Golden Concept Development Ltd v. Sun Deco Contracting Ltd and Another
Read the full judgment text of HCCT 30/2020 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 6 January 2023 before Hon Anthony Chan J.
Construction dispute concerning the fitting out works of a residential development known as The Cavaridge. The Plaintiff developer sued the 1st Defendant nominated subcontractor and the 2nd Defendant director for breach of contract, seeking damages including additional costs due to termination of the subcontract. The court held there was an implied contract between the Main Contractor PY and the 1st Defendant despite no formal signed subcontract (NSCtt), rejecting the Defendants' argument of a contract directly with the Plaintiff or collateral contract for direct payment. The Warranty from the 1st Defendant was enforceable; the 2nd Defendant's Personal Guarantee was binding but limited to Clubhouse works, and claim failed for want of attributable damages. The 1st Defendant breached the NSCtt by failure to proceed diligently and defective works, validating termination. Damages were assessed based on expert evidence, covering costs of rectification and additional expenses incurred, with reasonable allowances for prolongation. Judgment was granted to the Plaintiff against the 1st Defendant for over HK$10.8 million plus interest; claims against the 2nd Defendant and the 1st Defendant’s counterclaim were dismissed. Costs were awarded to the Plaintiff against the 1st Defendant.
Legal issues: Existence and nature of contract between Plaintiff, PY and 1st Defendant · Whether collateral contract existed between Plaintiff and 1st Defendant about direct payment · Enforceability of the Warranty by the 1st Defendant · Enforceability of the Personal Guarantee by the 2nd Defendant · Breaches of contract by 1st Defendant and validity of termination · Quantum of damages
Outcome: Judgment for the Plaintiff against the 1st Defendant for HK$10,833,049.06 plus interest; Plaintiff's claim against 2nd Defendant dismissed; 1st Defendant’s Counterclaim dismissed.
Cites 4 cases
|
HCCT 30/2020 [2023] HKCFI 68 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO 30 OF 2020 ____________________
____________________ Before: Hon Anthony Chan J in Court Date of Hearing: 24 – 25 and 28 – 30 November 2022, 2 and 8 December 2022 Date of Judgment: 6 January 2023 ________________ JUDGMENT ________________ 1.This is a construction dispute. The project in question was a residential development situated at Area 56A, Kau To Shan, Shatin, which is now known as “The Cavaridge”. The Plaintiff was the developer and Employer of the Project. Paul Y Construction & Engineering Co Ltd (“PY”) was the Main Contractor and the 1st Defendant was the Nominated Sub-Contractor (“NSC”) for interior fitting out works (there is a dispute as to who contracted with the 1st Defendant). The 2nd Defendant was (and is) a director and shareholder of the 1st Defendant. 2.The facts of this case were unexceptional. The 1st Defendant’s contract was terminated by reason of alleged breaches of contract based on defective quality of work and failure to meet the programme for completion. As a result, the Plaintiff is seeking damages based on (i) a Warranty provided by the 1st Defendant and (ii) a Personal Guarantee given by the 2nd Defendant. 3.There is a Statement of Agreed Facts filed pursuant to the directions of this court wherein a reasonably comprehensive “Agreed Chronology” as well as “Other Agreed Facts” can be found. In light of this document, this Judgment will focus on the issues and the factual disputes which have to be resolved to enable the adjudication of the issues. Issues 4.There is a List of Agreed Issues filed pursuant to the directions of this court. The issues can be boiled down to :
Contracting parties 5.It was common ground that no Nominated Sub-Contract (“NSCtt”) was executed by PY or the 1st Defendant. The Plaintiff’s case is that, notwithstanding the absence of an executed NSCtt, PY and the 1st Defendant had conducted themselves in accordance therewith so that an implied contract between them in the terms of the NSCtt was in existence at all material times. 6.On the other hand, the Defendants’ case is that the Plaintiff and 1st Defendant entered into various agreements concerning the Project, namely, the Letter of Nomination dated 29 March 2018, the Supplemental Agreement signed on 4 May 2018 and the “HK$60 Million Agreement” (so described by the Defendants) reached on 5 July 2019, whereby the Plaintiff agreed to pay the 1st Defendant directly for work done throughout the Project. 7.There was no dispute over the law on implied contract by conduct. The principles were helpfully encapsulated in Honour State Ltd v Gorgeous Textile Co Ltd [2022] HKCA 472 at [19], per G Lam JA, referring to the CFA decision in Shanghai Tongji Science & Technology Industrial Co Ltd v Casil Clearing Ltd (2004) 7 HKCFAR 79 at [38]-[39] & [48] :
8.It was not in dispute that the 1st Defendant was chosen by the Plaintiff after tender as the NSC for the fitting out work in respect of the Clubhouse of the Project, and a Letter of Nomination was accordingly issued to the 1st Defendant by the Architect, Andrew Lee King Fun & Associates Architects Ltd, dated 29 March 2018 (“L/N”). It was provided under the L/N that a NSCtt would be entered into by the 1st Defendant with PY (Cl. 5). The following paragraphs on p. 8 of the L/N were relied upon by the Defendants :
[emphasis added] 9.Mr Khaw SC, who appeared with Mr Chan for the Defendants, accepted in the course of his Opening that the above reference to “[u]pon execution of the Sub-Contract” would not exclude the application of the principles of implied contract by conduct. 10.The resolution of this issue depends largely on the evidence before the court. Before turning to the same, I agree with Mr Clayton SC, who appeared with Mr Tsang for the Plaintiff, that the Defendants’ case that the contract for the fitting out of the Clubhouse was governed by the L/N (the Supplemental Agreement and the HK$60 Million Agreement were made later) would not work for the simple reason that many of the essential contractual provisions were absent in that document and could only be found in the NSCtt, eg, payments, variation work and extension of time. That must be an important fact which has to be taken into consideration in resolving the present issue. 11.The contemporaneous documents strongly, if not overwhelmingly, suggested that the 1st Defendant and PY had conducted themselves as NSC and Main Contractor (“MC”) in accordance with the terms of the NSCtt. Indeed, those parties had in the course of the work referred to the provisions of the NSCtt. 12.The first contemporaneous document I should refer to was the Supplemental Agreement signed by the 1st Defendant not long after the L/N on 4 May 2018. By that Agreement, the 1st Defendant’s scope of fitting out work for the Project was extended to 2 Towers of apartments and the Houses. Cl. 1 and 2 of the Supplemental Agreement provided as follows :
