Build King Construction Ltd Formerly Known As Kaden Construction Ltd v. Sam Woo Bore Pile Foundation Ltd and Another
Read the full judgment text of HCCT 4/2023 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 27 February 2025 before Hon Anthony Chan J in Chambers.
Construction contract dispute — Application by Defendants to re-amend Amended Defence and Counterclaim to add new cause of action for breach of Main Contractor’s Management Obligation alleged to be undertaken by Plaintiff as Sub-Contractor. Plaintiff opposed on grounds of limitation period, no sustainable cause of action, and fictitious quantum. The court applied the three-stage test for amendment raising limitation issues, concluding that the new cause of action is prima facie time-barred as breaches began in August 2015, outside the six-year limitation period. The defence of abatement of price plea is recognized as permissible despite limitation. Continuing breach doctrine discussed; court deemed the issue fact-sensitive and inappropriate for interlocutory determination. The new cause of action found to arise from different facts than existing claims, thus not qualifying for amendment under limitation exceptions. Claim of deliberate concealment to extend limitation period rejected due to lack of evidence. The court emphasized principles favouring amendments unless bound to fail or causing prejudice; held amendment to plead abatement defence acceptable but refused to allow new cause of action absent proper particulars and foundation for loss. Application dismissed with costs to Plaintiff but Defendants may bring a new action or properly formulated further amendments. Legal principles from Limitation Ordinance Cap 347, case precedents including Shenzhen Futaihong, Ballinger v Mercer, and others on limitation, continuing breaches, and amendment rules applied.
Legal issues: Limitation period for new contractual claim · Applicability of continuing breaches doctrine · Whether new cause of action arises from same or substantially same facts as existing claims · Deliberate concealment under s.26 Limitation Ordinance · Amendment of pleadings principles
Outcome: Application to re-amend pleadings dismissed with costs to Plaintiff
Cited by 1 case · Cites 7 cases
|
HCCT 4/2023 [2025] HKCFI 894 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO. 4 OF 2023 ______________________
____________________
________________ DECISION ________________ 1.This is the Defendants’ application to re-amend their Amended Defence and Counterclaim with the addition of a new cause of action. Issues 2.The application is resisted by the Plaintiff on 3 grounds, namely, (a) limitation period; (b) no sustainable cause of action; and (c) fictional quantum. Background 3.In brief, the 1st Defendant was the Main Contractor in respect of the foundation and associated works (“Works”) for the Hospital Authority (“HA”) as the Employer for the expansion of United Christian Hospital (“Project”). The Plaintiff was the Sub-Contractor of the 1st Defendant for the majority of the Works. A smaller part of the Works was carried out by the 1st Defendant. 4.There is a Sub-Contract executed by the Plaintiff and the 1st Defendant on around 4 January 2017 but dated 22 August 2015. There is a dispute whether the contract between the Plaintiff and the 1st Defendant was solely embodied in that written document. The 1st Defendant says that the contract was partly oral. For convenience, the contract between the parties is referred to as “the Sub-Contract”. 5.The Works were split into Section 1 Works and Section 2 Works. The Works of both Sections were commenced on 22 August 2015 and substantial completion occurred for Section 1 Works and Section 2 Works on 17 March 2020 and 2 June 2020 respectively. 6.In addition to the Sub-Contract, about 17 months after the commencement of work, on 4 January 2017 the Plaintiff signed a Project Management Services Agreement (“PMSA”) with the 2nd Defendant (a sister company of the 1st Defendant) who, according to the PMSA, had been awarded the sub-contract for the provision of project management services by the 1st Defendant for the Project. Under the PMSA, the Plaintiff was to provide project management services on behalf of the 2nd Defendant on a back-to-back basis with the 2nd Defendant’s sub-contract from 15 July 2016 until the issuance of maintenance certificate. The PMSA was backdated to 1 June 2016. 