Ching To Yuen Ltd v. The Incorporated Owners of Pristine Villa
Read the full judgment text of HCA 632/2018 on BabelCite. This High Court CFI judgment was delivered on 20 January 2025.
4. Issue 2: Whether there was a legally effective dedication of the Access Road as a public right of way
Cites 8 cases
|
HCA 632/2018 [2025] HKCFI 388 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO 632 OF 2018 _______________ BETWEEN
_______________
________________________ JUDGMENT ________________________ 1.Introduction 1.1The Plaintiff (“P”) is and was at all material times the owner and occupier of Lot No 374 and Sections A and B of Lot No 375 in DD 186 (“P’s Land”). P’s Land is situate in the upper part of the Tao Fung Shan (道風山) area in Shatin, New Territories. 1.2The Defendant (“D”) is and was at all material times the Incorporated Owners of Pristine Villa. Pristine Villa is situate in a lower part of the Tao Fung Shan area relative to P’s Land and was erected on Sections A, B and C and the Remaining Portion of Shatin Town Lot No 331 (“D’s Land”). The developer of Pristine Villa was Sun Hung Kai Properties Ltd and the development consists of 14 blocks of building (with 498 flats), a clubhouse, common facilities including a swimming pool and car parking spaces. The development was completed in 1995 and the purchasers started to take possession of their respective units in or about April 1995. 1.3The present proceedings are concerned with an alleged right of way over Pak Lok Path, which is the access road of Pristine Villa (“Access Road”). The Access Road is coloured red on Annexure A annexed hereto with the blocks of building of Pristine Villa coloured orange. 1.4It is common ground that the Access Road is a private road. The geographical context can be shown by reference to another plan annexed hereto as Annexure B (“Plan”)[1]:
1.5A prominent feature in the present case is as follows:
1.6Although P’s Land is zoned as “green belt”, P has since 2005 operated a columbarium (“Columbarium”) on it (the legality of which is in dispute). It is P’s case that the visitors to the Columbarium and in particular the shuttle buses operated by it are entitled to use the Access Road. These proceedings were commenced in March 2018. As canvassed below, D had, in 2017, started to restrict the use of the Access Road by P’s shuttle buses. 1.7In the Statement of Claim (“SOC”), the relief sought by P are[3]:
1.8P’s claims are denied by D. In the Re-Amended Defence and Counterclaim (“RAD&C”), D counterclaims for:
1.9At the trial, P was represented by Mr Colin Leung and D by Mr MC Law SC (leading Mr Keith Chan). 1.10Of the issues identified in the Agreed List of Issue (“ALOI”), Mr Leung in opening confirmed that P no longer relies on the ground of easement by necessity. The following issues identified in the ALOI therefore remain for determination:
2.Witnesses 2.1P and D each called one witness. P called Mr Chan Sing Wai George (“Mr Chan”), a project manager of P. D called Mr Wong Shiu Kwan (“Mr Wong”)[4], the Vice Chairman of the management committee of D. D had previously filed witness statements from Mr Wong Chun Keung (“CK Wong”), a former Chairman of the management committee of D. As CK Wong had stepped down as the Chairman of the management committee in 2022 and could not be located, D decided to call Mr Wong as the “replacement” witness. Mr Wong and CK Wong were appointed respectively Vice Chairman and Chairman of the management committee of D on 29 August 2018 and both started to live in Pristine Villa in April 1995. Mr Wong largely adopts the contents set out in the witness statements previously filed by CK Wong. 2.2I agree with Mr Law that the resolution of the present case does not turn on the credibility of the oral evidence, as the documents adduced at the trial largely speak for themselves. Without prejudice to the foregoing, I agree with Mr Law on his following observations on the witnesses. 2.3Mr Chan lived and worked in England until 2011 and only joined P’s group of companies in 2015. Prior to 2015, he had no personal involvement in P’s Land or the Columbarium. As will be seen below, Mr Chan’s lack of personal knowledge of events prior to 2015 is an important deficiency in P’s case. Relatedly, as pointed out by Mr Law, a large part of his evidence consists of his beliefs, opinions, legal arguments or matters outside his personal knowledge, on which Mr Law in opening already stated no cross-examination was warranted or required. In closing, Mr Leung only placed limited reliance on Mr Chan’s evidence. 2.4Conversely, Mr Wong is in my view a credible witness. His evidence was clear and straightforward and made appropriate concessions. Indeed, Mr Leung in closing did not make any criticism on Mr Wong’s credibility. 3.Basic facts 3.1The parties have provided an agreed chronology setting out the basic facts (“Agreed Chronology”). I endeavour to summarize below the matters set out in the Agreed Chronology, supplemented by my observations and those set out in Mr Law’s closing submissions (with which, as I understand, Mr Leung has no quarrel). As one might expect, some of the details are not reflected in the Agreed Chronology and they will be canvassed at the appropriate juncture when dealing with the issues identified at §1.10 above. 3.2As to P’s Land:
3.3As to D’s Land:
3.4On 10 February 1998, D was incorporated. 3.5Following the expiry of the licence granted to Mr Godfrey, in 2005, P started to operate the Columbarium known as 淨土園 on P’s Land. 3.6In 2006, P started to organize shuttle buses to travel between Tai Wai MTR station and the Columbarium using the Access Road. 3.7Since 2006, D or Hong Yip had issued letters to complain to various government authorities regarding the use of the Access Road by P’s shuttle buses and the operation of the Columbarium on P’s Land, for example:
3.8On 25 May 2011, P made a town planning application to change P’s Land from “green belt” to “Government, Institution or Community”, but the application was withdrawn on 3 August 2012. A second application was made on 13 October 2014 but was withdrawn on 18 November 2015. 3.9On 2 October 2015, D sent a letter to Universal Travel Co Ltd, the shuttle bus company engaged by P, to request it not to use the Access Road, but the said request was not complied with. 3.10Around the time of Chung Yeung Festival in 2017, there were disputes regarding the use of the Access Road by P’s shuttle buses. Eventually, such use was restricted to 2 hours during the festival period:
3.11There were further disputes in 2018 around the time of Ching Ming Festival (which fell on 5 April 2018). On 15 March 2018, P’s solicitors demanded D not to block the Access Path during identified periods preceding and following Ching Ming Festival, failing which proceedings would be instituted. 3.12P commenced the present proceedings on 20 March 2018 and applied for an interlocutory injunction. D agreed to give an interim undertaking not to block the Access Road from 22 March to 30 June 2018. 3.13On 28 March 2018, P made an application under the Private Columbaria Ordinance Cap 630 for a licence to operate the Columbarium as well as temporary suspension of liability (“TSOL”). 3.14In 2019, D closed off vehicular access to the Access Road during Ching Ming Festival and closed off both vehicular and pedestrian access during Chung Yeung Festival. 3.15On 14 January 2020, D requested the Transport Department to convert the lower section of To Fung Shan Road to accommodate two-way vehicular traffic during Ching Ming Festival (ie altering the 1995 Traffic Arrangement). By letter dated 21 February 2020, D informed the Transport Department (copied to P) that it would block vehicular and pedestrian access to the Access Road on certain dates around Ching Ming Festival. Despite expressing some initial reluctance in its letter of 2 March 2020, ultimately the Transport Department adopted D’s proposal to convert the lower section of To Fung Shan Road to two-way vehicular traffic and issued a traffic advice to that effect on 26 March 2020. 3.16On 25 May 2022, the Government issued a press release, stating inter alia that the Access Road "falls within the private lot of Pristine Villa. There is no requirement under the lease of the lot that the grantees are obliged to open Pak Lok Path for public use" and that "[r]elevant departments will continue to monitor the traffic situation of Pak Lok Path and the effectiveness of the above measures before considering whether resumption of Pak Lok Path is necessary". 3.17On 16 August 2022, the Private Columbaria Licensing Board (“PCLB”) informed P that its TSOL application was approved in principle, with a validity period of 3 years from 16 August 2022 to 15 August 2025. 3.18Before turning to the issues identified at §1.10 above, it seems to me pertinent set out the following matters. 3.19First, prior to the Columbarium coming into operation in 2005, as I understand the evidence, there were the following institutions and residents in the Tao Fung Shan area:
