practically implemented and monitored.” This does not mean a workable mechanism must invariably take the form as suggested in the 2011 NNCP Arrangements. The funding proposal of the interested party followed the proposal in the EIA report that had been approved by the DEP in 2009. There was no suggestion that the funding proposal of the interested party was not workable. 59.The difference between a requirement that is part of the TPB policy and one that is not is that the former is binding on the TPB whereas the latter is a matter for the TPB as regards its relevance and weight in a given situation. No discretion or flexibility would be left to the TPB in the former situation. In light of this consideration, it seems to me that in construing the TPB policy and the planning intention, it is more important to have regard to how a policy had come to be adopted by the TPB as its own policy. 60.It is clear from the narrative given in the background section that this was done through a formal process. Whilst there was a good deal of interaction between the statutory body (the TPB) and the Government agency (the EB), and they often acted in tandem in the pursuit of the common goal to conserve and enhance the ecological value and functions of protected sites, formal steps were observed by the TPB in implementing its own guidelines and policies. That was the position in September 1992 and August 1993, when the first sets of guidelines were endorsed by the TPB. Where revisions were made to an existing policy of the TPB, they would be set out in a document of the TPB (such as TPB PG-No 12A, TPB PG-No 12B and TPB PG-No 12C) and would be subsequently reflected in and incorporated into the OZP in the Note and the Explanatory Statement of the OZP. There is no document promulgated by the TPB that expressly adopted the 2011 NNCP Arrangements of the EB. Nor is there anything in the Note or the Explanatory Statement of the OZP that added to or expanded upon the requirement in §6.3 of TPB PG‑No 12B. 61.Under Remarks (a)(ii) of the Note to the OZP, an applicant is required to submit documents showing “a wetland conservation and enhancement scheme, including its detailed design, wetland buffer proposals, a long-term maintenance and management plan, and monitoring and implementation mechanism” (emphasis supplied). 62.Whilst §9.83 of the Explanatory Statement of the OZP requires an applicant to submit “a wetland conservation and enhancement scheme, including its detailed design, wetland buffer proposals to mitigate the potential impacts on the existing wetland, a maintenance and management plan with implementation details, arrangements of funding and monitoring programme to ensure the long‑term management of the wetland”, the “arrangements of funding and monitoring programme” that are required to be included in the “wetland conservation and enhancement scheme” are not part of the “maintenance and management plan with implementation details”, contrary to the judge’s holding[19]. 63.Mr Mok drew attention to the words of Lord Steyn in In re McFarland [2004] 1 WLR 1289 at §24 that in interpreting statements of policy made by a public body, the primary point of reference is the text used, as the public is entitled to rely on the language of the policy statements, read in their proper context. He submitted that under the TPB’s own policy documents, only “a mechanism to ensure that the long-term management of the wetland could be practically implemented and monitored” is required to be identified. There is no requirement that a particular form (such as funding in the form of an upfront donation to the ECF under the 2011 NNCP Arrangements) must be adopted. I think that must be right. 64.Nor do I agree with the judge that objectively viewed, the TPB should be regarded as having adopted the 2011 NNCP Arrangements of the EB as part of the requirements under its own PPP Approach, whether generally or specifically for Fung Lok Wai, by merely expressing support for those arrangements at the July 2011 meeting, without more. Read in its proper context, in making the presentation at that meeting, the EB was not seeking to have the TPB endorse or adopt the 2011 NNCP Arrangements as part of TPB’s own policy, but was merely providing information to the TPB on how the EB would implement the 2011 NNCP Arrangements including the NNCP PPP Scheme for the priority sites. After that meeting, no amendment was made to TPB PG‑No 12B, the OZP, the Note, or the Explanatory Statement to incorporate the 2011 NNCP Arrangements, even though revision was made to the TPB Guidelines in 2014 which resulted in TPB PG‑No 12C. 65.For the above reasons, I think the judge was wrong to hold that the TPB had adopted the 2011 NNCP Arrangements as part of the requirements of the PPP Approach under its own policies. The TPB was at liberty to treat those arrangements as a relevant consideration, and give them such weight as it thought appropriate in all the circumstances, subject to rationality. If the TPB had unlawfully deferred its statutory duty to the DEP and the DAFC by imposing Condition (o) 66.The judge held that the TPB had acted ultra vires in approving the Application by imposing Condition (o) as it had deferred its own duty to satisfy itself that the Application met the PPP Approach with the 2011 NNCP Arrangements to the DEP and the DAFC[20]. This followed from his holding that the arrangements constituted part of the requirements under the PPP Approach either generally or specifically for application in relation to Fung Lok Wai, so the TPB had to satisfy itself that the arrangements had been met in considering whether to approve the Application[21]. 67.As I have formed the view that the judge was in error in his earlier holding, this contention may be dealt with succinctly. 