Read the full judgment text of HCCW 000246/1999 on BabelCite. This High Court CFI judgment was delivered on 1 December 1999.
1. The petition has been issued by a sub-contractor of the Company which is the main contractor of a building project. The petition is based on interim certificates which have been issued in favour of the Petitioner. On 9th November 1999, the petition was heard and it was also heard on 10th November 1999.