Cs v. Hkr
Read the full judgment text of CACV 76/2025 on BabelCite. This Court of Appeal judgment was delivered on 20 July 2026 before Poon CJHC, Kwan VP and Chow JA.
Arbitration – leave to appeal on a question of law – Arbitration Ordinance (Cap 609) Schedule 2 ss.5 and 6 – remeasurement subcontract for marine works under Hong Kong-Zhuhai-Macau Bridge Project – Sand Fill Issue concerning composition of Type A fill and entitlement to be paid for sand fill versus public fill in reclamation from +1mPD to +2.5mPD – Double Recovery Issue concerning alleged double payment under BQ Item 19 and Extra Works Item 20 for the same quantity of rockfill – whether the arbitral tribunal's decision was obviously wrong or open to serious doubt – threshold for granting leave is high and the filtering process has a fine mesh – arbitrator's process of reasoning divided into three stages and only the second (ascertainment of law) is the proper subject of an appeal on law – s 5(3) requires the court to decide the question of law on the basis of the findings of fact in the award – no principle of law requires all terms of a construction contract to be in writing – whether issue was raised before the arbitral tribunal – appeal against an exercise of discretion by the first-instance judge – Plaintiff (main contractor) was CS, Defendant (subcontractor) was HKR – arbitrator accepted the Defendant's alternative expert assessment that Type A fill between +1mPD and +2.5mPD was 70% sand fill and 30% public fill, based on an oral agreement reached at the 2 April 2012 tender meeting that was reflected in the change of description of BQ Item 17 from Type A fill to sand fill in the Subcontract – Judge refused leave on Question 1 as a disguised challenge to findings of fact – Judge refused leave on Question 3 because the issue was not raised in the arbitration, the arbitrator expressly rejected the underlying factual premise that the 23,059 m3 of Subject Rockfill came from the TWP, and the awards under BQ Item 19 (excavation) and Extra Works No 20 (deposition only) did not overlap – Judge later granted leave to appeal against her own refusal – Court of Appeal (Poon CJHC, Kwan VP and Chow JA) dismissed the appeal and affirmed the Judge's order of 22 November 2024 – Plaintiff to pay Defendant's costs of the appeal (including the costs reserved by the Judge when granting leave to appeal), to be taxed if not agreed, with the costs order nisi to become absolute unless varied within 14 days – starting point of analysis: principles from Finelvet AG v Vinava Shipping Co Ltd (The Chrysalis) [1983] 1 WLR 1469, Chun Wo Construction & Engineering Co Ltd v The Hong Kong Housing Authority [2018] HKCFI 147, and Maeda Kensetsu Kogyo Kabushiki Kaisha v Bauer Hong Kong Limited, HCMP 1342/2017.
Legal issues: Whether leave to appeal should be granted on Question 1 (Type A fill composition and payment entitlement) · Whether leave to appeal should be granted on Question 3 (alleged double recovery under BQ Item 19 and Extra Works Item 20)
Outcome: Plaintiff's appeal dismissed. The Judge's order dated 22 November 2024 dismissing the Plaintiff's originating summons seeking leave to appeal against the Arbitrator's Award is affirmed.; Plaintiff to pay the Defendant's costs of this appeal (including the costs reserved by the Judge when granting leave to appeal), to be taxed if not agreed; Costs order nisi to become absolute unless an application to vary is made within 14 days from the date of the judgment
Cites 4 cases
|
CACV 76/2025, [2026] HKCA 1142 On Appeal From [2024] HKCFI 3366 & IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO 76 OF 2025 (ON APPEAL FROM CONSTRUCTION AND ARBITRATION PROCEEDINGS NO 72 OF 2024) ________________________
________________________
________________________
________________________ J U D G M E N T ________________________ Hon Chow JA (giving the Judgment of the Court): 1.This is the Plaintiff’s appeal against the order of Madam Justice Mimmie Chan dated 22 November 2024 dismissing the Plaintiff’s application for leave to appeal against an Amended Interim Award on Liability and Quantum published on 27 May 2024 (“the Award”) by Mr Bernard Wu (“the Arbitrator”) in an arbitration between the Defendant as claimant and the Plaintiff as respondent. BACKGROUND 2.The basic facts of this case have been set out in the Award and his Amended Reasons for Award (“the Reasons”) forming part of the Award. We do not propose to set them out again in this judgment. The brief summary below should suffice for the purpose of disposing of the present appeal. 3.The Plaintiff was the main contractor for one of the works packages (“the Main Contract Works”) of the Hong Kong-Zhuhai-Macau Bridge Project pursuant to a contract dated 28 May 2012 (“the Main Contract”) awarded by the Highways Department (“HyD”) of the Government of the HKSAR as the employer. 