68.As submitted by Mr Mok, the most important point to note here is that when the TPB approved the Application subject to conditions including Condition (o), it was on the basis that the Government had made it abundantly clear, in the RNTPC Paper and at the Meeting, that the Government “would have no objection if the applicant followed the land and funding arrangement as set out in the submission (TPB Paper No 8869 – Arrangements to Implement Conservation and Development Proposals Involving the Priority Sites for Enhanced Conservation) by the Government to the Board in July 2011”[22], namely, the 2011 NNCP Arrangements, and that the land and funding arrangement under the Government policy involved the injection of an upfront seed money to the ECF and the appointment of a competent conservation agent to apply for funds from the ECF to manage the conservation portion of the development[23]. It was in those circumstances that Condition (o) was recommended by the Government and accepted by the TPB at the Meeting. 69.Condition (o) stipulates: “the submission and implementation of a funding arrangement proposal for ensuring the long‑term maintenance and management of the proposed [WNR] to the satisfaction of the [DEP] and the [DAFC], or of the TPB”. In accordance with its terms, although the discretion to approve the funding arrangement proposal could be exercised by the DEP and the DAFC, it is likely that the DEP and the DAFC would find the proposal to their satisfaction if it involved the injection of an upfront seed money to the ECF and the appointment of a competent conservation agent to apply for funds from the ECF to manage the WNR. This discretion could also be exercised by the TPB itself, if the interested party did not submit a funding arrangement proposal to the satisfaction of the DEP and the DAFC. 70.Thus, in effect, Condition (o) would result in either the funding arrangement proposal preferred by the Government to be implemented, or, in default, such proposal would be subject to the TPB’s own approval. There is therefore no question of the TPB deferring its statutory duty to the DEP and the DAFC by leaving some critical and essential matter to be decided by them in circumvention of the TPB’s scrutiny. The DEP and the DAFC are the authorities entrusted with the implementation of the 2011 NNCP Arrangements, and have the necessary expertise concerning the setting up of the ECF and the appointment of a conservation agent. It was clearly appropriate for the TPB to rely on the DEP and the DAFC to address the issues concerning the 2011 NNCP Arrangements. Nor is this the situation where a planning condition was imposed on the footing that details would be worked out later where such details are “critical to the decision as to whether planning permission should be granted at all”. (Delight World Ltd v The Town Planning Appeal Board [1997] HKLRD 1106 at 1116E to F) 71.I would uphold the contention of the TPB that it had not unlawfully deferred its statutory duty to the DEP and the DAFC by imposing Condition (o). If there is legitimate expectation that the TPB would take into account the 2011 NNCP Arrangements in applying the PPP Approach 72.The alleged legitimate expectation is based on the 2011 NNCP Arrangements being adopted as part of the TPB’s own policy. As I have found in favour of the TPB that the arrangements have not been so adopted, the TPB is also correct that there is no such legitimate expectation. Conclusion and costs 73.I would allow the TPB’s appeal and set aside the judge’s order quashing the Decision and make an order in lieu thereof that the application for judicial review be dismissed. 74.I would make these orders nisi relating to the costs on appeal and below. The orders would be made absolute if there is no application for variation within 14 days of the handing down of our judgment. 75.The costs order for the application for judicial review would be set aside and replaced with an order that the TPB should have the costs of the application. The order that the applicant’s own costs be taxed in accordance with the Legal Aid Regulations would stand. 76.As neither the applicant nor the interested party has taken part in this appeal, I would make no order as to the costs of this appeal. Hon Barma JA: 77.I agree with the judgment of Kwan VP. Hon G Lam JA: 78.I agree with the judgment of Kwan VP and the orders she proposes.
Ho, Tse, Wai & Partners, assigned by the Director of Legal Aid, for the Applicant (Respondent) Mr Johnny Mok SC and Ms Catrina Lam, instructed by Department of Justice, for the Respondent (Appellant) [1] Fung Lok Wai, which includes the development site, is among the priority sites. [2] Affidavit of Wong Yuen Sheung Ophelia, former Secretary of the TPB, made on 8 October 2015; affidavit of Au Wai Kwong Elvis, Assistant Director (Nature Conservation and Infrastructure Planning) of EPD, made on 5 October 2015 [3] The membership of the TPB and the RNTPC comprised official and non-official members. The Chairman of the TPB is the Permanent Secretary for Development (Planning and Lands). The Chairman of the RNTPC is the Director of Planning. [4] In the RNTPC Paper, it was termed as “Conservation”. [5] RNTPC Paper, §10.1.2 [6] RNTPC Paper, §12.8 [7] Affidavit of Au Wai Kwong Elvis, §12 [8] Minutes of the Meeting, §49(b)(vi) [9] Minutes of the Meeting, §§49(f)(v), (vi) [10] Minutes of the Meeting, §§51, 53 [11] Minutes of the Meeting, §53 [12] Minutes of the Meeting, §64 [13] Minutes of the Meeting, §§65, 66 [14] Minutes of the Meeting, §§72, 73 [15] With Ms Catrina Lam [16] Judgment, §§67 to 72, 78 to 84 [17] Judgment, §73 [18] Judgment, §74 [19] Judgment, §§81, 83 [20] Judgment, §90 [21] Judgment, §75 [22] Minutes of the Meeting, §49(f)(v) [23] Minutes of the Meeting, §49(f)(vi) |
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under CACV 540/2020