Chun Wo Building Construction Ltd. v. China Merchants Tower Co. Ltd.
Read the full judgment text of HCCT107/1999 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 20 January 2000 before Hon Burrell J in Chambers.
Construction law — Arbitration — Consolidation or concurrent hearing of arbitrations — s.6B Arbitration Ordinance (Cap.341) — Common questions of law and fact — Interrelated claims on delay, liquidated damages, and indemnity — Back to back contract clauses — Evidence from same architect for all contracts — Prematurity objection rejected — Cost and efficiency considerations. Chun Wo Building Construction Ltd applied for the three arbitrations relating to construction contracts to be heard concurrently under s.6B. The 1st respondent opposed on grounds of insufficient commonality; the 2nd respondent on prematurity; the 3rd respondent consented. The Court found substantial common legal and factual issues, particularly delay and indemnity claims, common terms and architect’s role, and held that consolidation or concurrent hearing was appropriate. Prematurity objection was dismissed in light of sufficient issue identification. Costs were ordered against the 1st and 2nd respondents. Orders granted to hear the arbitrations concurrently.
Legal issues: Application to consolidate arbitration hearings under s.6B of the Arbitration Ordinance · Prematurity of application for consolidation
Outcome: Order granted to hear the three arbitrations concurrently under s.6B Arbitration Ordinance; order nisi for costs in favor of the applicant against the 1st and 2nd respondents.
|
HCCT000107/1999 HCCT107/1999 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO.107 OF 1999 -------------------------------
------------------------- Coram: Hon Burrell J in Chambers Date of Hearing: 13 January 2000 Date of Judgment: 20 January 2000 ------------------------- J U D G M E N T ------------------------- 1. This is an application by Chun Wo Building Construction Ltd (the applicant) who seeks an order that three arbitrations in which it is involved be heard together pursuant to s.6B of the Arbitration Ordinance, Cap.341. 2. The first arbitration arises out of a construction contract between the applicant as the main contractor and China Merchants Tower Co. Ltd as the employer (the 1st respondent). 3. The second arbitration arises out of a contract between the applicant and one of two nominated subcontractors, Chevalier (HK) Ltd (the 2nd respondent). 4. The third arbitration arises out of a contract between the applicant and the other nominated subcontractor, Cerberus Hong Kong Ltd (the 3rd respondent). All the contracts relate to the same development. The two subcontracts were for air-conditioning and fire safety installations respectively. 5. The 1st respondent opposes the application on the ground that the applicant has failed to show sufficient commonality of issues to be determined. The 2nd respondent opposes on the ground that the application is premature and should be adjourned because the issues have not yet sufficiently crystallized for the court to be able to determine whether or not there is sufficient commonality. The 3rd respondent does not oppose the application and consents to concurrent hearings. 6. Section 6B of Cap.341 provides as follows :-
7. This confers a discretion on the court but the discretion should not automatically be exercised merely because there is some commonality of issues however small. The applicant must show sufficient commonality. In Dickson Construction Co. Ltd v. Schindler Lifts (HK) Ltd, CA 125/92, Nazareth JA said :-
8. The principal factors which are relevant to the court's determination and which were advanced one way or the other by counsel in this application are as follows :- 1. The terms for payment under the subcontracts were "back to back" with the terms in the main contract. Clause 11 (to which I shall refer later) is common to all three. One of the two main issues between all the parties is the question of delay, namely, was there delay giving rise to liquidated damages, if so, how much and who was responsible for it? Mr Pow, for the applicant, contends these issues are inter-related. Mr Shaw, for the 2nd respondent, submits they are not. He submits that any issues of delay in the main contract are not relevant to arguments about delay in the subcontracts. It is not necessary to recite his argument further because one thing is clear, namely, that the parties do not agree on the proper legal effect of the material terms concerning the question of delay in their respective contracts. To this extent, there are clearly common issues in the legal argument on the question of delay. Mr Pow submits there is a claim of indemnity between all parties. He argues that if the applicant is liable to the 1st respondent and the applicant successfully argues that the 2nd and 3rd respondents are liable to him, then the 2nd and 3rd respondents would be liable to indemnify the applicant. In my judgment, the fact that Mr Shaw may not agree with this is not the point. It is one of the matters which the arbitrator will have to determine. 