Ideas Design Engineering Company Ltd v. M.O.P. Development Ltd
|
DCCJ 1044/2021 [2025] HKDC 15 IN THE DISTRICT COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION CIVIL ACTION NO 1044 OF 2021 ------------------------------------
------------------------------------
--------------------------- JUDGMENT --------------------------- Introduction 1.This is the trial of the Plaintiff’s claim for outstanding contractor fee in the total sum of HK$650,140 under 6 fire installation service contracts. 2.On 10 March 2021, the Plaintiff issued the Writ (indorsed with a Statement of Claim) against the Defendant which was subsequently amended on 20 May 2021. At the outset of these proceedings, the Defendant was represented by Messrs Peter WK Lo & Co. On 31 August 2021, the Defence and Counterclaim (“D&CC”) was filed. The parties had filed their witness statements by April 2023. 3.On 10 November 2023, the Defendant’s solicitors obtained leave to cease to act for the Defendant. 4.The Defendant was absent in the subsequent CMC and PTR held on 20 December 2023 and 11 April 2024 respectively. On the first day of the trial hearing, one Mr Cheung Kwai Kin claimed to be the Defendant’s director, appeared in court. But according to the Court’s file record, the Defendant had not duly appointed Mr Cheung nor any other director in accordance with Order 5A of the Rules of District Court (Cap 336H) to represent themselves in these proceedings after their former solicitors had ceased to act. 5.In the end, the Court decided to give the Defendant one last chance to comply with the procedural requirement by adjourning the case to the following day. However, Mr Cheung did not show up the next morning, nor the Defendant filed any further documents as required to comply with Order 5A. As such, the Court saw it appropriate to proceed with the trial in the Defendant’s absence. Plaintiff's claim and evidence 6.The Plaintiff has been a contractor supplying labour, equipment and materials for carrying out fire service installation works. Although the Plaintiff itself is not a registered fire service installation contractor, it would collaborate with registered fire service installation contractors in their various projects for the purpose of issuing certificates of fire service installation and equipment (ie the FS251 Certificate) as required by the Fire Service (Installations and Equipment) Regulations (Cap 95B) upon the completion of the relevant works. In all the FS251 Certificates produced in this case, there were certification by the relevant registered fire service installation contractors as follows:-
7.In 2018, the Plaintiff entered into 6 fire service installation contracts with the Defendant as evidenced by 6 quotations issued by the Plaintiff to the Defendant (during the period between about August and October 2018) setting out the labour, equipment and materials to be provided. 8.The particulars of the quotations and the respective contract sums agreed thereunder (totalling HK$1,104,450) are set out at paragraph 6 of the Amended Statement of Claim (“ASOC”), which are admitted in the Defence. 9.It is further admitted by the Defendant the following essential payment term of the 6 contracts (“the Payment Term”) as pleaded in paragraph 9 of the Amended Statement of Claim[2]:-
10.In D&CC, the Defendant admitted that it only paid up HK$454,310, leaving the balance of HK$650,140 remains unpaid under these 6 contracts, but pleaded that some works done were defective, and the contract works were not yet completed. The six contracts are hereinafter defined as “Contract 1” to “Contract 6”, which correspond to fire service installation work done at the sites of (1) Yuen Long, (2) Tuen Mun, (3) Kwai Chung, (4) Lai Chi Kok, (5) San Po Kong, and (6) Tai Po respectively as referred to in ASOC, and corroborated by the 6 quotations adduced by the Plaintiff. 11.In respect of the said sum of HK$454,310, Mr Sebastian Leung, counsel appearing for the Plaintiff at the trial, agreed the following amounts of deposit were received from the Defendant:-
12.After some exchanges with the Bench at the closing submission stage, Mr Leung in the end agreed that in order to recover the outstanding balance under each contract, the Plaintiff has to prove on balance of probabilities that the relevant event triggering the corresponding Defendant’s obligation under the Payment Term had occurred. In other words, the required FS251 Certificate(s) had to be issued by the registered fire service installation contractor(s) and provided to the Defendant to obtain full payment of contract price as stipulated under the relevant quotation. 13.As such, Mr Leung also fairly agreed that the Plaintiff would abandon the claim for the payment for the last 10% balance for Contracts 2 to 5 because it is undisputed that no FS251 Certificates have not been provided to the Defendant for these 5 Contracts. Analysis and findings 14.After carefully considering the evidence before me, in particular, the testimony of the Plaintiff's project manager, Mr Man Pak Ki, and Mr Leung’s submissions, I come to the following views and findings:
15.Therefore, the Plaintiff is entitled to recover a total sum of HK$416,247 under these four contracts. 16.For completeness sake, I should mention that Mr Leung in his opening submissions made a fallback argument that the Plaintiff is also entitled to claim the outstanding payments against the Defendant on quantum meruit. 17.Mr Leung very fairly and sensibly did not press on such submission after the relevant authorities were drawn to his attention at the end of the trial: See Chitty on Contracts (Hong Kong Specific Contracts, vol 1) (7th ed), paras 8-189 to 8-190. In any event, this Court see no room for the Plaintiff to invoke the doctrine of quantum meruit to advance its claim under the circumstances of this case. 18.On the question of interest, I think that it is just and fair to order interest to accrue on the Plaintiff's entitled outstanding payment at the commercial rate counting from 27 March 2019 onwards, ie the completion date of the works done as certified under the last batch of FS251 Certificates. 19.Subject to the above findings of this Court, since the Defendant did not actually present its Defence, nor Counterclaim in this trial, both of them are dismissed accordingly. Disposition 20.Due to the above reasons, judgment was entered in favour of the Plaintiff and the Defendant’s Counterclaim is dismissed. This Court hereby orders the Defendant to pay the Plaintiff:-
Costs 21.On the question of costs, I see no reason why costs should not follow the event, and order that the Defendant shall pay the costs of this action to the Plaintiff (including all previous reserved costs order, if any), with certificate to counsel. 22.Lastly, it remains for me to thank Mr Leung for his helpful assistance.
Mr Sebastian Leung, instructed by Lam & Lai, for the Plaintiff The Defendant was not represented and did not appear | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||