Read the full judgment text of HCA 017683/1998 on BabelCite. This High Court CFI judgment was delivered on 23 October 1998.
1. The Plaintiff is the main contractor under a Government contract for maintenance works. The 1st Defendant was the Plaintiff's sub-contractor; the 2nd Defendant is a director of the 1st Defendant. The Plaintiff terminated the sub-contract in August 1998. The Defendants thereafter, however, retained possession of an area of some 500 square meters (which has been referred to by the parties as "the Site") which is used as inter alia a workshop. Also in issue before me are some items called "Gover