3.20Secondly, it is Mr Wong’s evidence, which is not disputed, that (1) the land over which the Christian Centre is situated belonged to Christian Mission to Buddhists, one of the Original Grantees, until it was gifted to Tao Fung Shan Foundation Limited (“TFSF”), (2) the Cemetery is owned by Rev KL Reichelt who is in the same parish as Christian Mission To Buddhists, (3) the Original Grantees remain owners of 15 flats and 35 parking spaces in Pristine Villa and (4) given the foregoing, any usage by the Christian Centre, TFSF and the Cemetery had always been allowed by D. 3.21Thirdly, Mr Wong accepts that LTS operates a minibus service for the seminary and that, in recent years, it has operated shuttle bus services during the Ching Ming and Chung Yeung Festivals. But what is clear from the documentary evidence is that these entities, unlike P, have not regarded their use of the Access Path to be as of right. 3.22Fourthly, it may be observed from the chronology above that soon after the commencement of the operation of the Columbarium in 2006, D already raised its complaints to various governmental departments regarding the use of the Access Road by P and the operation of the Columbarium on P’s Land. In October 2015, D engaged P on the issue of the use of the Access Road, initially through the shuttle bus operator. 3.23In my view, the above 4 observations, all based on undisputed or indisputable evidence, are particularly germane to the resolution of the issues identified at §1.10 above, to which I now turn. 3.24As is clear from Mr Leung’s submissions, P pursues Issue 2 (dedication of public right of way) as its primary case and Issue 1 (prescription by way of lost modern grant), in Mr Law’s characterization, has not been pursued with “much enthusiasm”. I will therefore first deal with Issue 2. 4.Issue 2: Whether there was a legally effective dedication of the Access Road as a public right of way 4.1Counsel agree that the relevant principles are set out in Kong Sau Ching v Kong Pak Yan & Ors [2004] 1 HKC 119. The relevant principles may be stated to be as follows: To establish a highway at common law by dedication and acceptance, it must be shown (a) that the owner of the land dedicated the way to the public and (b) that the public accepted that dedication, the acceptance normally being shown by user by the public: Kong Sau Ching §14. 4.2As further pointed out at Kong Sau Ching §14:
4.3As I understand Mr Leung, P does not rely on express or formal dedication. The question is therefore whether the facts of the present case raise a presumption of dedication. To raise such a presumption, it is necessary to show there is open user as of right for so long a time and in such a way that the landowner must have known that the public were claiming a right. 4.4Further, to establish public dedication, counsel agree that it is necessary to show that the Government as reversioner under the relevant Government Lease has consented to a dedication, which consent may be inferred: Kong Sau Ching §17. 4.5It is therefore the case that there are 3 broad issues to canvass (Kong Sau Ching §19):
4.6In my view, P’s claim premised on dedication of a public way fails. For the reasons set out below, P has failed to establish one or more of the 3 requirements identified in the preceding paragraph. (i) The 1st and 2nd Requirements: Intention to dedicate on the part of D and acceptance by public of dedication 4.7As pointed out at Kong Sau Ching §14, user by the public is effective to prove both dedication and acceptance. I therefore deal with the 1st and 2nd requirements together. 4.8At P’s Closing Submissions (“PCS”) §§23-25, Mr Leung has clarified that the relevant period for assessment of P’s present cause of action commences in April 1995, namely the completion of the construction of the Access Road. Two periods are identified: (1) the period between the completion of construction of the Access Road in April 1995 and 29 March 2006 (a period of 11 year) and (2) the period between April 2006 and October 2017 (another 11 years). For the first identified period, Mr Leung points out that it was only on 29 March 2006 that D first complained to various governmental departments about the use of the Access Road. For the second identified period, it is said that it was only in the latter half of October 2017 that D in fact limited access to the Access Road. Mr Leung refers to Kong Sau Ching §14 at which a period of enjoyment of 18 months has been said to be enough where the circumstances have pointed to an intention to dedicate. 4.9In relation to the 1st requirement, Mr Leung relies on the following matters as evidence from which an intention to dedicate the Access Road as a public way may be inferred: PCS §§11-15. 4.10First, Mr Leung relies heavily on the Tung Letter for the proposition that the Original Grantees had the intention to dedicate the Access Road as a public way. As mentioned above, the Tung Letter is dated 23 February 1995 and was purportedly issued by Sun Hung Kai Real Estate Agency Ltd on behalf of the Original Grantees. It is in the following terms:
