Malaya Banking Berhad v. China Insurance Co. Ltd.
Read the full judgment text of HCCT 48/1999 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 10 September 2002 before Hon Burrell J in Chambers.
Construction law — Performance bonds — Contract termination — Clause 24 of Development Agreement — Order 14A procedure — Application to strike out claim for wasted expenditure damages — Representative action and joinder — Defendant insurer issued a $30 million performance bond guaranteeing contractor's performance on a building project. The developer (UTIL) terminated the contractor (Molitoko) under Clause 24 due to alleged breaches, and the plaintiff bank acting for a syndicate claimed damages under the bond for wasted expenditure after the project was abandoned and left incomplete. Defendant applied to strike out the wasted expenditure claim as failing to disclose a reasonable cause of action and alternatively sought a determination under Order 14A limiting damages to additional completion costs under the contract. The defendant also applied to stay the proceedings pending joinder of other banks as co-plaintiffs. The court declined to determine the legal question under Order 14A without a trial because factual issues heavily influenced the claim validity. The strike out application failed as the pleaded claim disclosed a reasonable cause of action and the defence's abandonment assertion was a matter of fact to be determined at trial. The joinder stay was refused as the representative action was properly constituted and no compelling reason existed to add other banks as plaintiffs. Costs related to the plaintiff's abandonment of delay damages claim were reserved for later resolution.
Legal issues: Order 14A application on construction of Clause 24 · Striking out application under O.18 r.19 on Wasted Expenditure Claim · Joinder summons and representative action
Outcome: Defendant's summonses to strike out or dismiss the wasted expenditure claim and to stay proceedings pending joinder were dismissed. Plaintiff's action allowed to proceed with Maybank as representative plaintiff.
Cites 1 case
|
HCCT000048/1999 HCCT48/1999 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO.48 OF 1999 --------------------
-------------------- Coram: Hon Burrell J in Chambers Dates of Hearing: 3 and 4 September 2002 Date of Decision: 10 September 2002 -------------------- D E C I S I O N -------------------- 1.There are two summonses before the court. By the first, the defendant seeks a dismissal of the action by a striking out application and, alternatively a ruling under Order 14A to the same effect. By the second, the defendant seeks a stay of the proceedings pending the addition of two new plaintiffs. 2.The first summons involves an attack by the defendant on the validity of the damages claimed in the action. Originally two main heads of damage were claimed. They have been referred to as the "Delay Damages" claim and the "Wasted Expenditure" claims. Prior to the hearing Mr R. Tong, SC who appeared for the plaintiff with Mr A. Chan, informed the court that he would not be pursuing the "Delay Damages" claim and that the Statement of Claim would be amended to that effect in due course. This concession shortened the first summons to the extent that the issues now before the court are :
3.The plaintiff is one of three banks who lent money to United Trump International Limited ("UTIL") to buy and develop a building site. A firm called Molitoko became the contractors. The defendant insurance company (represented by Ms G. Li SC and Mr Thomas Lee) executed a performance bond in the sum of $30 million, in favour of UTIL, which guaranteed the performance of the contractor. After less than one year on site UTIL, in 1998, terminated Molitoko's contract. Molitoko has since gone into liquidation. In these proceedings the plaintiff's claim is limited to the value of the bond. 4.I now deal with the three issues in turn. Order 14A application 5.If the question posed under the O.14A application is answered in the affirmative the effect would be that the plaintiff's claim be dismissed, there being no remaining claims. 6.The court's approach to such an application has been recently summarised by Ma J in Rockwin Enterprizes Ltd v. Shui Yee Ltd & others [2001] HKEC 1102. It involves a three step approach as follows :
7.Put simply the question posed in the application is - having terminated the contract under clause 24 (thus, a contractual termination) are the plaintiff's damages limited to the additional costs of completing the contract? If so, the plaintiff cannot claim any loss under the heading of "wasted expenditure." 8.In fact, the contract never was completed. The site is now a car park. The issue goes to the heart of the case because the defence claim that the contract was terminated for reasons other than Molitoko's poor performance. They say the contract was abandoned and there is no causal link between the losses incurred by the plaintiff and the alleged breach for which the surety is answerable. 9.The plaintiff, on the other hand, puts its case quite simply that they will seek to prove that Molitoko were in breach of contract, termination followed as a result and the damages claimed flow from that breach. The damages claimed which they say flow from the breach come under two heads. Firstly, construction costs and secondly, interest payments. 10.The material parts of the clause in question, namely clause 24, which it is accepted by the plaintiff is the clause under which the termination was made, are as follows :
11.Ms Li submits that the whole of clause 24 contemplated the completion of the project. If, on the other hand, the project was abandoned and not completed, as she submits is the situation here, and if the expenses have been wasted as a result of the abandonment there can be no clause 24 damages for which the surety might be liable. 12.Although the court has been assisted by both counsel on the O.14A issue in some detail, having considered the matter, I feel I can deal with it quite shortly. Following the three step approach in the Rockwin case, I am not persuaded that the question posed in a pure matter of law or construction; I do not consider that I have all the material facts and matters before me to determine the question and I am not satisfied that it is a question which is suitable for determination under O.14A. Ultimately, there is a discretion whether or not to make a ruling under O.14A. Any court would think long and hard before making a ruling which would have the effect of dismissing a $30 million claim. Ma J made the following remarks when considering the exercise of the discretion :