7.These proceedings were issued on 18 January 2023 and in which the Plaintiff made 3 claims: (a) despite the certification of the total value of works executed by the Plaintiff, there is outstanding payment under the Sub-Contract of about HK$53 million; (b) outstanding refund of deposits paid by the Plaintiff (and certified by the 1st Defendant) in the sums of HK$405,000 (paid to Environmental Protection Department) and about HK$47,000 (paid to Water Supplies Department); and (c) outstanding payment for project management services under the PMSA due to the extension of completion dates for Section 1 Works and Section 2 Works in the sum of about HK$1.74 million. Claim (c) is made against the 2nd Defendant. 8.According to the Amended Defence and Counterclaim re-filed on 22 September 2023, the issues raised in defence were (a) for the amount due under the Sub-Contract, there was an over-certification which arose from contract price fluctuations of about HK$13.49 million; (b) breach of fiduciary duty by the Plaintiff in carrying out Maintenance Service Work under the Main Contract without the 1st Defendant’s consent; (c) the PMSA was a lump sum contract and the Plaintiff was in fact overpaid by about HK$5.8 million; and (d) the outstanding deposits were included in the Account. 9.For (a), the 1st Defendant claims to be entitled to deduct and/or set off against the Plaintiff’s claim. For (b), the 1st Defendant claims an account of profits or equitable compensation in the alternative. For (c), the Plaintiff is liable to return the overpayment to 2nd Defendant. 10.The proposed re-amendment seeks to introduce a new claim of breach of contract on the part of the Plaintiff in failing to manage the Project, described as “Main Contractor’s Management Obligation” which the Plaintiff had allegedly undertaken under the Sub-Contract. 11.The pleaded value of the new claim is about HK$163.5 million, being 10% of the total value of the work done for the entire Project on the basis of total failure of consideration by reason of the Plaintiff’s complete failure to manage the Project. 12.There are two points made by Mr Pennicott SC, who appeared for the Plaintiff, which are worthy of note. First, there appears to be no complaint by the Defendant about the lack of management for the Project until the re-amendment surfaced 4 years after completion of the Works. Second, it appears that the 1st Defendant was adequately paid by the Employer. This is consistent with the fact that there was no complaint, and hence there is no damages claim but an alleged restitution claim based on total failure of consideration. 13.The only reply made by Mr Chan SC, who appeared with Ms Ng and Mr Cheung for the Defendants, is that the Final Account between the 1st Defendant and the HA has not been signed off, although he was unable to assure the court that his instruction was based on adequate support. Limitation 14.Prima facie, if the new claim (being one in contract) is accrued more than 6 years prior to the date of Writ, ie, before 8 January 2017, it is time-barred under the Limitation Ordinance, Cap 347 (“Ordinance”). 15.Paragraph 13AA of the draft Re-Amended Defence and Counterclaim pleads that: “Since or around the commencement of the Project in August 2015, the 1st Defendant and 2nd Defendant aver that wrongfully and in breach of the Subcontract Agreement and/or the PMSA, the Plaintiff had failed to manage the entire Project as if it was the Main Contractor.” 16.This averment is unequivocal in that the Plaintiff’s alleged breach occurred in August 2015, well before 6 years prior to the date of the Writ. It follows that, prima facie, the claim is made outside the limitation period. Applicable principles 17.A 3-stage test is to be applied when approaching an application for amendment which raises a limitation issue, as explained by Ng J in Shenzhen Futaihong Precision Industry Co Ltd v BYD Co Ltd, unrep, HCA 2114/2007, 18 July 2016, [16] :
18.With respect, I venture to suggest that for (2) it may be desirable to adhere to the terminology of s.35 of the Ordinance, ie, “new claim”, which was defined under s.35(2) to mean “any claim by way of set-off or counterclaim, and any claim involving [for the present purpose] the addition or substitution of a new cause of action”. In respect of (3), again it may be desirable to following the formulation used in s.35(6)(a) (and O. 2, r. 5(5) of the RHC), ie, “arise out of the same facts or substantially the same facts as a cause of action in respect of which relief has already been claim in the action by the party applying for leave to make the amendment”. 