4.11Mr Leung further points out that, as a matter of chronology, the Letter of Compliance was issued on 3 April 1995, shortly after the issuance of the Tung Letter. In addition, the 1995 Traffic Arrangement was put in place on 11 April 1995, by which the Access Road became the only vehicular way for going downhill to leave the Tao Fung Shan area. 4.12Secondly, Mr Leung submits that D was keen to surrender the Access Road, as shown in the following documentary evidence:
4.13Thirdly, whilst it is not disputed that (1) there were at all material times signs erected along the Access Road making clear that it was a private road and (2) Gurkha security guards were engaged by D from 1995 to 2014 to perform certain duties in relation to the Access Road, Mr Leung submits that neither of the foregoing has the effect of negating D’s intention to dedicate the Access Road as a public way. 4.14Fourthly, D has acted in a manner which is only consistent with having dedicated the Access Road as a public way. In this regard, Mr Leung relies on a modification letter dated 11 August 1993 (“Modification Letter”) which modifies SC[6] (19) of the New Grant, the effect of which is that (1) prior to the surrender of the Access Road, all vehicles can only enter the Access Road through both ends of the Access Road and (2) after surrender of the Access Road, the owners can then enter the Access Road through other openings as shown in the plan (ie r-t-s, v-w-v, x-z-y). Mr Leung points out that the carpark entrances of Pristine Villa are located at “r-t-s”, “v-w-v” or “x-z-y” and it is therefore the case that D and/or the residents of Pristine Villa have used the openings in the middle of the Access Road for many years. He reasons that not only has D breached the New Grant for many years, but this is also evidence that D is presumed to open the Access Way for general public use as if the Access Road had been surrendered under SC(19) of the New Grant. 4.15In relation to the 2nd requirement, the only submission made by Mr Leung on the public’s acceptance of the alleged dedication is the effect flowing from the 1995 Traffic Arrangement, namely the Access Road was the only vehicular path to enable vehicles to leave the Tao Fung Shan area. 4.16In my view, the approach advocated by Mr Leung (set out at §4.8 above) is overly simplistic. As pointed out at Kong Sau Ching §14, in order to raise a presumption of dedication, there must have been open user as of right for so long a time and in such a way that the landowner must have known that the public were claiming a right. User with the landowner’s permission or tolerance is no user as of right and the court is slow to find a claim of right where the user is attributable to the landowner’s indulgence. At the end of the day, the length of the enjoyment which has to be shown depends on the circumstances of the case. 4.17For the following reasons and having assessed the evidence holistically, I find that during the periods identified by Mr Leung, it cannot be inferred that D had the intention to dedicate the Access Road as a public way. To the contrary, the evidence shows that the use of the Access Road was with D’s permission or tolerance. 4.18First, as regards the Tung Letter, it is important to set out the relevant context, namely the terms of the New Grant and in particular GC[7] (10) and SC(17):
4.19The combined effect of GC(10) and SC(17) is as follows: (1) the grantee was obliged to build the Access Road to the requisite standards, specifications and design; (2) unless the Director made a demand for surrender, the Access Road remained part of D’s Land and (3) whilst the Access Road remained part of D’s Land, the responsibility to maintain it remained on the grantee and (4) whilst the Access Road remained part of D’s Land, the Director may install and maintain road lighting for the sake of public interest. 4.20Read against the above context, I agree with Mr Law’s submissions that the Tung Letter does not have the effect of evincing an intention to dedicate the Access Road as a public right of way. Where the Tung Letter expressly undertook the responsibility of all maintenance works relating to the Access Road, it plainly contemplated that the Access Road would remain part of D’s Land as per the terms of GC(10). In my view, the Tung Letter should be understood as only giving permission for the public to use the Access Road. In the alternative, the Tung Letter, on its own, is at best equivocal[8]. 