深圳正高金屬製品有限公司 v. Iu Ho Construction Engineering Co Ltd
Read the full judgment text of HCCT 33/2019 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 29 August 2022 before Deputy High Court Judge H. Au-Yeung.
Construction and arbitration proceedings — Contractual dispute over supply of aluminium system formwork — Alleged breaches including defects, failure to deliver timely, and supply of wrong materials — Defendant counterclaimed substantial damages — Single joint expert opined formwork was fit for purpose, defects attributed to defendant’s workmanship — Defendant abandoned counterclaim and failed to engage counsel or cooperate with expert procedures — Plaintiff applied for leave to discontinue action — Court applies Order 21 rule 3(1), requiring good reason and costs on usual principle that costs follow event — Plaintiff showed good reason as defendant ceased participation and failed to comply with court orders — Expert report favored plaintiff and trial appearance by defendant unlikely — Court granted leave to discontinue and ordered defendant to pay plaintiff’s costs — Trial dates vacated and security for costs paid out to plaintiff’s solicitors.
Legal issues: Leave to discontinue the action and costs order
Outcome: Leave granted to plaintiff to discontinue action; defendant ordered to pay plaintiff’s costs; trial dates vacated; security for costs paid out to plaintiff.
Cited by 5 cases · Cites 2 cases
|
HCCT 33/2019 [2022] HKCFI 2685 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO.33 OF 2019 (Transferred from HCA 435 of 2018) --------------------------
------------------------- Before: Deputy High Court Judge H. Au-Yeung in Chambers (Open to Public) Date of Hearing: 29 August 2022 Date of Decision: 29 August 2022 -------------------------- DECISION -------------------------- THE APPLICATION 1.This is the Pre-Trial Review of the trial of this action which is originally scheduled for a 6-day trial commencing on 24 October 2022. 2.By summons filed on 3 August 2022 (“The Summons”), the plaintiff seeks, inter alia, the following orders from this Court:- (1) leave be granted to the plaintiff to discontinue its claim against the defendant; (2) costs of the plaintiff’s claim be paid by the defendant, to be taxed if not agreed; (3) the trial dates scheduled for 24 to 28 and 31 October 2022 be vacated; and (4) the security for costs of $600,000.00 paid into Court by the plaintiff be paid out from the Court and be released to the plaintiff’s solicitors. BACKGROUND 3.Before this Court deals with the Summons, it is necessary to set out the background of the case. 4.The present action arose out of the contractual disputes in relation to sums due and owing in the amount of around $24.85 million by the defendant to the plaintiff in relation to aluminium system formwork supplied by the plaintiff to the defendant for various construction projects in Hong Kong. 5.In the defendant’s Defence and Counterclaim filed on 31 May 2018, it was pleaded, among other things, that the plaintiff had been in breach of four agreements between the parties under which the plaintiff was engaged to design, manufacture and supply the aluminium system formwork for the construction of reinforced concrete at four different construction sites. The particulars of the alleged breach were as follows:
6.It was further alleged by the defendant that it had to try to rectify the defects itself by employing more workers and ordering materials from other suppliers, at an estimated cost of some $20.3 million. Notwithstanding these efforts, the main contractor imposed contra‑charges against the defendant by reason of the defects and breaches, estimated in the amount of about $54.08 million. 7.The defendant therefore counterclaimed damages for such losses estimated in the total sum of around $74.4 million. 8.The Defence and Counterclaim was subsequently amended on 21 May 2021, pursuant to which the defendant abandoned its counterclaim and only maintained its claims for loss and damage for the purpose of its defence of set-off. 9.By an order dated 4 January 2021, Mimmie Chan J gave leave to the parties to adduce expert evidence on liability and quantum respectively, both by a single joint expert. As far as the expert report on liability is concerned, eight expert issues had been identified. 10.The single joint expert report on liability (“the Expert Report on Liability”) was then filed on 28 February 2022 pursuant to the said Court order. In the Expert Report on Liability, the single joint expert (“the Liability Expert”) took the view that the aluminium system formworks were of merchantable quality and fit for purpose. While he agreed that there were indeed Notices of sub-standard performance issued in a number of the construction sites concerned, he opined that those defects were caused by the defendant’s sub-standard work, due to poor workmanship or failure to read the construction drawings properly, and therefore the defendant should be responsible to pay for the rectification costs. 11.On 12 April 2022, the defendant’s solicitors applied for a declaration that it had ceased to be the solicitor acting for the defendant in this action. 12.The “cease to act” order was granted on 28 April 2022, and the defendant’s solicitors formally came off the Court’s record on 13 May 2022 upon the filing of a Certificate of Service pursuant to Order 67 rule 6(1) of the Rules of the High Court (“RHC”). 13.As the defendant had all along failed to provide the single joint expert on quantum with copies of documents which were disclosed in the defendant’s own lists of documents, the plaintiff applied for an unless order from this Court. The hearing was held on 20 May 2022, at which the defendant did not turn up. 14.The order was granted accordingly on 20 May 2022, pursuant to which the defendant had been ordered to provide those documents within 8 days of the service of the order. 15.However, the order was not complied with by the defendant. 16.Apparently, after the defendant’s former solicitors had ceased to act for them, the defendant has not engaged another firm of solicitors, nor has any of its directors applied for leave to represent the defendant in this action. THE LEGAL PRINCIPLES 17.Order 21 rule 3(1) of the RHC reads:
18.The legal principles governing an application for leave to discontinue an action pursuant to Order 21 rule 3 have been succinctly summarised by To J. in Coqueen Company Limited v Chui Wai Kwan & Others (HCMP 438/2010, unreported, 8 December 2015) as follows:
19.The above principles have been applied in Perrine Chamonix Limited v Star League Limited & Another (HCA 1139/2017, unreported, 13 September 2017), in which the Court awarded the plaintiff the costs of and occasioned by the action despite the fact that leave to discontinue the action was granted. DISCUSSION Leave to discontinue and costs of the action 20.In my view, there are not only good reasons for leave to be granted to the plaintiff herein to discontinue the whole action, there are also exceptional circumstances in the present case which justify the award of costs to the plaintiff:
21.If the plaintiff goes ahead with the trial, the end result will be that it will have to spend much legal costs but only in exchange for a Judgment which is very likely to be an empty one. In my view, the Court should take this reality into account. In the circumstances of the present case, justice cannot be fully done even if the Court makes no order as to costs when it grants leave to discontinue the action, because such an order would only benefit the defendant by exonerating its liability to bear the plaintiff’s costs of the action which it would have to bear if the case goes to trial. 22.By reasons of the aforesaid, I grant leave to the plaintiff to discontinue this action and order that the defendant shall bear the plaintiff’s costs of the action (with all costs reserved), to be taxed if not agreed. Consequentially, I also order that the trial dates scheduled for 24 to 28 and 31 October 2022 be vacated. Payment out 23.Pursuant to the Order of G. Lam J. (as his Lordship then was) dated 30 April 2021, the plaintiff had paid into Court the sum of $600,000.00 as security for costs. 24.In the light of the aforesaid decision, there is no reason why the money shall remain in Court. 25.I therefore grant the order sought by the plaintiff accordingly. ORDER 26.To conclude, I make the following orders:
Mr Adrian Leung, instructed by Humphrey & Associates, for the plaintiff The defendant was not represented and did not appear | ||||||||||||||
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under HCCT 33/2019