13.I accept the plaintiff's submission that the question posed is not a question of pure law or construction. Whether or not the plaintiff is entitled to the damages it claims as a result of a termination under clause 24 is, in my judgment, likely to or may depend on findings of fact. Before a court can safely answer that question there would have to be, at least, some investigation into the circumstances of the termination. The plaintiff does not accept that at the time of the termination the project was being abandoned, which is at the heart of the defendant's submission. The issue of "abandonment" has been raised in the defence. The defence rely on it and to that extent there is a burden on them to prove it. 14.Moreover, even if the question posed under O.14A were pure law, as it involves an issue of construction of a contractual clause a court would be entitled to consider the factual matrix at the time of the contract to ascertain the true intentions of the parties. 15.In short, the bottom line is that I have no doubt that the court's discretion should be exercised to decline to answer the O.14A question. The legal argument alone does not equip the court to do so in this particular case. Mr Tong simply says - I will seek to prove the damages at trial. By that he means not merely that losses were incurred but that they were incurred as a result of Molitoko's defaults, thus making the bond payable. Regardless of the evidence, which the plaintiff submits it will be necessary to consider when the court ultimately decides the validity of the wasted expenses claim, Mr Tong points to clause 24.6 in support of his submission that as a matter of pure legal construction he has a plainly arguable case that the question posed should be answered in his favour. Clause 24.6 says : "On termination ... the developer shall pay ... any direct loss ... including without limitation, liquidated damages ...". The suggests that liquidated damages (which are now not claimed) is but one head of damage claimable. Striking out application under O.18 r.19 16.This is an alternative application which seeks the same result but by a slightly different route. It is primarily a pleading point. Ms Li's submission is premised on the basis that the project was abandoned. She argues that the fact of abandonment may be assumed from the fact that the damage claimed is wasted expenditure. 17.It is submitted by the defence that the pleading is deficient in two important respects. Firstly there is no reference in the Statement of Claim (as amended) that the project was, in fact, abandoned. Secondly, there is no plea to the effect that the contractor's default (for which the defendant would be liable under the bond) caused the abandonment and thus that the wasted costs flowed therefrom. It is argued that these are more than merely technical defects in the Statement of Claim. They are fundamental defects because no reasonable cause of action is disclosed due to the lack of a causal link between the alleged breach and the claimed damages. 18.After due consideration I have concluded that the application to strike out has not been made good, for the following brief reasons. 19.The test to be applied in a strike out application is to decide if the claim is uncontestably bad or is bound to fail. A claim for wasted expenses is not, of itself, bad in law.
20.This particular claim for wasted expenses is arguably not bad in law either. Mr Tong has demonstrated this in part by his resistance to the O.14A application. Moreover, the plaintiff's pleaded case does not make abandonment the central element of the claim. In argument Mr Tong emphasized that it was not the central element of the claim. He stands by the pleaded case which fully particularizes breach followed by termination followed by claimed damages which he recognizes he must prove flow from the breach. I agree that framed as it is, there is no necessity to plead "why, when and by whom" the project had been abandoned. It is fundamental in a striking out application that the matters pleaded by the plaintiff must be assumed to be facts for the purpose of the application. 21.Looking at the pleading as a whole it adequately sets out the plaintiff's case. It is apparent from the pleaded defence that it is understood by the defence that the claim is based on allegations of default by Molitoko. The defence goes on to say that the claimed losses would have arisen irrespective of Molitoko's alleged defaults because in truth the project was abandoned. That is a matter of fact for the defence to prove. The amended Statement of Claim however avers that at the time of the termination it was UTIL's intention to continue the project. In any event, the pleadings still require some further amendments described by Mr Tong as "tidying up" arising out of this application. Joinder summons 22.The plaintiff, Maybank, is only one of three banks which provided the loan to UTIL to embark on the project. They sue "as agent and on behalf of the syndicate of ... (the three banks)". Ms Li seeks an order that the proceedings be stayed until the other two banks consent to being joined as co-plaintiffs. In fact, they do not wish to be co-plaintiffs and have consented to being represented by Maybank. 23.The defence take no issue with Maybank's contractual right to represent the co-lenders. However they invite the court to exercise its residual discretion not to let the case proceed in its present form. In my judgment there are several reasons why this discretion should not be exercised.
24.In conclusion both counsel invited the court to be silent on the question of costs in this decision. Even though both applications by the defence have been unsuccessful there remains an issue on costs arising out of the plaintiff's abandonment of its "Delay Damages" claim. The parties may now attempt to agree an appropriate costs order. If that is not possible a short hearing will have to be fixed in due course.
Representation: Mr Ronny K.W. Tong, SC leading Mr Anthony Chan, instructed by Messrs Simmons & Simmons, for the Plaintiff Ms Gladys Li, SC leading Mr Thomas Lee, instructed by Messrs Masons, for the Defendant Remarks: Appeal by the Defendant to the Court of Appeal. Appeal allowed. Please refer to the appeal judgment of CACV000424/2002. |
Cases cited in this judgment