4.21Secondly, whilst it is true that the owners of Pristine Villa had expressed their views at various meetings of D their desire for the Government to take over the Access Road and pay for its maintenance, I agree with Mr Law’s submissions that the foregoing does not mean that in the absence of taking over by the Government, D nevertheless intended for the Access Road to be used as a public road. I accept Mr Wong’s evidence that the use of the Access Road was always controlled and regulated by D through (1) multiple signs erected along Access Road (since the completion of its construction) making clear that it was a private road, (2) the stationing of security guards and (3) installation of CCTV cameras along the Access Road since 1995. It seems to me clear from the context that the owners’ wish to have the Access Road taken over by the Government was motivated by monetary reasons (to rid D of the monetary obligations to maintain the Access Road) as opposed to an unqualified wish to dedicate the Access Road as a public way. 4.22Thirdly:
4.23Fourthly, whilst Mr Law has not dealt with the Modification Letter, it is only part of the relevant factual matrix. In my view, I do not believe the issue raised by Mr Leung in relation to the Modification Letter has the effect of outweighing the other evidence on my conclusions set out at §4.17 above. 4.24Fifthly, as pointed out by Mr Law:
4.25Sixthly, it is plain from Mr Leung’s identification of the two periods (§4.8 above) that he realistically accepts D’s complaints to various governmental departments on 29 March 2006 as inimical to the contention that D had intended to dedicate the Access Road as a public way. Two observations may be made. (1) In all the circumstances of the case, I am unable to accept Mr Leung’s proposition that P can take advantage of the period before P started to operate the Columbarium (ie the period when P’s Land was used as the residence of the then Moroccan consul). During that period, the use of the Access Road by others (including by the then Moroccan consul residing on P’s Land) was, more likely than not, only tolerated by D. As soon as (or soon after) P started its shuttle bus service, D complained to various government authorities (see the preceding paragraph). (2) As pointed out at Kong Sau Ching §14, it takes only ceremonial act, for example by closing the way for one day each year, to disprove any intention to dedicate. The present case is a far cry from the facts found at Kong Sau Ching §§51-52:
4.26For the above reasons, I find that during the periods identified by Mr Leung, it cannot be inferred from the facts found that D had the intention to dedicate the Access Road as a public way. To the contrary, the evidence shows that the use of the Access Road was with D’s permission or tolerance and the public, including P until 2017, accepted that to be the case. (ii) The 3rd Requirement: Government consent to a dedication 4.27Further, I am of the view that P has failed to satisfy the 3rd requirement. 4.28As I understand Mr Leung, he relies on the follow matters to infer that the Government had consented to the alleged dedication:
4.29In my view, the above (incomplete) matters are insufficient to infer Government consent. As submitted by Mr Law, the evidence shows that the Government has repeatedly and expressly disavowed the alleged dedication of the Access Road as a public right of way, despite D’s requests. 4.30The documentary evidence referred to by Mr Law include:
4.31Mr Leung was unable to provide an answer to the matters raised in the preceding paragraph. 4.32Conversely, I agree with Mr Law’s answers to the specific matters raised by Mr Leung:
4.33Further, as pointed out by Mr Law, Mr Chan agreed in his oral evidence that he had no factual basis to say the Government had demanded the surrender of the Access Road, or that there was in fact a surrender of the Access Road. This at least strongly suggests that the Government would not have consented to any dedication of the same road as a public right of way. 4.34For the above reasons, I find that, on the evidence, there was no Government consent to a dedication by D. 4.35I therefore determine Issue (2) against P. I find that there was no effective dedication of the Access Road as a public right of way. 5.Issue 1(a): Whether the alleged right of way is capable of being an easement 5.1The issue here is whether P can satisfy the second characteristics of easement as stated at Regency Villas Ltd v Diamond Resorts Ltd [2019] AC 553 §35, namely “the easement must accommodate the dominant easement” with the element of “propinquity” so the servient tenement must be close enough to the dominant tenement to confer a practical benefit on it. 5.2Mr Law does not seriously contest Issue 1(a). He merely contends that it is for P to show that P’s Land and D’s Land are close enough such that the right of way over the Access Road confers a practical benefit on P’s Land. 5.3I accept Mr Leung’s submissions that P had relied on the Access Road for its benefit, the Access Road being the only means for vehicles to leave the Tao Fung Shan area when the 1995 Travel Arrangement remained in place. I answer Issue 1(a) in the affirmative. 6.Issue 1(b): Whether an easement arose by prescription by way of lost modern grant 6.1The law on prescription by lost modern grant has been usefully summarized in Lee Kok Che & Ors v Royal Mortgage Ltd & Ors [2023] HKCFI 648:
6.2At PCS §§32, Mr Leung contends that P has shown more than 20 years of uninterrupted user as of right from completion of the Access Road in April 1995 to the blockage in October 2017 (22 years). 6.3I do not agree with Mr Leung, for the following reasons. 6.4Prior to operating the Columbarium, between 1995 and 2004, P’s Land was used as the residence of the then Moroccan consul and they must have utilized the Access Road for vehicular passage to leave the Tao Fung Shan area. 6.5The burden is on P to show that such use was, amongst other factors, nec precario (without permission from the owner). Apart from a bare assertion (and not based on any personal knowledge) of Mr Chan, there is simply no evidence from P to show that that was the case, especially given the existence of “private road” signs since the completion of the Access Road. I accept Mr Law’s submission that even if there was any use of the Access Road from 1995 to 2004 by the residents on P’s Land (or their visitors), that use would have likely been no more than sporadic, tolerated out of neighbourly good relations, and/or resulting from temporary permission(s) from D. As noted at Sara and Dovar, Boundaries and Easements, 7th Ed at §15-023:
6.6Indeed this foregoing is precisely the evidence of Mr Wong, which I accept[9]:
6.7In these circumstances, the 20-year period can only begin to count from 2006 when P started to organize shuttle buses, in which case the requisite period obviously would not have elapsed by October 2017. 6.8In my view, Issue 1(b) must be answered in the negative. No easement in respect of the Access Road had arisen by prescription by way of lost modern grant. As a result, it is strictly unnecessary to deal with Issue 1(c) and Issue 3. 6.9For completeness, I deal with them briefly. 6.10In relation to Issue 1(c), both counsel refer to the principles set out in McAdams Homes Ltd v Robinson [2005] 1 P&CR 30 and applied in Wan Yuk Wing v Wong Kwok Hing Patrick [2010] 4 HKC 151. In gist, the issue as to whether an easement could continue to be enjoyed following some development on the dominant land should be determined by answering 2 questions: (1) whether the development of the dominant land represented a “radical change in the character” or a “change in the identity” of the site, as opposed to a mere change or intensification in the use of the site and (2) whether the use of the site as redeveloped would result in a substantial increase or alteration in the burden on the servient land. 6.11I do not understand Mr Leung to have argued that the operation of the Columbarium on P’s Land, when it was previously used as the residence of the then Moroccan consul, did not present a radical change in character. Mr Leung suggests, however, that there was not substantial increase or alteration in the burden on the servient land. I accept Mr Law’s submissions set out at §§65 -66 of D’s closing submissions (“DCS”) that the frequency and usage of the shuttle buses operated by P represented a substantial increase in the burden on the Access Road. Had it been necessary, I would have held that any easement would have been extinguished or suspended. 6.12In relation to Issue 3, the issue is whether the legality of the operation of the Columbarium would have the effect of denying P relief. Both counsel refer to Loyal Luck Trading Ltd v Tam Chun Wah [2007] 4 HKLRD 917 in which the Court of Appeal rejected the defendant’s defence of illegality on the basis that (1) the use of the Access Road itself was not unlawful and (2) the plaintiff did not need to rely on the illegality but Mr Law emphasizes that that case should be distinguished on the basis that the present case is concerned with unclean hands as opposed to illegality, bearing in mind that the relief sought by P are equitable in nature. 