4.Prior to the award of the Main Contract, the Plaintiff invited the Defendant to submit a quotation for certain marine works items (“the Subcontract Works”) which were to form part of the Main Contract Works. The Subcontract Works included reclamation works to be carried out on the eastern coast of Chek Lap Kok Island behind a new permanent seawall (to be constructed). The Defendant submitted its revised quotation for the Subcontract Works to the Plaintiff on 17 December 2011. A number of subcontract tender interviews were held between representatives of the Plaintiff and the Defendant prior to the award of the Main Contract. One such subcontract tender interview took place on 2 April 2012. On 25 April 2012, a “Pre-bid Agreement” was signed, and the Plaintiff agreed to engage the Defendant as the marine works subcontractor in the event that it was awarded the Main Contract by HyD. 5.On 28 May 2012, HyD awarded the Main Contract to the Plaintiff. On 29 May 2012, the Plaintiff informed the Defendant that it had been awarded the Main Contract, and the commencement date would be 31 May 2012. The Plaintiff also instructed the Defendant to prepare for the execution of the Subcontract Works pending the preparation of a formal subcontract. 6.As a matter of fact, the formal subcontract between the Plaintiff and the Defendant was not signed until 7 November 2013 (“the Subcontract”), after works had been commenced by the Defendant since around July 2012. It is not in dispute that the Subcontract is a “remeasurement contract”. 7.The Defendant submitted its draft final account statement to the Plaintiff on 19 August 2019. The parties disagreed on the amounts due and payable to the Defendant in respect of various items of works which were eventually referred to arbitration for determination. The disputes relevant for the present purpose relate to two issues, namely:
8.The Sand Fill Issue arose in the following circumstances:
9.The Arbitrator accepted the alternative assessment provided by Mr Nie. In summary, the Arbitrator found that:
10.The question of law which the Plaintiff seeks leave to appeal in respect of the Arbitrator’s determination in respect of BQ Item 17 Claim is as follows:
11.The Double Recovery Issue arose in the following circumstances:
12.The Plaintiff now argues that there was double recovery under BQ Item 19 and Extra Works No 20 by the Defendant, and seeks leave to appeal in respect of the following question of law:
Pausing here, it may be noted that the issue raised under Question 3, namely, double recovery under BQ Item 19 and Extra Works Item 20, was not an issue raised by the Plaintiff in the arbitration for determination by the Arbitrator. THE DECISION 13.On 24 June 2024, the Plaintiff issued an originating summons seeking leave to appeal against the Award in respect of 4 questions. Only Questions 1 and 3 referred to at §§10 and 12 above are relevant for the present purpose. 14.By her written decision dated 22 November 2024 (“the Decision”), the Judge refused to grant leave to appeal. 15.In respect of Question 1, the Judge held that:
16.In respect of Question 3, the Judge held that:
THE LEAVE DECISION 17.By a written decision dated 7 February 2025 (“the Leave Decision”), the Judge granted the Plaintiff leave to appeal against her earlier decision of 22 November 2024 in respect of Questions 1 and 3. 18.In respect of Question 1, the Judge considered that it was reasonably arguable that the tribunal’s decision on that question was in substance a matter of construction of the Subcontract, its provision and the drawings, and the parties’ obligations thereunder, and that the intended appeal was not merely against the Arbitrator’s finding of fact as to what the parties had agreed as a result of their meetings and discussions. The Judge also took the view that it was reasonably arguable that the Arbitrator decided Question 1 as to whether the parties had agreed on the maximum use of sand, but failed to consider the effect of the Subcontract provisions and the drawings, and whether or how these could be affected by the tender meeting discussions. On this footing, it was reasonably arguable that the tribunal had erred in law, and the decision of the tribunal could be said to be obviously wrong[39]. 19.In respect of Question 3, the Judge considered that it was reasonably arguable that if the Award and the amount allowed thereunder actually resulted in the Defendant obtaining double recovery, the tribunal erred in law and the determination would be one that was out of conformity with the only correct answer or lay outside the range of possible correct answers, and could be made the subject of an appeal on a question of law arising from the Award[40]. 20.Pursuant to the leave to appeal granted by the Judge, the Plaintiff served a Notice of Appeal dated 14 February 2025 challenging the Judge’s conclusions in the Decision in respect of Questions 1 and 3. DISCUSSION Relevant principles 21.It is common ground that the provisions of Schedule 2 to the Arbitration Ordinance, Cap 609, apply to the arbitration between the Plaintiff and the Defendant in the present case. 22.Section 5 of Schedule 2 makes provisions for an appeal against an arbitral award on a question of law:
23.Section 6 of Schedule 2 provides for leave to appeal against an arbitral award on a question of law.:
24.The principles for granting leave to appeal have been set out by the Judge at §§2 to 7 of the Decision, and are not in dispute. In summary:
25.It should also be borne in mind that although the Judge has granted leave to appeal, the present appeal is an appeal against an exercise of discretion by the Judge. Accordingly, the usual principles governing an appeal against discretion is applicable. This Court should not intervene in the Judge’s decision unless she has erred in law or approach, or has failed to take into consideration relevant matters or has taken into consideration irrelevant matters, or her decision is plainly wrong. Question 1 26.§§1 to 4 of the grounds of appeal relate to Question 1. In substance, they boil down to one point, namely, that by reason of various provisions of the Subcontract (read together with the Main Contract) and some other documents, the Defendant was under an obligation to use public fill in the reclamation “whenever possible”, subject to an upper limit of 30%. This means that the Defendant had a positive obligation to use 30% of public fill, absent a contractual basis not to do so, and such obligation overrode the oral agreement entered into by the parties prior to the award of the Main Contract[41]. 27.The contractual provisions and the documents that the Plaintiff argues give rise to the Defendant’s obligation to maximize the use of public fill in the reclamation “whenever possible”, subject to an upper limit of 30%, include:
28.If these provisions and documents stand alone, the Plaintiff would have a strong argument to say that the Defendant was under a contractual obligation to maximize the use of public fill in the reclamation works, up to the limit of 30% (although not necessarily in the ratio of 70% of public fill to 30% of sand fill). However, the above provisions and documents do not stand alone. The Arbitrator found that there was a specific oral agreement reached between the Plaintiff and the Defendant at the tender meeting on 2 April 2012 that the Defendant was entitled to use 100% sand as Type A fill under BQ Item 17[42]. Although that oral agreement was made prior to the award of the Main Contract (and therefore prior to the making of the Subcontract), it was reflected in the Bills of Quantities which was expressly made part of the Subcontract documents (see Item 6 of §15 of the Special Conditions of Subcontract). A copy of the Bills of Quantities was also annexed to the Subcontract as Appendix 4. The Arbitrator found that, because of this agreement, the Plaintiff changed the description of BQ Item 17 from “Type A fill to +2.5mPD” in the Pre-bid Agreement to “Sand fill (material supplied by Sub-contractor)” in the Subcontract booklet[43]. 29.In substance, the Arbitrator found that the oral agreement made on 2 April 2012 was part of, or had been incorporated into, the Subcontract. The Plaintiff’s submission that the oral agreement was inconsistent with the written terms of the Subcontract is beside the point. There is no principle of law which requires that all the terms of a construction contract (or subcontract) must be in writing, or that such a contract cannot be partly oral and partly written. The Arbitrator’s finding that there was a specific oral agreement reached by the parties concerning the use of sand as Type A is a finding of fact. By virtue of s 5(3) of Schedule 2 to the Arbitration Ordinance, the court must decide the question of law on the basis of the findings of fact in the award. In view of this finding of fact by the Arbitrator, the Arbitrator’s decision that the Defendant was not under a contractual obligation to maximize the use of public fill to the extent of 30% in the reclamation works cannot, in our view, be said to be “obviously wrong” or “open to serious doubt”. There is no suggestion by the Plaintiff that, absent the alleged obligation on the part of the Defendant, the Arbitrator was wrong to have assessed the Defendant’s entitlement to be paid for the reclamation works (i) from the seabed to +1.0mPD on the basis of 100% of sand fill, and (ii) from +1.0mPD to +2.5mPD on the basis of 30% of public fill and 70% of sand fill. 30.The Judge was entitled to take the view that the Plaintiff’s argument on Question 1 is nothing more than an impermissible challenge to the Arbitrator’s finding of fact. It was also open to the Judge to take the view that the Arbitrator’s conclusion was not “obviously wrong” or “open to serious doubt”. We see no basis to intervene in the Judge’s exercise of discretion to refuse to grant leave to appeal in respect of Question 1. Question 3 31.§§5 to 7 of the grounds of appeal relate to Question 3, and can be disposed of briefly. 32.The Plaintiff’s argument proceeds on the basis that 23,059 m3 of rockfill that had been deposited as part of the TWP by the Defendant and paid for under BQ Item 18 were reused (as sand equivalent) in the reclamation at CH +0550 to CH +2070. The Plaintiff argues that the “excavation, transportation and deposition” of the rockfill formed part of the scope of works under Extra Works No 20, and the scope of works for BQ Item 19 also included the “excavation, transportation and depositing” of the same material, and thus there is a complete overlap of the two items and the Arbitrator had allowed double recovery in respect of the reuse of 23,059 m3 of rockfill[44]. 