13.Self-evidently, by signing the Supplemental Agreement, the 1st Defendant accepted the existence of a contract between it and PY. 14.To give a few further examples of the conduct of PY and the 1st Defendant :
15.Further examples where PY and the 1st Defendant referred to the provisions of the NSCtt could be found in (a) the 1st Defendant’s email in respect of “NSC Payment Application (MC IP No 30)” dated 6 June 2019[1] and (b) a Notice of Default dated 8 November 2019 from PY to the 1st Defendant[2]. 16.From the contemporaneous documents, the first time where the 1st Defendant asserted that there was no contract between itself and PY was by way of a letter dated 16 December 2019 to PY responding to its Notice of Termination dated 11 December 2019 (“N/T”). This letter carried little significance in light of the totality of contemporaneous documents. 17.In cross-examination, the 2nd Defendant (the first of 2 witnesses of the Defendants) admitted that the 1st Defendant applied to PY for interim payments as its sub-contractor, and that PY in turn made its interim payment applications (which included the 1st Defendant’s payment applications) to the Architect as MC. The 2nd Defendant agreed that such process was normal, and the only difference with the normal process in this case was that the Plaintiff was paying the 1st Defendant and other NSCs directly. 18.When asked about the absence of an executed NSCtt, the 2nd Defendant agreed that PY and the 1st Defendant just got on with the work in accordance with the NSCtt. Further, the 2nd Defendant agreed that the 1st Defendant’s NODs were given to PY pursuant to the NSCtt. It was also accepted that PY did not merely conveyed messages between the 1st Defendant and the Plaintiff as suggested in the 2nd Defendant’s witness statement. 19.There were two points of substance advanced on behalf of the Defendants to contradict the case of implied contract. Firstly, it was said the PY had consistently refused to sign a NSCtt. The only relevant document in this regard was a letter from PY to the Architect dated 4 June 2018[3] in which PY advanced a “reasonable objection to [the 1st Defendant’s] nomination” because of concern that the “late nomination” would hinder the completion of work according to the Master Programme (by 11 September 2018). Therefore, PY would require an extension of time “[f]ailing receipt of which we must reluctantly refuse to continue the execution of a sub-contract with [the 1st Defendant]”. 20.It is plain from the letter that PY was asking for an extension of time before it would agree to enter into a NSCtt with the 1st Defendant. As a matter of agreed fact, soon after PY’s letter to the Architect, the Master Programme was revised with the completion date extended by about 7½ months to 30 April 2019[4]. The very fact that PY wrote to the 1st Defendant as a NSC about the Revised Master Programme (see para 14(1) above) strongly suggested that its concern about entering into a NSCtt with the same had been resolved. 21.Further, there was only 1 document in support of this point. Assessed against the entirety of the contemporaneous documents which evidenced the conduct of the 1st Defendant and PY, it could not be said that PY had acted consistently in refusing to sign a NSCtt. Mr Richie Lui, PY’s Deputy Project Manager who was in charge of this Project (the 3rd of the Plaintiff’s 7 witnesses), said that there was no pressing need for the NSCtt to be signed. 22.By an email from the QS to the 1st Defendant dated 18 July 2018, a draft NSCtt was sent to the latter for “checking”. On 31 July 2018, the 1st Defendant replied that it had no comment on the draft contract but only the completion date stated on the same. The QS was asked to advise “if there is any updated completion dated (sic) or there will be EOT granded (sic) for the project”. The completion date stated in the draft NSCtt was 11 September 2018, which was rendered out of date by the Revised Master Programme (see para 14(1) above). 23.According to the QS’s email and the 2nd Defendant’s evidence, the draft NSCtt sent by the QS only covered the Clubhouse fitting out work but not the Towers and Houses subsequently added by the Supplemental Agreement. I believe that the totality of the evidence suggested that the issue of signing a NSCtt for the 1st Defendant’s fitting out work was overlooked or put aside in the course of events. 24.Finally, the 2nd Defendant said that between August and December 2018, he continued to make enquiry with both PY and the Plaintiff about when the formal sub-contract could be executed, and he was told that the execution would be “very problematic”. Plainly, such evidence must be carefully scrutinised in light of the totality of the contemporaneous documents (see Eu Asia Engineering Ltd v Wing Hong Contractors Ltd, unrep, HCCT 16/1990, 23 December 1991, per Kaplan J at p. 9 (3rd para)). I do not believe that the 2nd Defendant’s evidence was consistent with the contemporaneous documents or the conduct of the parties, and it does not sway me from the belief that the matter was in fact overlooked or put aside. 25.In respect of the second point, it was said that the direct payment by the Plaintiff to the 1st Defendant (after assessment by the QS as aforesaid) was inconsistent with the existence of a contract between PY and the 1st Defendant, and consistent with a contract between the Plaintiff and the 1st Defendant. I am unable to agree. 26.That issue was specifically addressed in Cl. 10 of the L/N (see also SCC-23(8) of Appendix ‘A’ to Special Conditions of Sub-Contract[5]) which provided that :
27.By the Acknowledgement at the end of the L/N and signed by the 1st Defendant, the 1st Defendant (acting via the 2nd Defendant) “confirm the acceptance of the terms and conditions stipulated in this Letter of Nomination”. 28.It is very difficult to see any real scope for argument that the direct payment arrangement was inconsistent with a contract between PY and the 1st Defendant. 29.One final point which should be made on this issue was the requirements of the Warranty and Guarantee from the Defendants (see further below). Such requirements fit with the usual contractual arrangement whereby the NSC would contract with the MC, and those documents were required to give the Employer a cause of action against the NSC (and its director) which it would not otherwise have due to the absence of a contractual relationship. 30.In the premises, I hold that there was an implied contract between PY and the 1st Defendant in accordance with the terms of the NSCtt which was not executed. Collateral contract and related arguments 31.It is convenient at this juncture to deal with the Defendants’ case of a collateral contract between the Plaintiff and the 1st Defendant based on a pre-contract discussion about direct payment. 