6.13I do not agree with Mr Law. Like Loyal Luck, the use of the Access Road is not unlawful, and where in that case the illegality did not operate as a defence, it seems to me that I should be slow to use it as a justification to deny relief. In any event, as matters present stand, P has obtained TSOL. 7.Issue 4: D’s Counterclaim 7.1Mr Leung did not deal with D’s counterclaim in the PCS. When invited by the court, the oral submissions made were mainly directed at D’s counterclaim for damages. 7.2In the light of my above conclusions that P has failed to establish an easement in respect of the Access Road or a dedication of the Access Road as a public right of way, I am satisfied that P is liable for trespass. I am further satisfied that it is appropriate to grant the declaration and injunction sought by counterclaim relief (1) and (2): Cheng Lai Yin v Liu Yee Mui [2022] HKCFI 940 §33, in particular the principle set out in that case that for a claim in trespass, damage suffered is not a pre-requisite to the grant of an injunction, nor is the triviality of the interference a sufficient reason to justify a departure from the general rule of granting injunctions. In a case concerning trespass to land (in particular for threats of trespass and acts of trespass in the future), the court is concerned with the protection of a property right which, if not protected by an adequate remedy becomes diminished. I also note in particular that D has quite reasonably limited the relief sought to vehicular traffic only and has not included pedestrian traffic. 7.3I am also satisfied that P is liable for private nuisance. Mr Law refers to Cheng Lai Yin §51. It is stated there that a private nuisance is committed by a person doing, on his own land, something which he is lawfully entitled to do but the consequences of which extend to the land of his neighbour by (i) causing an encroachment on his neighbour’s land; (ii) causing physical damage to his neighbour’s land; or (iii) unduly interfering with his neighbour in the comfortable and convenient enjoyment of his land. I accept Mr Law’s submission that P’s liability for private nuisance is established, as the unauthorized use of the Access Road by those going to P’s Land amounts to private nuisance by at least causing physical damage to the Access Road. I also accept Mr Law’s reliance on Pierhead Garden Management Co Ltd v The I/O of Pierhead Garden [2021] HKCFI 678 for the proposition that general damages may be award for the inconvenience suffered as a result of nuisance and interference with property rights. 7.4I am however not satisfied that I should accede to Mr Law’s invitation to award general damages in the sum of HK$800,000. D’s pleaded case on damages is as follows:
7.5No evidence has been adduced for the foregoing complaints. There is no evidence on the precise degree of congestion and Mr Wong was not able to tell me the extent of the maintenance and repair costs. In my view, D has failed to prove its counterclaim for damages. 8.Disposition 8.1In the premises, I dismiss P’s claim and enter judgment in favour of D for its counterclaim for a declaration and an injunction as sought in counterclaim relief (1) and (2). 8.2I also make a costs order nisi P is to pay to D the costs of the action and the costs of the counterclaim to be taxed if not agreed with a certificate for 2 counsel. Despite D’s failure to prove its claim for damages, my provisional view is that the time spent on, and the extent of, the materials relevant to the monetary counterclaim do not warrant a reduction of D’s costs entitlement.
Mr. Colin Leung, instructed by Lo, Wong & Tsui, for the Plaintiff Mr Law Man-chung, SC leading Mr Keith Chan, instructed by Au Yeung, Cheng, Ho & Tin, for the Defendant Annexure A
Annexure B
[1] The Plain is annexed as Annexure A to the Statement of Claim. [2] The roundabout is located at the bottom of the Plan (marked as a circle) when viewed in landscape orientation. [3] Although P’s claims include a claim for damages, P does not pursue the monetary claim. [4] D decided not to call Mr Leung Kam Tim Ivan, a resident of Pristine Villa. His short witness statement predominantly confirms the truth and accuracy of evidence of Mr Wong [5] Then under the name of Jadesmart Ltd. (“Jadesmart”). In November 2005, Jadesmart changed its name to P. [6] Special Condition [7] General Condition [8] Given my conclusions, I agree with Mr Law that it is necessary to further consider D’s pleaded case that the Tung Letter was issued without proper authority. Had it been necessary, I agree with Mr Law that even were the Tung Letter binding on the Original Grantees, PCS does not deal with the point that the Tung Letter does not bind D as the Tung Letter had never been registered against D’s Land in the Land Registry: RAD&C §§12(8)(b)(ii). [9] CK Wong’s Supplemental Statement §3,41 which Mr Wong adopted. |
Cases cited in this judgment