19.The arguments advanced by Mr Chan are: (a) the new claim is used as a defence which is permissible even if the claim is statute-barred; (b) continuing breaches of contract; (c) the new cause of action arises out of the same or substantially the same facts; and (d) deliberate concealment of relevant facts by the Plaintiff. Defence 20.There is no dispute that the Ordinance does not apply to a new defence. It was pointed out by Mr Chan that in para 13AL of the proposed re-amendment the new claim was pleaded as a defence of abatement of price. It is reasonably clear that abatement of price is a defence: Chitty on Contracts, 35th edn, [30-008]. Therefore, I agree with Mr Chan that this plea is not affect by limitation period. I shall deal with below whether the amendment in question should be allowed under general principles on amendment of pleadings. 21.Mr Chan conceded that if this application only succeeds on the ground of defence, then the counterclaim made in the amendment based on the new claim should be deleted in conjunction with prayers (1B) of the 1st. Defendant and (1A) of the 2nd Defendant. Continuing breaches 22.The Defendants say that the new cause of action against the Plaintiff for breach of Main Contractor’s Management Obligation is not time-barred. They rely on Chitty on Contract, 35th edn, vol 1, [32-035], where the concept of continuing breaches was elaborated as follows :
23.Mr Chan submitted that there are subsequent authorities consistent with Midland Bank Trust Co Ltd, namely, 2 Entertain Video Limited v Sony DADC Europe Ltd [2020] EWHC 972(TCC), [251]-[252] and Equitas Ltd v Walsh Bros & Co Ltd [2013] EWHC 3264 (Comm), [59]-[71]. In [64] of Equitas, Males J identified the key elements of continuing duties, namely, the relationship of the parties and whether the particular obligation in question is such as to give rise to a continuing obligation. In [69], the learned Judge applied the principles to the case before him :
24.I can see that on the basis of the above principles, it is arguable that the Plaintiff’s alleged duty to manage the Project was a continuing obligation such that every day of failure to fulfil the obligation gave rise to a fresh cause of action. 25.I have been referred by Mr Pennicott to the recent judgment of In Media Trust SPA v BGB Weston Ltd [2024] EWHC 3277 (KB), [13(iii) and (iv)], where Spencer J identified a number of applicable principles on limitation. Amongst which was that the court should not determine seriously disputed questions of facts on an interlocutory application, and this extends to issues of law which are not straightforward, clear or obvious; or issues of law or facts (or both) which required detailed argument and mature consideration. 26.In my view, these principles are applicable here on the issue of continuing obligation. Apart from the fact that the new cause of action is hotly contested by the Plaintiff, it is facts-sensitive to the case, eg, the Defendants’ allegation that they placed reliance on the Plaintiff for the due performance of the Main Contractor’s Management Obligation and in the administration of the entire Project, including the 1st Defendant’s part of the Works. It is not appropriate for the court to determine such issue on an interlocutory application. 27.Moreover, Mr Pennicott submitted that the new cause of action (or at least part of it) must be statute-barred even on the Defendants’ case because some of the breaches must have been committed prior to 18 January 2017 given the commencement of work in August 2015. It should be noted that there is no attempt by the Defendants’ to make any distinction to the alleged breaches which took placed before and after that date. Further, Mr Pennicott made the point that one indivisible amount is being claimed under the new cause of action. 28.I agree with Mr Pennicott that the Plaintiff is only required to show that it has a reasonably arguable case on limitation, and it has done so in answer to the continuing obligation point. Thus, the amendments (with the exception of abatement of price) are arguably outside the limitation period. The relevant amendments should be disallowed so that the Plaintiff will not be prejudiced by the “relation back” principle. The Defendants, however, will suffer no prejudice (and they do not suggest the contrary) since they can issue a new Writ in respect of its new claim. Arising from the same facts 29.The remaining two arguments of the Defendants are of little merits and can be disposed of quickly. 