32.The 1st Defendant’s evidence was that there was a meeting on 25 August 2017 attended by, inter alia, representatives of the Plaintiff, including the Plaintiff’s first witness Mr Chang Wing Yu (“Chang”). The purpose of the meeting was a pre-tender inspection by the Plaintiff of the quality of the previous projects undertaken by the 1st Defendant. During the course of the meeting the Plaintiff said to the 1st Defendant that it would make direct payment to the 1st Defendant for the fitting out work, thus bypassing PY in respect of whom the 1st Defendant was concerned about getting paid on time. The 1st Defendant was induced by the promise to enter into contracts with the Plaintiff, which it would otherwise have refused. 33.Chang agreed that he did discuss the issue of payment with the 2nd Defendant at a meeting (the date of which he could not recall) during which the 2nd Defendant asked the Plaintiff to pay the 1st Defendant directly. In response and “to alleviate [the 1st Defendant’s] concern”, the Plaintiff agreed. However, Chang emphasised that it would not make the Plaintiff liable to the 1st Defendant. The Plaintiff subsequently informed the Architect of the terms agreed, which were then incorporated into the L/N and accepted by the 1st Defendant. 34.The best guide to the reliability of the witnesses’ evidence was the contemporaneous documents. The L/N was in line with the evidence of Chang and not consistent with that of the 2nd Defendant or the Defendants’ case of a collateral contract. I believe that the 2nd Defendant would not have signed the L/N if its terms (in particular, Cl. 10) were inconsistent with what was agreed. 35.Indeed, in cross-examination, the 2nd Defendant agreed that the terms of the L/N reflected what was agreed in August 2017. The 2nd Defendant’s attempt to water down that answer in re-examination by saying that the L/N “… stated perhaps [the Plaintiff] would pay or not pay [directly]. So I signed [the L/N] without paying particular attention to this sentence.” Such explanation could not be taken seriously. 36.In the premises, I reject the Defendants’ case of a collateral contract that the Plaintiff was bound to make direct payment to the 1st Defendant for the fitting out works. 37.The forgoing analysis applies equally to the Defendants’ case on variation, estoppel and waiver. In light of Cl. 10 of the L/N and the 2nd Defendant’s own evidence, these arguments could not get off the ground. 38.For completeness, I am unable to accept the Defendants’ arguments based on unjust enrichment either. The 1st Defendant was entitled to be paid pursuant to the terms of the NSCtt. If it was dissatisfied with the payments made, there were provisions under the NSCtt for recourse. Enforceability of the Warranty and the Guarantee 39.The arguments here were purely legal, turning upon the proper construction of the two documents. Warranty 40.The Deed of Warranty provided that the 1st Defendant “will carry out complete and maintain the Sub-Contract Works in accordance with the terms of the Sub-Contract.” 41.The Sub-Contracts Works were the “Interior Fitting Out Works to Clubhouse” which was “intended to form part of the Main Contract Works as a Nominated Sub-Contract”. Further, the Warranty was given by the 1st Defendant “in consideration of [the Plaintiff] nominating us as Sub-Contractor for the Sub-Contract Works”. 42.Clause 13 of the L/N referred to the Deed of Warranty and required the 1st Defendant to execute it. The Defendants submitted that it was obvious from the L/N that both the Plaintiff and the 1st Defendant envisaged that the latter and PY would actually sign a NSCtt. 43.It followed, the Defendants argued, that at the material time both the Plaintiff and the 1st Defendant agreed the Deed of Warranty would not take effect except on the signing of a NSCtt between the 1st Defendant and PY. 44.Given that the 1st Defendant and PY never signed any agreement let alone a NSCtt, the condition precedent for the Deed of Warranty was never satisfied and therefore the Deed of Warranty was a conditional and unenforceable contract: Chitty on Contracts, 34th edn, [4-197]. 45.I am unable to agree with the Defendants’ submissions. The 1st Defendant was nominated by the Plaintiff as the NSC for the fitting out of the Clubhouse, the 1st Defendant in fact carried out such work and, as found by this court, there was an implied contract between PY and the 1st Defendant in accordance with the terms of the NSCtt. 46.I agree with the Plaintiff’s submission that there was no requirement stated in the Deed of Warranty to the effect that it would only take effect upon the execution of a NSCtt. There is no reason or logic for the 1st Defendant to be bound by the NSCtt, having conducted itself on that basis, and then be able to avoid the effect of the Warranty entered into due to its nomination by the Plaintiff, because no NSCtt was actually signed. 47.In the premises, I hold that the 1st Defendant is bound by the Warranty. Guarantee 48.Turning to the Personal Guarantee of the 2nd Defendant, the relevant provisions were as follows :
49.Four arguments were advanced by the Defendants in their Opening submissions against the Guarantee :
50.The first point is difficult to understand. The Guarantee was made between the Plaintiff and the 2nd Defendant and it took the form of a deed. It was “signed, sealed and delivered” by the 2nd Defendant on 29 March 2018, the same date as the L/N. 51.Clause 14 of the L/N provided that the 1st Defendant was to provide a Personal Guarantee to the Plaintiff. Preamble (C) of the Guarantee referred to the L/N and “[the 1st Defendant] entered into a [NSCtt] with [PY] to carry out the Sub-Contracts Works … as described in the [NSCtt]”. Preamble (D) went on to refer to the 2nd Defendant as the substantial shareholder of the 1st Defendant and “is willing to provide personal guarantee to the [Plaintiff] for [the 1st Defendant] …”. It is thus quite clear that, if needed, consideration was provided by the Plaintiff for the Guarantee by agreeing to appoint the 1st Defendant as the NSC for the fitting out work. 52.The same analysis set out in paras 45 and 46 above applies equally to the Defendant’s condition precedent argument for the Guarantee, and it is rejected. 53.In respect of the time barred argument, the documents showed that the NSCtt between PY and the 1st Defendant was terminated on 11 December 2019 by the N/T. The Plaintiff’s demand under the Guarantee was made on 3 July 2020 after its demand dated 13 June 2020 on the Warranty was rejected by the 1st Defendant on 18 June 2020. 54.There appears to be 2 aspects of the time barred argument: (i) the time of claim (Cl. 1.2) and (ii) the duration of the Guarantee (Cl. 1.4). 55.In my view, despite the use of different words under Cls. 1.2 and 1.4, “the terms of the [NSCtt]” and “the period of [NSCtt]” referred, on proper construction, to the same thing, ie, the duration of the NSCtt. There is thus a strong argument that the “terms” or “period” had been specifically stipulated under Cl. 1.4. I therefore agree with Mr Clayton that the time of claim argument ignored the Plaintiff’s case that the 1st Defendant had not discharged its obligations under the NSCtt and the CPC was issued only on 28 August 2020. Assuming that the Plaintiff’s claim had to be made within the duration of the NSCtt, both its letter of 3 July 2020 and the Writ[7] in this action preceded the CPC and were issued in time. This deals with argument (i). 