Shenzhen Baoming Ceramics Co Ltd v. Companion-china Ltd
Read the full judgment text of CACV 93/2000 on BabelCite. This Court of Appeal judgment was delivered on 17 May 2000.
1. In May 1997, the Plaintiff, Shenzhen Baoming Ceramics Co. Ltd, concluded an agreement ("the original agreement") with the Defendant, Companion-China Ltd, for the manufacture by the Plaintiff and the sale to the Defendant of quantities of ceramic tiles. By a subsequent agreement concluded in September 1997 ("the settlement agreement"), the parties agreed that they should be discharged from performing their obligations under the original agreement. One of the terms of the settlement agreement w
Cited by 9 cases
|
CACV000093/2000 CACV 93/2000 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO. 93 OF 2000 (ON APPEAL FROM HCA NO. 9059 OF 1999) ______________
______________ Coram: Godfrey V-P and Keith JA in Court Date of Hearing: 3 May 2000 Date of Judgment: 17 May 2000 _______________ J U D G M E N T _______________ Keith JA (giving the judgment of the Court): Introduction 1. In May 1997, the Plaintiff, Shenzhen Baoming Ceramics Co. Ltd, concluded an agreement ("the original agreement") with the Defendant, Companion-China Ltd, for the manufacture by the Plaintiff and the sale to the Defendant of quantities of ceramic tiles. By a subsequent agreement concluded in September 1997 ("the settlement agreement"), the parties agreed that they should be discharged from performing their obligations under the original agreement. One of the terms of the settlement agreement was that certain payments would be made by the Defendant to the Plaintiff, and the settlement agreement included a timetable setting out the deadlines for those payments. 2. In due course, the Plaintiff commenced proceedings against the Defendant. One of its claims was that sums of $2,349,394.86 and RMB7,447.86 (which were part of the sums owed by the Defendant under the settlement agreement) had not been paid. The Plaintiff applied for summary judgment for these amounts plus interest under Ord. 14. The Defendant admitted that sums totalling $1,859,755.88 due under the settlement agreement had not been paid. Master Lau gave the Plaintiff summary judgment for that amount plus interest, and gave the Defendant unconditional leave to defend the balance of the Plaintiff's claim. 3. The Defendant appealed against the award of summary judgment. The appeal was heard by Cheung J. He allowed the appeal, and gave the Defendant unconditional leave to defend the whole of the Plaintiff's claim. The Plaintiff now appeals. It seeks to have Master Lau's orders restored. The defence of agency 4. The defence which caused the judge to grant the Defendant unconditional leave to defend the whole of the Plaintiff's claim related to the status of the Defendant. The Defendant's case was that when it entered the original and subsequent agreements it was not acting as principal. It was acting as an agent, and entered the agreements as agent for and on behalf of Saint Galarie Tiles Ltd ("SGT"). Both the fact of this agency, and the identity of the principal, were said to have been disclosed to the Plaintiff. Accordingly, it was said that the Plaintiff's claim for the amounts unpaid under the settlement agreement could not succeed against the Defendant, and that the Plaintiff's cause of action was against SGT. The judge allowed the appeal because he thought that this defence raised a triable issue. 5. The basis on which the Defendant claims that it was acting as the agent of SGT appears from the affirmation of Leung Kwok Wa, one of its directors. In essence, Mr Leung's evidence was that the Defendant is a member of the Companion Group of Companies. It is principally engaged in investment holding. It is not one of the operating companies in the Group, and owns no factory or machinery. SGT is its wholly-owned subsidiary. It is SGT which carries on the business of supplying ceramic tiles to local and overseas customers. That was known to the Plaintiff's representative with whom Mr Leung negotiated the original agreement. Since
Mr Leung thought that "it would be better to use the Defendant's name to enter" the original agreement with the Plaintiff. Accordingly, he told the Plaintiff's representative that the agreement "would be signed in the name of the Defendant but the buyer was SGT". He mentioned that both during the visit of the Plaintiff's representative to SGT's retail outlets in Hong Kong and when the terms of the original agreement were finalised on the mainland. He claims that on neither occasion did the Plaintiff's representative raise any objection. 6. Mr Leung's evidence on the topic concluded with the following statement:
It was on the basis of this extrinsic evidence from Mr Leung that the judge held that there was a triable issue as to whether the Defendant was liable to the Plaintiff for the sums due under the settlement agreement. The admissibility of the extrinsic evidence 7. The admissibility of extrinsic evidence is the subject of Art. 102 in Bowstead and Reynolds on Agency, 16th ed. At para. 9-037, the authors write:
A similar statement of principle appears in Halsbury's Laws of England, 4th ed., vol. 1(2), para. 137:
That is to be contrasted with the case of an agent who "contracts in his own name but not in terms which are consistent only with his having done so as principal". In such a case, "oral evidence may be admitted to prove the identity of the principal". These are also quotations from Halsbury, op. cit., para. 137, as is the statement that "[w]hether he has contracted in such terms or not depends upon the construction of the particular contract". 8. Against this background, we turn to the agreements themselves. Both of them were in Chinese, but they have been translated into perfect English. Although the translation has not been certified, there is no dispute that the translation is correct. The Defendant is named in each of the agreements as the contracting party, each of the agreements was signed by a person who purported to be a representative of the Defendant, and who purported to be signing the agreements on behalf of the Defendant, and each of them bore the Defendant's chop. So far as the original agreement is concerned, although it provided for the tiles to be delivered to SGT,
