Able Engineering Co Ltd v. Welmetal Resources Group Ltd
Read the full judgment text of HCA 51/2022 on BabelCite. This High Court CFI judgment was delivered on 22 September 2022.
1. This is an application by Able Engineering Company Limited (“the plaintiff”) for summary judgment against Welmetal Resources Group Ltd (“the defendant”) pursuant to RHC Order 14 and Order 14A on 3 questions of law set out in §1 of its summons dated 22 April 2022. At the conclusion of the hearing, this court dismissed (i) §1 (a) and (b) and § 2 of the summons; and (ii) the action, with costs in favour of the defendant, such costs to be summarily assessed. Directions were then given for their a
Cites 1 case
|
HCA 51/2022 [2022] HKCFI 2963 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO 51 OF 2022 ________________________
________________________ Before: Deputy High Court Judge Le Pichon in Chambers Date of Hearing: 22 September 2022 Date of Judgment: 22 September 2022 Date of Handing Down of Reasons for Judgment: 26 September 2022 __________________ Reasons for Judgment __________________ 1.This is an application by Able Engineering Company Limited (“the plaintiff”) for summary judgment against Welmetal Resources Group Ltd (“the defendant”) pursuant to RHC Order 14 and Order 14A on 3 questions of law set out in §1 of its summons dated 22 April 2022. At the conclusion of the hearing, this court dismissed (i) §1 (a) and (b) and § 2 of the summons; and (ii) the action, with costs in favour of the defendant, such costs to be summarily assessed. Directions were then given for their assessment in Chambers. BACKGROUND FACTS 2.On 17 April 2020, the plaintiff as buyer and the defendant as seller entered into a contract for the sale and purchase of steel bars (“the contract”) for a 2-year period commencing 1 May 2020. 3.Clause 12 of the Contract is in the following terms:
4.Between 1 May 2020 and 27 May 2021, the plaintiff placed 24 purchase orders with the defendant. 5.It is common ground that in respect of 14 of the purchase orders, the plaintiff failed to make payment within 30 days from the date of delivery. 6.In May 2021, the defendant sent the following emails to the plaintiff:
7.By 27 May 2021, the overdue payments exceeded $2.9 million. The defendant exercised its right to terminate the contract, informing the plaintiff the same day by email and by letter of its decision, stating that the contract “shall, following the terms contained and agreed therein, be terminated with immediate effect”. 8.The email was sent early that morning and the letter delivered by courier the same day. 9.In the afternoon of 27 May, the defendant received a request from the plaintiff to collect a cheque for the overdue payments which the defendant did later that afternoon and deposited it with the bank the following day. 10.Apart from the delivery made of a purchase order on 31 May, the defendant has refused to further supply steel bars to the plaintiff. 11.The plaintiff commenced this action on 12 January 2022 and issued the present summons on 22 April 2022. THIS APPLICATION 12.By its summons, the plaintiff seeks the determination and/or construction, inter alia, of the following questions of law:
CLAUSE 12 OF THE CONTRACT 13.Clause 12 of the contract confers on the defendant an express right to terminate the contract in the circumstances set out, namely, a failure by the plaintiff to pay for commodities supplied within 30 days of delivery (“the specified event”). 14.It is common ground that as at 27 May 2021, the plaintiff was in breach of its payment obligations under the contract. Clause 12 of the contract is an express provision that on its face conferred an express right of termination on the defendant on the occurrence of the specified event. 15.Ms Christine Yu, counsel for the plaintiff, submitted that the plaintiff is entitled to terminate only if the breaches amounted to a repudiation of its contractual obligations. The thrust of her submissions is that unless punctual payment is a “condition” of the contract, the defendant cannot exercise the right to terminate. 16.She submitted that clause 12, properly construed, was an innominate or intermediate term. Whether or not the defendant was entitled to terminate the contract would depend on the severity of the breach(es), the length of delay, the amount outstanding, the conduct of the plaintiff et cetera. In other words, the right to terminate only arises if the breach or breaches were repudiatory, amounting to a fundamental breach. 17.It was drawn to the court’s attention that the contract was for the supply of 15,000 MTS over a two-year period, the commodities to be supplied by partial deliveries within that period. The total value of the commodities was of the order of $49 million and the plaintiff was obligated to make full payment of undrawn quantities on or before 30 April 2022. 18.Against that background, it was suggested that the breaches that had occurred were relatively minor and were not repudiatory. 19.Reference was made to the schedule to the statement of claim. The court’s attention was directed to the fact that the invoice date as well as the invoice receipt date would invariably lag behind the delivery date by several days. The point sought to be made appears to be that, as a result, the plaintiff had less than 30 days from the date of delivery to make payment because of the time lag of several days between the date of delivery and the date of receipt of the invoice. 