56.The suggestion that, based on the terms of Cl. 1.4, the Guarantee had expired upon the issuance of the CPC is not a proper construction of the Guarantee as a whole. I agree with Mr Clayton that the “period” referred to in Cl. 4 was a reference to the time of breach by the 1st Defendant of the NSCtt – against which the 2nd Defendant had agreed to indemnify the Plaintiff for the resulting loss and damage. In other words, the Guarantee did not cover a breach committed by the 1st Defendant during defects liability period after Practical Completion. Such construction is the only sensible one, otherwise a claim made in time (before practical completion) but had not been resolved when the CPC was issued would become void. 57.Further, if the Plaintiff is right about the 1st Defendant’s breach of the NSCtt (see below), there can be no argument that the Guarantee had expired by reason of the Termination of the NSCtt because the 1st Defendant had not discharged its obligation under the NSCtt in full by paying damages. 58.Finally, I also agree with Mr Clayton that although the Architect had not certified the loss suffered by the Plaintiff, there was no stipulation in the Guarantee that such a certificate was a condition precedent to give rise to the Plaintiff’s entitlement to indemnity under Cl. 1.2: see Keating on Construction Contracts, 11th edn, [5-023]-[5-025], [5-028] and [5-036] to [5-038]. 59.In their Final Submissions, the Defendants made an additional argument in respect of the coverage of the Guarantee, ie, it only covered the Clubhouse fitting out works. I agree. At the time of the Guarantee, the Supplemental Agreement had not come into existence. Indeed, Recital (C) of the Guarantee referred to the L/N and the amount of the Guarantee was based on the contract sum for the Clubhouse works. 60.Mr Clayton argued that the Guarantee was for the NSCtt works which were later enlarged by the Supplemental Agreement. The problem with that argument was that the 2nd Defendant was not a party to the Supplemental Agreement[8] and there was no basis for suggesting that he had agreed to extend the Guarantee to the additional works. 61.Although the additional argument would not entirely release the 2nd Defendant of liability under the Guarantee should this court finds that the 1st Defendant had breached the NSCtt, quite fairly Mr Clayton accepted that the Plaintiff was unable to identify the damages attributable to the breach in respect of the Clubhouse works. 62.In the premises, notwithstanding that the 2nd Defendant remains bound by the Guarantee. This part of the Plaintiff’s claim must fail. Breaches of the NSCtt 63.The breaches on which the Plaintiff relied upon to justify PY’s termination of the NSCtt on 11 December 2019 were delay and defective works. On both issues, the court had the evidence of Single Joint Expert (“SJE”). Ms Wong was the SJE on programming, and Mr Cock was the one for Defects. The HK$60 Million Agreement 64.It is relevant to say a few words about the HK$60 Million Agreement before dealing with the issue of delay in completion of the fitting out works. 65.In early July 2019, arrangements were agreed between the Plaintiff and the 1st Defendant, whereby the former agreed to a payment timetable of a total sum of HK$60 Million subject to the latter meeting labour resource commitments and achieving promised site progress, with the completion of all the 1st Defendant’s works by 31 October 2019. 66.There is an undated document from the 1st Defendant (signed by the 2nd Defendant) addressed to the Plaintiff which recorded the “preliminary agreement” reached between the parties on 5 July 2019 (“5 July Letter”) wherein the abovementioned terms could be found. 67.There was no issue that the first 4 instalments, in the total sum of HK$40 million were paid by the Plaintiff to the 1st Defendant pursuant to the 5 July Letter. The Plaintiff refused to make further payment thereunder due to, it said, the failure by the 1st Defendant to meet the labour resource commitments and progress promised. Delay 68.It is uncontroversial that the completion of the 1st Defendant’s work was delayed. The extended completion date of 30 April 2019 was not met. Neither was (a) the completion date of 15 August 2019 based on a verbal confirmation by the Plaintiff and recorded in PY’s letter to the 1st Defendant dated 3 June 2019[9] or (b) the completion date of 31 October 2019 stated in the 5 July Letter. However, the parties differed on the cause of the delay. 69.The Plaintiff had identified the causes of delay as the 1st Defendant’s: (i) failure to proceed regularly and diligently; and (ii) failure to rectify defects. On the other hand, the 1st Defendant alleged that the delay was caused by the Plaintiff’s: (i) failure to make adequate payments, which resulted in the 1st Defendant’s shortage of cash flow and such shortage prevented it from engaging enough workers; (ii) failure to ensure other trades completed their works on time, which led to late handover of Site to the 1st Defendant; and (iii) causing or permitting frequent changes of design. 70.The SJE on Programming, Ms Wong, had addressed these alleged causes of delay, and also considered the extent of delay at various critical points, namely, when Notices of Default and the N/T were issued. Failure to rectify defects 71.In respect of a major defect of water leakage at the Houses (see also the evidence of the SJE on defects below), Ms Wong’s opinion were :
72.In the premises, subject to the issue of liability over the water leakage, it was a cause of delay to the completion of the 1st Defendant’s work. Although there were general allegations of poor quality of work in PY’s 1st Notice of Default[13] and 2nd Notice of Default[14] to the 1st Defendant, the water leakage appeared to be the only specific issue on quality relied upon in the N/T. Failure to proceed regularly and diligently 73.Ms Wong’s opinion regarding the 1st Defendant’s resource deployment level from July to December 2019 and its lack of intention to proceed diligently were :