Indeed, the settlement agreement referred to the fact that it was the Defendant which owed the sums unpaid under the original agreement. So far as the settlement agreement itself is concerned, it required the Defendant to pay the sums due under the settlement agreement. 9. Having looked at the two agreements as a whole, it is plain that the Defendant contracted with the Plaintiff in such terms as to imply that it was the real and only principal and in terms which are consistent only with it having done so as principal. It follows that the conditions necessary for Mr Leung's extrinsic evidence to be admissible have not been satisfied, and that the Defendant has to be treated as the party with whom the Plaintiff contracted. For these reasons, the defence of agency does not, in our view, raise a triable issue. The defence of set-off 10. Since the judge was giving the Defendant unconditional leave to defend the whole of the Plaintiff's claim on the basis of the defence of agency, he understandably did not address the question whether any of the Defendant's other pleaded defences raised triable issues. Mr Francis Yip for the Defendant relied only on one other pleaded defence as raising a triable issue, and that is the defence of set-off. 11. The Defendant's pleaded case is that in September 1998 another agreement was entered into with the Plaintiff ("the third agreement"), this time for the purchase of 60,000 tiles in order to fulfil a contract which SGT had concluded with one of its customers. However, a substantial number of the tiles delivered to SGT pursuant to the third agreement were defective. In the light of SGT's inability to honour its agreement with its customer, SGT's customer terminated that agreement, and SGT suffered losses under various heads amounting to $5.2m. The Defendant, alternatively SGT, claim that sum from the Plaintiff, and they claim that one or other of them is entitled to set off that amount by way of defence to the Plaintiff's claim. 12. The question which arises is which of the Defendant or SGT was the contracting party with the Plaintiff in the third agreement. The third agreement was in the form of a memo sent to the Defendant containing the terms of the agreement. It was countersigned by an unidentified person who agreed to the terms proposed in the memo. That person did not identify for which company he was agreeing the terms, but since
it is plain that it was the Defendant who was contracting with the Plaintiff, and doing so in such terms as to imply that it was the real and only principal. Thus, the cause of action for breach of the third agreement vests in the Defendant, not SGT. 13. In these circumstances, the potential difficulty for the Defendant is that the Defendant is counterclaiming damages for losses which were sustained by SGT. Are damages for such losses claimable by the Defendant? The answer to that question does not depend, as has been contended, on the following principle in the law of agency:
That is because the Defendant had not been acting as SGT's agent when it concluded the third agreement. The answer to the question depends on the law of privity of contract. Where X breaks its contract with Y which was made for the benefit of Z and which causes loss to Z, can Y claim from X damages for Z's loss? The common law on this topic is in a state of flux: see the discussion on the topic in Chitty on Contracts, 28th ed., vol. 1, paras. 19-046 and following. Indeed, in the United Kingdom, Parliament has intervened to legislate in the field: see Contracts (Rights of Third Parties) Act 1999. In our view, although this is a crisp question of law, it is one which requires mature and detailed consideration, and is not one which is susceptible to resolution in a summary procedure of the kind provided for by Ord. 14. In any event, we have not had the benefit of any submissions of counsel on this topic. Accordingly, there is a triable issue as to whether the loss alleged to amount to $5.2m. sustained by SGT can be counterclaimed by the Defendant. 14. What order, then, should be made in these circumstances? The law in this area has been usefully summarised in the Supreme Court Practice 1999, vol. 1, at p. 179 as follows:
The Defendant's counterclaim does not come within category (a) or category (b). Accordingly, there is no defence to the Plaintiff's claim for $1,859,755.88 plus interest, and there must be judgment for the Plaintiff for that sum. The issue is whether the Defendant's counterclaim comes within category (c) or category (d). In our view, it comes within category (c). Both the settlement agreement and the third agreement arose out of orders given to the Plaintiff for ceramic tiles pursuant to an ongoing trading relationship. In our judgment, it would be unjust to require the Defendant in such a relationship to pay a sum which represents a compromise as to the balance of the purchase price of goods to which the original agreement related before the determination of the seller's liability to compensate the buyer for losses alleged to have been incurred as a result of sub-standard goods being delivered under the third agreement. Conclusion 15. In these circumstances, we allow the appeal, we set aside the order made by the judge, and we substitute for it the following orders:
As for costs, the orders nisi which we make are that the Defendant must pay to the Plaintiff the Plaintiff's costs of the summons under Ord. 14 up to and including the hearing before the master in any event, to be taxed if not agreed, but that the costs of the summons thereafter, including the costs of the appeals to Cheung J and the Court of Appeal, should be in the counterclaim.
Representation: Mr Patrick Chong, instructed by Messrs So & Co., for the Plaintiff. Mr Francis Yip, instructed by Messrs Amelia Cheung & Co., for the Defendant. |
Other judgments that cite this case