33.The validity of the Plaintiff’s argument depends on the true nature of the scope of works under BQ Item 19 and Extra Works No 20. As pointed out by the Judge, the Arbitrator apparently accepted the Defendant’s case that Extra Works No 20 was an award for the “deposition” cost, without any element of excavation[45], while BQ Item 19 was concerned with measuring the quantity for “excavating” the rockfill only[46]. On that footing, there was no overlap between the 2 items. 34.While it is possible for different views to be taken as regards the true nature of the scope of works under BQ Item 19 and Extra Works No 20, as mentioned at §24(6) above, the mere fact that there could be different views on the true construction of a document does not lead to the conclusion that the tribunal’s conclusion was “obviously wrong” or “at least open to serious doubt”. The Judge took the view that it could not readily be seen that the Arbitrator’s decision was either “obviously wrong” or “open to serious doubt”. In the context of an appeal against an exercise of a discretion by the Judge, the question that this Court has to answer is whether the Judge was plainly wrong in coming to that view. We are not satisfied that the Plaintiff has successfully crossed this high threshold. 35.Having reached the above conclusions, it is not necessary to consider the Respondent’s Notice dated 7 March 2025, save to point out that, as argued by the Defendant at §7 of the Respondent’s Notice, the Arbitrator expressly rejected the Plaintiff’s case that the Subject Rockfill came from the rockfill removed from the TWP, holding that it had no factual support or basis. The rejection of this underlying premise means that the Plaintiff’s argument of double recovery by the Defendant under BQ Item 19 and Extra Works Item 20 cannot even get off the ground. For this reason as well, leave to appeal in respect of Question 3 ought to be refused. DISPOSITION 36.The Plaintiff’s appeal is dismissed, and the Judge’s order dated 22 November 2024 dismissing the Plaintiff’s originating summons filed on 24 June 2024 seeking leave to appeal against the Award of the Arbitrator is affirmed. 37.We further make an order nisi that the Plaintiff shall pay the Defendant’s costs of this appeal (including the costs reserved by the Judge when granting leave to appeal), to be taxed if not agreed. The above costs order nisi shall become absolute unless an application is made to vary the same within 14 days from the date of this judgment.
Mr Peter Clayton SC, instructed by Pinsent Masons, for the Plaintiff Mr Anthony Chan SC leading Mr Solomon Lam, instructed by Wong & Lawyers, for the Defendant [1] See §3 of the Articles of Agreement of the Subcontract. [2] See §3(1) of the General Conditions of Subcontract. [3] See §23 of the General Conditions of Subcontract. [4] See §2a of Schedule 1 to the General Conditions of Subcontract. [5] See §2b(23) of the Special Conditions of Subcontract. [6] See §21.09S of Section 21 (Marine Works) of Part 14 (Construction Specification) of the Main Contract. [7] The Arbitrator assessed sand fill at the rate of $150 per m3, and public fill at the rate of $47 per m3. [8] See §52.17 of the Reasons. [9] See §§52.18 and 52.19 of the Reasons. [10] See §§48 and 54.1 of the Reasons. [11] See §54.2 of the Reasons. [12] See §54.5 of the Reasons. [13] See §§54.3 and 54.4 of the Reasons. [14] See §54.4 of the Reasons. [15] See §54.7 of the Reasons. [16] See §54.7 of the Reasons. The figure of HK$3,295,155.90 mentioned in that paragraph relates to a separate Sub-Item 9 in BQ Item 17 which is not relevant for the present purpose. [17] See §4.1 of the “Grounds of Application and Appeal” annexed to the Plaintiff’s Originating Summons dated 24 June 2024. [18] See BQ attached to the Subcontract as Appendix 4, and BQ Item 18 on p11 of the Award. [19] See §§61 and 63 of the Reasons. [20] See BQ attached to the Subcontract as Appendix 4, and BQ Item 19 on p11 of the Award. [21] See §§64.7 and 66 of the Reasons. [22] See Extra Works Item CSHK 020 on p15 of the Award. [23] See §166.1 of the Reasons. [24] See §165.1 of the Reasons. [25] See §165.10 of the Reasons. [26] See §167 of the Reasons. [27] See §§165.7-165.9 and 169 of the Reasons. [28] See §6.1 of the “Grounds of Application and Appeal” annexed to the Plaintiff’s Originating Summons. [29] See §13 of the Decision. [30] See §14 of the Decision. [31] See §§15-16 of the Decision. [32] See §§17-22 of the Decision. [33] See §23 of the Decision. [34] See §24 of the Decision. [35] See §25 of the Decision. [36] See §37 of the Decision. [37] See §§38-42 of the Decision. [38] See §§43-44 of the Decision. [39] See §6 of the Leave Decision. [40] See §10 of the Leave Decision. [41] See §§2.5 to 2.7 of the Plaintiff’s Skeleton Argument dated 27 February 2026. [42] See §§46 and 54.1 of the Reasons. [43] See §47of the Reasons. [44] See §§3.3 to 3.5 of the Plaintiff’s Skeleton Argument. [45] See §44 of the Decision. [46] See §43 of the Decision. | ||||||||||||||||||||||||||||||
Cases cited in this judgment