74.In light of the 1st Defendant’s alternative case that its failure to deploy adequate workers was caused by payment problems for which the Plaintiff was responsible, the opinion of Ms Wong was not surprising. 75.I agree with Mr Clayton that the 1st Defendant’s failure to deploy adequate manpower was a key factor to take into account when deciding whether it failed to proceed with works regularly and diligently. Alleged payment problems 76.Ms Wong stated that she was “not able to assess the liability on payment issues”, but she went on to note that “in my experience, there is no mechanism for contractors or sub-contractors to slow down the progress of the Work in the event of non-payment.”[19] 77.In respect of the Defendants’ suggestion that the Plaintiff had failed to meet its obligation to pay for work done by the 1st Defendant, I do not believe that it was made out in the evidence. 78.The high-water mark of this allegation was the draft assessment of the 1st Defendant’s Interim Payment Application (“IPA”) No 13. IPA 13 was submitted by the 1st Defendant to PY on 25 March 2019, which was included in IPA 30 of the latter. On about 7 May 2019, the QS made its 3rd draft assessment of IPA 13 with a Net Amount Due at HK$11.245 million. 79.By its email dated 4 June 2019 to the 1st Defendant, the QS stated that: “[we] are informed that there are issues of progress, workmanship and document submissions in regard to the Interior Fitting Out Nominated Sub-Contract Works and need to be further verified by Kingboard[20], LWK[21] and Steve Leung Designers[22]. In order not to jeopardize the Main Contract Interim Payment No. 30 certification process, the payment valuation for [the 1st Defendant’s works] will be dealt with and included in the next IP after receiving final comments …”. 80.The writer of the email, Ms Hu, gave evidence for the Plaintiff as its 6th witness. She was taxed in cross-examination on the non-payment of IPA 13 in accordance with her 3rd assessment. Ms Hu stood by her evidence that there were issues concerning the provision of adequate information by the 1st Defendant and that the information was provided by the 1st Defendant in a piecemeal fashion. She said that the whole assessment process took 1½ to 2 months during which updated information was received by her. After the 1st draft assessment, she started to receive notices of workmanship and progress issues, which explained why there were so many draft assessments. 81.Ms Hu said that the assessment of IPA 13 was later suspended because of defects in the 1st Defendant’s work and the foreseeable fact that the progress could not be met by the 1st Defendant. She denied that she failed to act independently as the QS for the Project or that she simply acted on the instructions of the Plaintiff. 82.Quite apart from the fact that Ms Hu impressed me as a credible witness, her evidence was consistent with the contemporaneous documents. In particular, firstly, the terms of the 5 July Letter, written by the 2nd Defendant on behalf of the 1st Defendant, suggested that the Plaintiff was dissatisfied with the progress of the 1st Defendant’s work, which led to the promises of work force, completion dates and of the 2nd Defendant’s daily attendance on Site to inspect the progress of work. 83.Secondly, during a meeting held on Site on 6 December 2019[23] (“6 December Meeting”) attended by the representatives of the Plaintiff, QS, PY and the 1st Defendant, the 1st Defendant’s representative stated that due to its financial position the 1st Defendant was unable to pay workers resulting in their departure from Site. It was further stated that due to lack of capital, no worker was willing to carry out water testing and no proposal for rectification of water leakage could be made by the 1st Defendant. 84.Such record should be considered against the fact that after issuing the 1st Notice of Default on 13 November 2019 (with which were enclosed a letter from the Architect to PY dated 8 November 2019 and a letter from LWK to the 1st Defendant dated 7 November 2019, both referring to the 1st Defendant’s persistent poor performance and sub-standard workmanship), PY issued the 2nd Notice of Default on 22 November 2019 expressing strong dissatisfaction of the 1st Defendant’s failure to complete the Sub-Contract Works by 31 October 2019 and highlighted the water proofing problems. PY expressly relied on General Conditions of Sub-Contract, Cl. 20(a), and notified the 1st Defendant of its failure “to proceed regularly and diligently with the Sub-Contract Works”, and having “persistently neglected after notice in writing from PY to remove defective work or improper material”. 85.Thirdly, by the N/T issued on 11 December 2019, PY terminated the NSCtt with the 1st Defendant. I am unable to think of a good reason for PY to have done so if not for the delay and poor workmanship on the part of the 1st Defendant. Self-evidently, terminating the contract of a NSC at the final stage of the Project would result in many problems, such as finding a replacement contractor. In this case, the replacement contractor was only able to complete the works on 31 March 2020. 86.Contrary to the suggestion that the Plaintiff was underpaying the 1st Defendant, Ms Hu’s evidence, which I accept, was that the HK$40 million paid to the 1st Defendant under the HK$60 Million Agreement were booked as “on account” payments by the Plaintiff because based on site inspection and other information available to the QS, the payment actually due to the 1st Defendant would be in the negative. 87.Finally, Mr Clayton’s submission that there was no provision in the NSCtt which permitted the 1st Defendant to slow down its progress due to a payment dispute was not disputed by the Defendants. Any such dispute (there were of course contractual provisions for the resolution of payment disputes), could not justify the 1st Defendant’s failure to proceed regularly and diligently with its works (see West Faulkner Associates v London Borough of Newham (1994) 71 BLR 1, at 14F and Vivergo Fuels Ltd v Redhall Engineering Solutions Ltd [2013] EWJC 4030 (TCC), [402]). Alleged obstruction by other trades & late handover 88.Ms Wong had considered in detail the evidence of the 2nd Defendant regarding obstruction by other trades. She summarized her opinion as follows :
89.Similar opinion was expressed by Ms Wong in respect of the effect of late handover of the Clubhouse to the 1st Defendant. Her opinion was set out in §§10.80 to 10.90 of her Report and summarized in §10.90 as follows :
90.Hence, Ms Wong was unable to ascertain any critical delay caused to the 1st Defendant’s works due to the late handover of the Clubhouse. 91.Ms Wong was cross-examined by Mr Khaw on the above matters. She was taken to various documents by which the 1st Defendant had referred to alleged causes of delay. However, she remained unshaken on her evidence that without evidence on how those alleged causes had impacted upon the critical path of the 1st Defendant’s works, no assessment of delay could be made. I see no reason to doubt Ms Wong’s evidence. 92.On the late handover of the Site. Ms Wong pointed out that there were IPAs made by the 1st Defendant prior to the handover indicating that some of the works were carried out. Further, I note that in its memo to PY dated 17 December 2018 (shortly before the alleged late handover on 27 December 2018[25]), the 1st Defendant submitted a programme which provided for completion on 23 April 2019 (consistent with the Revised Master Programme). 93.Finally, on 24 June 2019, the 1st Defendant issued its NOD No 2 to PY stating that its works had been delayed for 30 days by the late installations by E&M NSC. Photos of the whiteboard of lunchbox meetings on 8 January, 26 February, 19 March, 2 and 9 April 2019 were attached evidencing that the delay had been discussed previously and that the Plaintiff, PY and all the contractors knew about it. 94.In this regard, Ms Wong stated that: “… EOT shall be granted if the Judge decides that the ‘$60M Agreement’ has not already covered the delays entitlement”. In light of the timing of the 5 July Letter, and the completion dates promised by the 1st Defendant contained therein, I take the view that this NOD No 2 must have been fully taken into account by the 1st Defendant. Alleged design changes 95.On this cause of delay advanced by the 1st Defendant, Ms Wong had reviewed the supporting documents and expressed her opinion as follows :