20.I fail to see the relevance of that submission. The contract is clear: payment is due within 30 days from the date of delivery. It could have provided for payment to be made within 30 days of the date of the invoice or the date of receipt of the invoice but that was not what the parties had agreed. 21.It was further submitted that on the occurrence of the specified event, the defendant had an option to withhold delivery instead of terminating the contract. The former was less draconian or drastic in its effect and it could not have been the intention of the parties that the defendant could resort to exercising the ‘nuclear option’ of termination when it had the option of withholding deliveries which was also “without prejudice” to the defendant’s “other remedies”. However, there was no elaboration of what those “other remedies” would be had the defendant gone down that route. 22.The plaintiff placed considerable reliance on Spar Shipping AS v Grand China Logistics (Group) Co Ltd [2017] Bus LR 663 where the English Court of Appeal considered the effect of an identical clause 11 of 3 charter parties. In pertinent part, it reads as follows:
23.The issue before the Court of Appeal is succinctly stated in the judgment of Gross LJ:
24.The plaintiff focused on the finding, upheld on appeal, that punctual payment of hire was not a condition entitling the innocent party to terminate the contract[1]. Its approach was directed at the question whether a punctual payment provision amounts to a ‘condition’ and entirely overlooks what the Court of Appeal went on to hold, namely, that if the obligation to make punctual payment was not a condition, then failure to make punctual payments entitled the innocent party to terminate the charter parties pursuant to the express provisions of the withdrawal clause in clause 11. 25.The plaintiff’s submissions disregarded the fact that clause 12 conferred an express right to terminate the contract on the occurrence of the specified event. In my view, there is no discernible difference between the express provisions of the withdrawal clause in Spar Shipping and the express right conferred by clause 12. 26.It is also clear from Spar Shipping the effect of exercising the express power to terminate puts to an end future performance obligations and also to claim the outstanding balances at the date of termination. It does not entitle the innocent party to claim damages for loss of bargain. Had the obligation been a ‘condition’, apart from its right of termination, the innocent party would be entitled to claim damages for loss of bargain. 27.In the present case, the defendant does not claim damages and the question whether the obligation to make payment within the stipulated time amounts to a condition is irrelevant and beside the point for present purposes. 28.Mr Jiang, counsel for the defendant, submitted that, given the Court of Appeal’s holdings at §§17 and 64, Spar Shipping is actually an authority that supports the defendant’s case. 29.As regards the express provision to terminate contained in clause 12, there are authorities on the subject. Under the rubric “Express provision for determination” in Treitel on The Law of Contract (15th Ed., 2020) at §18-067, it is clear that a contract may provide for one party to terminate in circumstances that do not amount to a breach or failure to perform and that such provisions can also confer a right to terminate for some specified failure to perform. Its purpose is explained at §18-075:
30.The English Court of Appeal’s decision in Kason Kek-Gardner Limited v Process Components Ltd [2017] EWCA Civ 2132 is an illustration of its application. The relevant provision before the court was clause 11.2[2] of the contract which was in the following terms:
31.The issue was whether any breach of clause 10 which was a non-remediable material breach, triggered the right of termination. Lewison LJ held (at §57) that where the parties have themselves agreed to the circumstances in which the contract may be terminated, the distinction between conditions and innominate terms does not matter. What matters is what the parties have agreed about the circumstances in which the contract may be terminated. 32.He noted (at §58) that clause 11.2 is not a blanket provision entitling the injured party to terminate on “any” breach of contract. Rather, clauses 10 and 5 are singled out for special treatment and on breach of clause 10, the innocent party was entitled to terminate the license. 33.On the issue of stipulations as to time, Treitel (at §18-117) states as follows:
34.A similar view is expressed in Chitty on Contracts, 34th Ed., 2021 (p. 1994):
35.Footnote 79 to the above extract states:
36.In my view, there is no doubt but that the defendant was entitled to terminate the contract on 27 May 2021. The questions raised in §1 of the plaintiff’s summons Questions §1 (a) and (b) 37.Given that the defendant had the right to terminate the contract when it did, questions §1 (a) and (b) are irrelevant. Accordingly, they fall to be dismissed. Question §1 (c) 38.The answer must be in the affirmative. CONCLUSION 39.As the contract has been duly terminated by the defendant, this action must be dismissed and I so order.
Ms Christine Yu, instructed by Chan, Lau & Wai, for the plaintiff Mr Zixin Jiang, instructed by Henry Yu & Associates, for the defendant | ||||||||||||||
Cases cited in this judgment
Further hearings and rulings under HCA 51/2022