Lanbase Surveyors Ltd. v. Holyrood Ltd.
Read the full judgment text of HCA 481/1999 on BabelCite. This High Court CFI judgment was delivered on 25 September 2002.
1. The plaintiff is an incorporated firm of surveyors. It is suing the defendant for the balance of professional fees in the sum of $952,800.
Cited by 1 case
|
HCA000481A/1999 HCA481/1999 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO.481 OF 1999 ---------------------
------------------------- Coram: Deputy High Court Judge Fung in Court Dates of Hearing: 19 - 20 September 2002 Date of handing down Judgment: 25 September 2002 ------------------------- J U D G M E N T ------------------------- 1.The plaintiff is an incorporated firm of surveyors. It is suing the defendant for the balance of professional fees in the sum of $952,800. The Background 2.The following background are not in dispute. 3.The defendant is the developer of Inland Lot No. 7878 on the Peak. P&T Architects and Engineers ("P&T") is the architect for the defendant. The defendant has applied to the Lands Department for modification of the lease. By a letter dated 27 April 1998, the Lands Department informed the defendant that the premium payable was $13.8 million. 4.By a letter dated 11 May 1998 sent by P&T to the plaintiff, P&T sought the advice of the plaintiff on the following :
5.By a letter dated 13 May 1998 sent by the plaintiff to P&T, the plaintiff stated the following :
6.On 18 May 1998, the defendant countersigned the above letter and confirmed and accepted the terms of the letter ("Engagement Letter"). 7.By a letter dated 20 May 1998 sent by the plaintiff to the Lands Department, the plaintiff stated the following :
8.On 16 June 1998, the plaintiff enclosed the draft written submissions to the Lands Department for P&T's comment. 9.On 19 June 1998, the plaintiff submitted to the Lands Department the appeal against the premium assessment and the written submissions stated that the premium should be reduced to $2.57 million ("1st Submissions"). 10.On 30 September 1998, the plaintiff submitted the revised premium assessment for the reference of the Lands Department and stated the premium should be further reduced to $990,000 ("2nd Submissions"). The 2nd Submissions were prefaced by the following :
11.By a letter dated 9 October 1998 sent by the defendant to the plaintiff, the defendant stated the following :
12.By a letter dated 19 October 1998 sent by the Lands Department to the plaintiff, the Lands Department stated the following :
13.On 20 October 1998, the plaintiff wrote to the defendant c/o P&T informing the premium reduction of 86.3% from $13.8 million to $1.89 million. The plaintiff enclosed the debit note for the professional fee of $952,800 being 8% of the reduction in premium. 14.On the same day, P&T wrote to the defendant referring to the premium appeal submitted by the plaintiff on behalf of the defendant and informed the defendant of the reduction. 15.On 6 November 1998, P&T wrote to the defendant referring to the premium appeal submitted by the plaintiff on behalf of the defendant and reminded the defendant that the Lands Department's revised premium offer was open for acceptance until 9 November 1998. 16.On 9 November 1998, the defendant accepted the revised premium in a telephone conversation with P&T. On the same day, P&T wrote to the plaintiff informing it the acceptance by the defendant and asked the plaintiff to proceed with the written acceptance letter to the Lands Department before 9 November 1998. The plaintiff's case 17.The plaintiff's case is as follows:
18.Mr C K Chan ("Chan"), a director of the plaintiff at the material time, gave evidence for the plaintiff. Chan said that the so called premium appeal procedure was an administrative procedure and was not laid down in any statutory rules. Once the surveyor gave notice to appeal and the administrative fee was paid, the case would be put in the queue pending consideration at an internal meeting of the Lands Department. There was no fixed appeal period but the waiting time was usually about two months. The relevant date for the assessment of the premium would be the date of the internal meeting. Hence, the surveyor would find out the date of the internal meeting and keep track of any adjustments between the date of the initial submissions and the meeting. 19.Chan said his assistant found out the date of the internal meeting. Shortly before 30 September 1998, he telephoned Mr James Cho ("Cho") of the Lands Department to discuss the matter and Cho said the arguments in the 1st Submissions were quite clear already. He wanted to refer to further comparables and Cho suggested that he send in further submissions in writing. 20.After he received the letter dated 9 October 1998 from the defendant, he had two telephone conversations with Mr Charles Woodhouse ("Woodhouse"), General Manager of the defendant at the material time. Chan refused to accept a fee cut. Woodhouse never terminated the service of the plaintiff. There was no conversation before 30 September 1998. The defendant's case 21.The defendant's case is as follows :
22.Woodhouse gave evidence for the defendant. He said after 15 September and before 30 September 1998, he had two telephone conversations with Chan. In the first conversation, he complained that the plaintiff was late in making the 1st Submissions, and unless the plaintiff was willing to accept a substantial reduction of fee to about 10% of the 8%, its service would be terminated. Chan said he had to consult his partners. In the second conversation, Chan refused to reduce the fee and he terminated the plaintiff's service. 23.Woodhouse said the defendant's letter dated 9 October 1998 was signed by Mr Law Fong, director of the defendant, and not himself. Both Law and himself agreed that the plaintiff's service was terminated, but Law was kind hearted and did not want to mention it in the letter. 24.Woodhouse was involved in the premium assessment of the redevelopment of the Depot of the China Motor Bus. Unlike the present case, there was negotiation between the developer and the Government. Termination of service 25.Mr Au for the defendant submitted that P&T had made it clear to the plaintiff that the appeal must be proceeded with as a matter of urgency, and the defendant stated in the Engagement Letter that the preparation of the appeal would take about two weeks. Hence, it should be implied as a term of the Engagement Letter that time was of the essence and the 1st Submission should have been lodged within about two weeks. The defendant was entitled to terminate the plaintiff's service for delay in making the 1st Submissions. 