96.Again, similar comment was made by Ms Wong in respect of the variation orders relied upon by the 1st Defendant :
Delays at various critical points 97.Ms Wong provided her opinion regarding the extent of delays at 3 critical points of time when the Notices of Default and N/T were issued by PY :
98.Ms Wong’s evidence was tested under cross-examination by Mr Khaw. This court has no reason to disagree with the assessment of Ms Wong. It is trite that a contractor seeking extension of time to complete its work must provide proper support for its claim. Typically, supporting documents for the delaying event, as well as an analysis of how such event impacted upon the critical path for the contractor work would be provided. It was quite clear from the cross-examination of Ms Wong that there was no such information provided by the 1st Defendant. 99.In my view, the evidence of failure to proceed regularly and diligently by the 1st Defendant was fairly overwhelming. As pointed out by Mr Clayton, the Notes of the 6 December Meeting[30], §§5, 13, 16 and 18, recorded that the 1st Defendant made it abundantly clear that it would not further proceed with the works without additional payment, which was not due in accordance with the certified IPCs and not going to be paid. It appeared that PY had little option but to terminate the NSCtt as it did a few days later. Defects 100.The Plaintiff’s evidence was that various defects in the 1st Defendant’s works were identified and the 1st Defendant was notified of the same regularly. Of particular significance were the water leakage problems discovered in early November 2019. Despite repeated reminders, the 1st Defendant failed to rectify the water leakage. It was one of the grounds relied upon by PY in terminating the NSCtt. 101.After termination, through its solicitors the Plaintiff retained a defects consultant, Mr Carmine Siu (the Plaintiff’s 7th witness) to carry out inspection and prepare “Inspection Records”, which formed the basis of part of the claims in this action by the Plaintiff. Mr Siu’s evidence was not challenged. 102.The SJE on defects, Mr Cock, had prepared a report setting out his opinion on, inter alia, the defects at Termination. 103.It should be made clear that “defects” had been given a wide meaning to include both unsatisfactory and outstanding works under two groups: (i) General Defects in Annex 1 to the Plaintiff’s Further and Better Particulars (“FBP”); and (ii) Particular Defects in Annex 2 to the FBP. General defects 104.As analysed by Mr Cock, there were 1,778 line items of alleged General Defects and over 7,700 instances pleaded (each alleged defect within a particular Unit was referred by Mr Cock as an “instance” of the relevant line item)[31]. 105.In respect of Question 1 for Mr Cock: “Identify the Sub-Contract Work and/or the Additional Works and/or Variation Works, which pursuant to the terms of the Nominated Sub-Contract and the Supplemental Agreement, remained outstanding as on 11 December 2019?”, he opined that 880 of the line items were outstanding works, and all 880 line items did in fact remain outstanding on 11 December 2019[32]. 106.In response to Question 2: “Whether the Sub-Contract Work and/or the Additional Works and/or Variation Works completed as on 11 December 2019 were defective or non-compliant?”, Mr Cock carried out checking by selecting 1,200 instances (out of 7,772) representing about 945 line items (out of 1,778) for the General Defects pleaded in the FBP[33]. 107.Mr Cock summarized his opinion regarding the General Defects in a table (Annex JEC-E to his Report[34]). The average percentage of Non-Compliant (“NC”) was assessed as 91.3%, which included both outstanding works and defective works (the General Defects included both). 108.Since all outstanding works pleaded had been accepted by Mr Cock as so (ie, 100% NC), therefore the average percentage of NC items for defective works pleaded should be less than 91.3%. 109.Table 7 of Mr Cock’s Report[35] provided a summary of the NC items. The vast majority of NC items were incomplete works, most of which were in the Houses, followed by the Flats (about 70% of line items categorized as NC). Next were snagging items (just under 30% of items categorized as NC). Only 2 line items were considered serious defects, namely, “Wrong stone material for door threshold” and “Wrong type of toilet door”[36]. However, there were 2 other potential serious defects (“Wong stone material at the threshold of the entrance” and “Single layer gypsum board in ceiling”) depending on this court’s finding on liability for the defects[37]. 110.In respect of the 4 categories of Particular Defects (Floor Drains, Toilet Mirror Box Finish, Waterproofing System and Door Heights), Mr Cock expressed his opinion in sections 22 to 25 of his Report respectively. 111.On Category 1: Floor Drains, Mr Cock opined that 2 of the 5 blocked floor drains were shown to be blocked due to cementitious material that had been poured. He was unable to express a view as to who was responsible for the blockage[38]. Quite properly, Mr Clayton took the view that since this was only a minor defect, it does not merit separate consideration. 112.On Category 2: Toilet Mirror Box Finish, Mr Cock stated that he was not aware of any evidence to support the Plaintiff’s claim[39]. However, he was taken by Mr Clayton to, inter alia, the Inspection Record at G4/34478-34482. In light of Mr Cock’s evidence after having been shown the Record, I am satisfied that the Plaintiff was entitled to have the Mirror Box defects rectified at the cost of the 1st Defendant. 113.On Category 3: Waterproofing System, Mr Cock opined that the evidence did not support defective materials or workmanship in the 1st Defendant’s waterproofing works as constructed up to the date of the last Floor Test Record on 19 August 2019[40]. On the other hand, whether leakage was caused by subsequent damage and whether that was caused by the 1st Defendant or others were questions of fact on which Mr Cock expressed no opinion[41]. 114.In preparing his Report, Mr Cock had considered the Water Test Inspection Record and Water Test Videos prepared by Mr Siu and observed that the evidence appeared to record failed water testing on 24-27 December 2019 after the 1st Defendant had left the Site[42]. 