30.With respect, it is self-evident that the existing causes of action relied upon by the Defendants (see para 8 above) do not involve facts from which the new cause of action may arise. In his submission, Mr Chan pointed to the 2nd Defendant’s claim of overpayment under the PMSA. With respect, that is an extremely tenuous connection. The PMSA claim is in fact a claw-back of payments made to the Plaintiff, which were applied for, assessed and paid by the 2nd Defendant, based on the allegation that the PMSA was actually a lump sum contract. I agree with Mr Pennicott that this application is refused, the Plaintiff’s carrying out and fulfilment of its management obligations will not be an issue at the trial. Deliberate concealment 31.To his credit, Mr Chan did not press this point in his viva voce submissions but merely relied on what had been stated in the Defendants’ skeleton submissions. 32.Section 26 of the Ordinance provides :
33.For the purpose of s.26(1)(b) of the Ordinance, as summarized in Lee Tsan Sum v Wong Pui Hon David [2010] 4 HKLRD 219, per Fok J (as he then was), [39]:
34.I do not see how these stringent requirements had been satisfied by the Defendants. Their case is simply that there was, in breach of management obligation on the part of the Plaintiff, no management service provide from day one. Given the fact that the 1st Defendant was on site carrying out its part of the Works over a long period of time, periodic interim payment applications were made by it to the HA, and in turn it had certified and made payments to the Plaintiff as its Sub-Contractor, it is inconceivable that the 1st Defendant could not have found out the relevant facts until, allegedly, the recent filing of the Plaintiff’s witness statements. 35.With respect, the point has no merits and should not have been advanced to burden the court and increase the costs. Amendment of pleadings principles 36.Returning to the new plea of abatement of price. The principles can be found in Hsu Ming Chi v Lam Shu Chit, unrep, HCCL 8/2013, 22 October 2014, [13]-[18], where Ng J summarized them as follows :
37.The trial of this action has not been set down. Apart from Mr Pennicott’s misgivings about the state of the plea over the cause of action, I see no good reason to refuse the amendment to plead the abatement of price defence. 38.In respect of the lack of a properly particularised plea. There are merits in Mr Pennicott’s submission that the Sub-Contract and the PMSA did provide for certain management obligations on the Plaintiff, and it is incumbent on the Defendants to plead what it was that the Plaintiff was required to do over and above those existing duties and how it had failed to do so. 39.Mr Chan did not offer to provide particulars of the abatement plea. He relies on the Defendants’ allegation that the Plaintiff had obtained payment of the management duties which it did not carry out. I regret to say that this is both an unsatisfactory and unfair approach. 40.As for the claim of HK$163.5 million without any foundation on loss, I am inclined to the view that it is a matter for the trial judge whether the restitution claim can be accepted. In any case, as a claim of abatement it cannot exceed the size of the Plaintiff’s claim. 41.The lack of a properly formulated claim is a concern with merits. In my view, it is inappropriate to grant an amendment application which is keenly contested with the hope that proper particulars will be provided after amendment (none has in fact been offered). That is wrong in principle. Amendment application should be supported by a properly formulated set of amendments. 42.In the premises, I am driven to dismissing this application. The dismissal should not be taken as a bar to the Defendants to bring another amendment application with a properly formulated abatement plea. They are of course free to bring new action to advance the new cause of action. Disposition 43.The application is dismissed with costs to the Plaintiff, to be taxed if not agreed.
Mr Ian Pennicott SC, instructed by Hogan Lovells, for the Plaintiff Mr Edward Chan SC, Ms Queenie WS Ng and Mr Matthew Cheung, instructed by CLY Lawyers, for the 1st to 2nd Defendant | |||||||||||||||||||||||
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under HCCT 4/2023