26.Alternatively, the Engagement Letter could be terminated by the defendant giving reasonable notice. 27.Mr Yin for the plaintiff that the "timetable" of about two weeks for the preparation of the appeal was an indication only in response to P&T's enquiry and the use of the word "about" could not make time the essence of the Engagement Letter. 28.I reject Woodhouse's evidence that he had ever terminated the plaintiff's service in late September. Termination was not mentioned in the defendant's letter dated 9 October 1998. The letter mentioned the lodging of the 1st Submissions in six instead of two weeks, and sought a reduction in fee. I see nothing in any kind heartedness in not mentioning any termination if it had taken place. I also fail to see why P&T were not informed if the plaintiff's service had been terminated. 29.Further, even if there were breach of the implied time clause, the defendant must have waived it and affirmed the contract. The 1st Submissions were sent to P&T for comment before submitted to the Lands Department. No complaint was raised. All subsequent correspondence between P&T and the plaintiff and/or the defendant pointed to the engagement of the plaintiff still being on foot. 30.I find that the defendant has never terminated the service of the plaintiff prior to the acceptance of the revised premium assessment by the defendant. Hence, it does not befall me to find whether time is of the essence of the Engagement Letter, or whether the defendant is entitled to terminate the plaintiff's service by giving reasonable notice. Negotiation Fee 31.Mr Au submitted that on the proper construction of the Engagement Letter, two fees are chargeable :
32.Mr Au referred to the meanings of "negotiation" and "negotiate" in The New Shorter Oxford English Dictionary on Historical Principles :
33.Mr Au submitted that negotiation needs not be oral, but must be interactive, to and fro, with a view to a compromise. 34.Mr Au submitted that the appeal was lodged when the 1st Submissions were made on 19 June 1998, and not by the plaintiff's letter dated 20 May 1998, which was only an intention to lodge an appeal later. There was no evidence of any negotiation subsequent to the lodging of the appeal. Contacting and enquiring as to when the appeal would be considered could hardly be negotiation. The 2nd Submissions were included in the fixed fee and were not part of the subsequent negotiation. 35.Mr Au submitted that Chan's evidence that he had contacted the Lands Department and Cho suggested him to put in further written submissions was not credible as it was not mentioned in Chan's witness statement, but instead, Chan stated that he put in the further submissions in view of the movement of the property market since the lodging of the appeal. Chan originally said he requested a meeting with Cho but Cho said it was not necessary as the 1st Submissions were quite clear. Under cross-examination, Chan said he could not recall whether he requested a meeting. 36.I accept the evidence that Chan had contacted Cho to discuss about the revised assessment shortly before the 2nd Submissions. The 2nd Submissions were prefaced that the revised premium assessment were submitted for the reference of the Lands Department as per request. 37.Looking at the Lands Department's letter dated 19 October 1998, it is clear that the Lands Department regarded the appeal was initiated by the plaintiff's letter dated 10 May 1998. It stated that the plaintiff's counter-offer was unacceptable to the Government. It re-offered the revised premium of $1.89 million to the defendant, which was open for acceptance within 21 days. I find it beyond reasonable argument that such a process of counter-offer and re-offer is a process of negotiation, albeit in writing. 38.I find that the plaintiff did represent the defendant in negotiation by means of the 1st and 2nd Submissions and the telephone conversation between Chan and Cho of the Lands Department. Rejection of the appeal 39.Mr Au referred to the statement of Chan that the extent of reduction of the premium after the appeal was due to the in-depth research, market analysis and good presentation of argument put forward in the appeal submission rather than the downturn of the property market. As the appeal was rejected by the Lands Department, the plaintiff's efforts were fruitless and not causative of any premium reduction offered by the Government. 40.Mr Yin submitted that the 1st and 2nd Submissions constituted negotiation with the Lands Department, and the state of the property market was fortuitous. The structure of a percentage contingency fee best reflected the reward of the plaintiff's efforts being dependant on the result of the reduction. As the 1st Submissions were adequate, it would be too whimsical to depend on whether any revised submissions were required. 41.It should be noted that the Lands Department did state in their letter of 19 October 1998 that after reviewing the case with reference to the plaintiff's submissions, the Government was prepared to revise the premium to $1.89 million. The Lands Department clearly referred to the plaintiff's submissions in offering the reduced premium. I reject the argument that the plaintiff's work was not causative of the premium reduction. 42.Granted that property prices must have come down during the relevant period. After all, premium assessment is concerned with relevant movements in the property market. In the instant case, all the conditions for the lease modifications were accepted apart from the premium figure. There is nothing incongruous between the plaintiff's efforts and the downward trend in the property market. Conclusion 43.Judgment is entered in favour of the plaintiff in the sum of $952,800, with interest at judgment rate from the date of the writ. Subject to any costs order made previously, the defendant shall pay the costs of the action to the plaintiff.
Representation: Mr Michael Yin, instructed by Messrs A. Tse & Fung, for the Plaintiff Mr Thomas Au, instructed by Messrs P.C. Woo & Co., for the Defendant |
Other judgments that cite this case
Further hearings and rulings under HCA 481/1999