115.In cross-examination, Mr Cock was referred by Mr Clayton to (a) the Water Leakage Tests and Open-up Inspection Record of Mr Siu; (b) the uncontested evidence of the Plaintiff’s Clerk of Works, Mr Cheung Wai Wing (the Plaintiff’s 2nd witness), who noticed damage to waterproofing due to the 1st Defendant drilling holes through the waterproofing for installing the channel for shower tray (which was also the 1st Defendant’s work); and (c) the contemporaneous correspondence between LWK and the 1st Defendant on damage to the waterproofing. 116.In answer, Mr Cock accepted that if the water membrane was drilled through and no sealant was applied over the bolts, water leakage was likely to occur. In light of such evidence and the documents, I accept the Plaintiff’s case that there was damage to the waterproofing and the 1st Defendant was responsible for the same. 117.Finally, Mr Clayton’s submission that even if the damage to waterproofing had been caused by other sub-contractors, the 1st Defendant would still have been responsible for making good the damage was supported by Cls. 6.5(a) and 6.14 (c) of Section A – General Preliminaries of the NSCtt. In short, those provisions required the 1st Defendant to protect its works against damage and to make good such damage. Further, the 1st Defendant remained fully liable for the conditions of its works until the date of Practical Completion. No contrary submission had been made on behalf of the Defendants. 118.On Category 4: Door Heights, Mr Cock noted that the existence of such defects was admitted and no opinion was required from him. Hence, the 1st Defendant was responsible for such defects. 119.Mr Cock was also cross-examined by Mr Chan on behalf of the Defendants :
Findings on delay, defects and the Termination 120.In light of the above evidence and analysis on delay, I find that the 1st Defendant was in breach of the NSCtt in failing to proceed regularly and diligently. It had failed to meet the proposed completion dates set out in its 5 July Letter. 121.The unsatisfactory and outstanding works of the 1st Defendant had been dealt with above. Given the lack of completion by the time of Termination of the 1st Defendant’s contract, the existence of outstanding works was unsurprising. There was ample evidence proving the defective works of the 1st Defendant. In particular, the water leakage was a serious defect which the 1st Defendant had failed to rectify despite PY’s complaints. 122.In the premises, I hold that the 1st Defendant was in default under the NSCtt. The 1st Defendant continued with those defaults despite having received the 2nd Notice of Default, and PY’s Termination of the NSCtt on 11 December 2019 was validly made. 123.For completeness, I do not accept that PY was simply acting under the Plaintiff’s instructions in issuing the N/T as suggested by the Defendants. Self-evidently, the N/T was issued by PY for which it must be responsible. Quantum 124.First of all, the Counterclaim does not fall for consideration for obvious reason. However, I do not believe that the 1st Defendant would be disadvantaged by not being able to make a claim against the Plaintiff for unpaid work because it will be seen below that the Plaintiff’s claim would take into account the value of all the 1st Defendant’s works. 125.Due to the 1st Defendant’s breaches of the NSCtt which led to the termination by PY, the Plaintiff had suffered 2 heads of damage: (a) the additional costs incurred to complete the contract works (including rectifying the 1st Defendant’s defective works) and (b) the prolongation claim by PY for the period from 11 December 2019 (date of termination) to 31 March 2020 (date of completion of work by the contractors who replaced the 1st Defendant). Additional Costs Costs for completing outstanding works and rectifying defects 126.There are 3 basic components for working out this claim: (a) Total payments made to the 1st Defendant (agreed at HK$99,886,000); (b) Costs of completing the outstanding works and rectifying the defective works; and (c) Notional final sub-contract sum. By adding (a) and (b), the total costs incurred by the Plaintiff can be ascertained. Subtracting the notional final sum from the total costs will produce the additional costs incurred by the Plaintiff. There was no disagreement to this formula. 127.The reasonable costs for completing the outstanding works and for rectifying the defective works had been considered by the SJE for Quantum, Mr Cheung, in sections 9 and 10 of his Final Report on Issue 7 (valuation of the reasonable costs for completing the outstanding works) and Issue 8 (valuation of the reasonable costs for rectifying the defective works). 128.In coming to his valuation, Mr Cheung had considered all the relevant materials, including quotations, payment records, letters of nomination and Architect’s Instructions of nomination for replacement sub-contractors. Mr Cheung considered that the extent of General Defects (together with outstanding works), the Particular Defects, the extent of remedial works, and the scope and extent of works had been broadly identified. 129.In his summary of assessment (§1282), Mr Cheung allocated the replacement sub-contractors’ costs under 3 main headings: (a) Rectifying Defects at HK$27,423,217.25; (b) Outstanding Works at HK$54,100,477.79 (this was not contentious[43]) and (c) Variation Works at HK$1,265,273. 130.Quite rightly, Mr Clayton did not pursue the costs of Variation Works because they were regarded by Mr Cheung as betterment. 131.The reasonable costs for rectifying the defects (HK$27,423,217.25) could be sub-divided between General Defects (HK$18,373,331.25) and Particular Defects: Waterproofing (HK$3,370,460); Mirror Boxes (HK$1,272,639); and Doors (HK$4,406,787). This court has found that the 1st Defendant is liable for all 3 Particular Defects (see paras 112, 116 and 118 above). 132.As regards the General Defects, Mr Clayton adopted a percentage for which the 1st Defendant is liable (75.66%) based on the Mr Cock’s Report[44]. 75.66% of HK$18,373,331.25 is HK$13,901,102.80. 133.The total costs for completing outstanding works and rectifying defects are: Particular Defects (HK$3,370,460 + HK$1,272,639 + HK$4,406,787) + General Defects (HK$13,901,102.80) = HK$22,950,988.80. Adding it to the Outstanding Works (HK$54,100,477.79) gives the total of HK$77,051,466.59. 134.In my view, the above quantification is properly supported by the evidence, as well as the analysis of Mr Clayton to which Mr Khaw did not offer any valid opposition. It is right to point out that there was an element of broad brush approach adopted in the quantification, eg, the assessment of the costs of rectifying the General Defects. However, I believe that the approach is justified and proportionate in light of the very large number of defective items (see Mr Cock’s Report, §20.2[45] and Mr Cheung’s Report, §1234[46]). I bear in mind also the principles referred to in Chun Wo Building Construction Ltd v Metta Resources Ltd, unrep, HCCT 29/2013, 19 August 2016, [255]. Notional final sub-contract sum 135.This component was considered by Mr Cheung in section 3 of his Final Report on Issue 1 (valuation of the notional final sub-contract sum), and had been summarized to be within a range from HK$167,001,754.92 to HK$175,207,080.13. The reason for the range was that the assessments for the variations were made in a range from HK$42,492,594.92 to HK$50,697,920.53. 