2. As with many construction disputes, much will depend on the architect's evidence and the certificates he issued. It is the same architect in all three sets of proceedings. The proceedings, taken together, are two subcontracts flowing from a main contract. They can and should be regarded as the same series of transactions about which it would be desirable and sensible for the architect to give evidence on one occasion only. 3. In the main action between the applicant and the 1st respondent, the respondent is firstly counterclaiming about $30 million in liquidated damages for delay. Its second counterclaim relates to alleged defects. It counterclaims specific defects against the applicant only but also unspecified defects generally. The 2nd and 3rd respondents are not specifically excluded from responsibility for the alleged unspecified defects. They should therefore not be excluded from the arbitration when evidence of defects is being given. If the first arbitration is heard separately, they would be. 4. Section 11(b) 9. As referred to earlier, this applies to all three contracts. It states :-
10. It is not necessary to recite the factual issues between the parties arising out of this provision. The issues of the calculation of liquidated damages, set-off and the liability to indemnify will be common issues. In my judgment it does not seem realistic to divorce these arguments in the main contract from the same arguments in the subcontracts. A similar situation arose in Re Shui On Construction Co. Ltd v. Schindler Lifts (H.K.) Ltd [1986] HKLR 1177 where Rhind J at page 1186 said :-
5. Convenience 11. This on its own is not a ground to order concurrent hearings. However, if sufficient commonality is made out, the fact that the advantages in hearing the arbitrations together clearly outweighs the disadvantages is a factor to be taken into account. 12. During this hearing the court was informed that a very experienced and respected arbitrator, Mr Bruce Humphreys, was available and acceptable to all parties as the arbitrator for all three cases. The same arbitrator conducting one set of proceedings will prevent inconsistent findings on law or fact. Furthermore, it eliminates concerns such as those expressed by Lord Denning MR in Abu Dhabi Gas v. Eastern Bechtel Corporation [1982] 2 Lloyd's Rep. 425 :-
and :
13. Once the same arbitrator is seized of the whole matter, consistent and practical directions and interlocutory orders will also inevitably follow. 6. Time and cost 14. There is no doubt that the first arbitration between the applicant and the 1st respondent involves the greatest amount of money and would last significantly longer than the other two, if heard separately. What is also inevitably true is that the time for hearing them together would be significantly shorter than the total time for hearing them individually. 15. I am satisfied that the costs to be incurred by the two subcontractors by being involved in a concurrent hearing need not be very much greater (or even need not be greater at all) than if each case were heard separately. In concurrent hearings (unlike with a consolidated hearing) the different parties need not attend the hearing on every day. The arbitrator will be able to regulate the proceedings so that the parties need only be present at the relevant times. Indeed the 3rd respondent does not oppose this application on the basis that it wishes to keep its costs to a minimum. It has not incurred costs in this application and it will only attend the combined arbitration when that part of the proceedings which concerns it is being heard. The same considerations apply to the 2nd respondent. 16. As far as the 1st respondent is concerned, Mr Ip readily concedes that, as the main party, its liability to costs will be effectively the same whether the 2nd and 3rd respondents are included or not. He also concedes that their inclusion will not lengthen the duration of his case by a significant amount. There is no prejudice to the 1st respondent by including the 2nd and 3rd respondents. His sole submission is on the sufficiency of the commonality. 17. Mr Shaw's sole submission is that the application is premature. (It follows therefore that the order sought may be the proper order in due course). With respect I do not agree that it is premature. A substantial amount of paper has already been generated, affidavits have been filed, issues have been identified in correspondence and in reality no significant mysteries remain about what will be the arbitrator's task. Rhind J in the Re Shui On case dealt with this argument in the following way :-
18. In conclusion and for the above reasons, I am satisfied that I should exercise my discretion in the applicant's favour. I am satisfied that sufficient common issues have been made out and that this is an appropriate time to make the order. I therefore make the order as sought by the applicant in its originating summons dated 3 November 1999. I further make an order nisi as to the costs of the application that they be paid by the 1st and 2nd respondents.
Representation: Mr Jason Pow, instructed by Messrs Lovell White Durrant, for the Applicant Mr Francis Ip of Messrs K.F. Wong & Co., for the 1st Respondent Mr Geoffrey Shaw of Messrs Deacons Graham & James, for the 2nd and 3rd Respondents |
Further hearings and rulings under HCCT107/1999