136.The Plaintiff contended that the total value of Variations should be in the sum of HK$44,073,881.72. By adopting that sum for “Sub-Total (3)” of the table in §56 of the Final Report[47], the notional final sub-contract sum should be HK$168,583,041.32. 137.The justifications for the valuation of Variations at HK$44,073,881.72 had been set out in a 11-page Attachment 1 to the Plaintiff’s Opening Submissions, plus enclosed supporting documents. However, I agree with Mr Khaw that the detailed analysis set out in Attachment 1 had not been adequately covered by the factual evidence. It would not be appropriate for this court to, in effect, carry out a paper assessment of the value of the Variations. 138.On the other hand, I see no sufficient reason to adopt the higher end of the range as suggested by Mr Khaw because it was premised on the assumption that all the factual and liability issues in relation to the assessment for the notional value were found in favour of the 1st Defendant. Doing the best I can and adopting a broad brush approach, I adopt the median of the range as the notional final sub-contract sum: HK$171,104,417.53. Conclusion on Additional Costs 139.The Plaintiff’s claim for additional costs incurred to complete the Sub-Contract Works becomes :
PY’s prolongation claim 140.The Plaintiff relied upon its Voluntary Particulars, §§1 to 3, which set out the basis and quantum of this claim :
141.The evidence suggested strongly that the NSCtt of the 1st Defendant would not have been terminated if not for the delay and defects of its fitting out work. There was no sensible reason for PY to choose to termination the NSCtt if the situation was tolerable. The Plaintiff’s evidence was that there was a pressing need to have the Clubhouse ready to be used as the sales office for the Development. Clearly, the delay had got to a point where PY had little choice but to look for replacement contractor(s) to complete the fitting out work. 142.Further, there is no reason to believe that the Plaintiff had not acted reasonably in nominating replacement fitting out contractors given the prevailing delay and its need to have the work completed as soon as possible. If there was available a reasonable replacement contractor who could have completed the work before 31 March 2020, it was unlikely for the Plaintiff not to have chosen it. 143.Based on the authorities cited by Mr Clayton, I am satisfied that PY’s prolongation claim was attributable to the breaches by the 1st Defendant of its NSCtt, and the Plaintiff is entitled to be compensated by the 1st Defendant under the Warranty for what it had paid in respect of such claim: see Keating on Construction Contracts, 11th edn, [13-076] to [13-078]; Bickerton v NW Metropolitan Regional Hospital Board [1970] 1 WLR 607, at 613A-E; Fairclough Building Ltd v Rhuddlan Borough Council 30 BLR 26, at pp 41-42; and Percy Bilton Ltd v GLC [1982] 1 WLR 794, 802C-D. 144.As for the quantum of this claim, PY’s prolongation claim was settled by the Plaintiff in the sum of HK$10 million. The Plaintiff accepted that the settlement with PY embraced more than the delay occasioned by the need to nominate replacement contractor for the fitting out. The Plaintiff relied on Mr Cheung’s assessment of PY’s prolongation costs from 11 December 2019 to 31 March 2020 at HK$7,540,186.53[48]. 145.Mr Khaw took issue with 2 elements of the assessment, namely, the expenses under “Other expense” and the statutory levy percentage. There is some force in the submissions. However, given that the sum of HK$10 million was arrived at as a commercial settlement, it is pointless to try to make a precise adjustment based on the Defendants’ objections. 146.Doing the best I can and adopting a broad brush approach whilst using Mr Cheung’s assessment as a guide, I award the sum of HK$5,000,000 under this head of claim. The discount is justified given the lack of clarity on how much of the settlement sum was attributable to the prolongation resulted from the Termination. Disposition 147.I give judgment in favour of the Plaintiff against the 1st Defendant in the sum of HK$10,833,049.06 with interest at prime rate(s) plus 1% from 13 June 2020 (date of the Plaintiff’s demand made to the 1st Defendant[49]) to date of judgment and thereafter at judgment rate(s) until payment. 148.The Plaintiff’s claim against the 2nd Defendant is dismissed, and so is the 1st Defendant’s Counterclaim against the Plaintiff. 149.As between the Plaintiff and the 1st Defendant, the costs of this action and the Counterclaim, with a certificate for 2 counsel, be paid by the 1st Defendant to be taxed if not agreed. I make no costs order in respect of the action against the 2nd Defendant. All costs orders are made on nisi basis. 150.Last but not least, I am grateful for the assistance of counsel.
Mr Peter Clayton SC and Mr David Tsang, instructed by Fung, Wong, Ng & Lam LLP Solicitors, for the Plaintiff Mr Richard Khaw SC and Mr Anthony HK Chan, instructed by SK Wong & Co, for the 1st and 2nd Defendants [1] G2/17826. [2] G1/7847. [3] G1/6213. [4] By an Extension of Time Assessment dated 16 August 2018 from the Architect to PY, the completion date was formally revised. [5] CB/37. [6] The 1st Defendant was defined as the NSC under the Guarantee. [7] The Writ in this action was issued on 8 July 2020. [8] Quite rightly, this additional argument was not advanced in respect of the Warranty. [9] CB/746. [10] §10.9. [11] It was issued by PY. [12] §10.14. [13] CB/1462. [14] CB/1654. [15] §10.21. It was based on the records kept by Mr Cheung Wai Wing, the Plaintiff’s Clerk of Works for the Project and its 2nd witness, which was not challenged. [16] §10.22. [17] §10.23. [18] §10.24. [19] §10.97. [20] The Plaintiff’s parent company. [21] The Resident Designer for the Project. [22] The Clubhouse Designer. [23] Record of meeting at D/1288. [24] §§10.76 to 10.79. [25] Mr Richie Lui’s evidence was that the handover took place in November 2018 despite the letter at CB/511. [26] §10.94. [27] §10.96. [28] §12.9. [29] §12.10. [30] D/1288. [31] §§13.4 and 13.5 of the Defects Report. [32] §§15.2-15.4. [33] §20.7 and Table [34] F1/2189. [35] Report, E/1454. [36] §20.10.1. [37] §20.10.2 [38] §22.9. [39] §23.3. [40] §24.13.1. [41] §24.13.3 [42] §§24.1-24.6. [43] See Defendants’ Closing Submissions, §153. [44] See Table 7 at E/1454: Ignoring the Incomplete Works (880), adding together Serious Defects (2) and Snagging Items (371) = 373. By dividing 373 with 493 (373 plus Non-NC Items (120)) and multiply by 100% = 75.66%, which broadly reflected the quantum of defective works. [45] E/1450. [46] E/1980-396. [47] E/1980-27. [48] E/1980-433, §1399. [49] CB9/2008. |
Cases cited in this judgment