Goldspeed Investment Ltd. v. Easy Success Enterprises Ltd.
Read the full judgment text of HCA 8187/1998 on BabelCite. This High Court CFI judgment was delivered on 5 April 2000.
1. This case concerns the construction of a clause commonly used in the sale and purchase of units of building under construction. It is Clause 16 of the agreement entered into between the parties here.
Cited by 1 case · Cites 1 case
|
HCA 8187/1998 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO. 8187 OF 1998 ____________
____________ Coram: Deputy Judge S Kwan in Court Date of Hearing: 28 March 2000 Date of Handing Down of Judgment: 5 April 2000 _______________ J U D G M E N T _______________ 1. This case concerns the construction of a clause commonly used in the sale and purchase of units of building under construction. It is Clause 16 of the agreement entered into between the parties here. 2. The parties had placed before me a bundle of agreed documents. No witness was called and I was told that the witness statements filed in Court can be disregarded in this trial. 3. The relevant facts are as follows. 4. An agreement for sale and purchase dated 21 April 1994 ("the Agreement") was entered into by the Defendant as the vendor, Chuang's Properties Limited as the financier and the Plaintiff as the purchaser for the sale and purchase of the 7/F ("the Property") of a commercial building at Nos. 376-382 Lockhart Road, Hong Kong, which was then under construction. The purchase price was HK$25,200,000.00, of which 30% being HK$7,560,000.00 had been paid by the Plaintiff to the Defendant when the Agreement was terminated by the Defendant in the circumstances described below. 5. The sale and purchase was to be completed within 14 days of the Plaintiff being notified in writing that an Occupation Permit had been issued and that the Defendant was in a position validly to assign the Property to the Plaintiff. Such notice was given by the Defendant's former solicitors in a letter dated 8 May 1995 to the Plaintiff's solicitors, stating that completion was to take place not later than 4 pm on 22 May 1995. On 22 May 1995, the Defendant accepted the Plaintiff's request for an extension of time and agreed to extend the time for completion to 4 pm on 6 June 1995. On 5 June 1995, the Plaintiff's solicitors notified the Defendant's former solicitors that the Plaintiff was not prepared to proceed with the purchase of the Property and returned all relevant title deeds and documents. 6. On 14 June 1995, the Defendant's former solicitors wrote to the Plaintiff's solicitors demanding the Plaintiff to complete the sale and purchase and to make good the default including payment of the balance of the purchase price in the sum of HK$17,640,000.00 and HK$62,319.00 being the costs of completion, stamping and registration. In that letter, it was stated that unless the aforesaid sums with interest were paid and the sale and purchase completed within 21 days from the date thereof, the Defendant would forthwith enforce its right under Clause 16 to terminate the Agreement and forfeit all monies already paid by the Plaintiff. 7. The Plaintiff did not complete the sale and purchase. 8. On 6 July 1995, the Defendant's former solicitors wrote to the Plaintiff's solicitors and gave notice that "in accordance with Clause 16 of the Agreement, the Agreement is hereby determined and the deposit and all monies paid under the Agreement is hereby forfeited to [the Defendant]." It was also stated that the Defendant "reserves all its right and remedies against [the Plaintiff] under the Agreement and by law as a result of [the Plaintiff's] breach of the Agreement." 9. In September 1996, 14 months after the Defendant's termination of the Agreement, the Defendant re-sold the Property together with the 11/F of the building to another purchaser subject to existing tenancies for the total consideration of HK$35,280,000.00. 10. By a letter dated 26 April 1997 from the Plaintiff's solicitors to the Defendant, the Plaintiff demanded repayment of HK$5,040,000.00 being two part payments made by the Plaintiff to the Defendant. It was accepted in that letter that the Defendant was entitled to forfeit the deposit in the sum of HK$2,520,000.00. 11. The Defendant's solicitors replied by a letter dated 8 May 1997 denying liability to refund to the Plaintiff the sum of HK$5,040,000.00. They asserted that Clause 16 of the Agreement did not preclude the Defendant from maintaining its claim against the Plaintiff under common law for damages for breach of contract and for a set-off by reason of the same. It stated that at the material time of the Plaintiff's failure to complete, the open market price of the Property had dropped to about HK$15,000,000.00. The measure of the Defendant's damages would be the difference between the contract price and the market price at the time of breach, and that would be well in excess of HK$5,040,000.00. 12. On 21 May 1998, the Plaintiff issued the writ in this action. 13. I set out the material terms of the Agreement:
14. In the Statement of Claim, the Plaintiff claims payment of HK$7,560,000.00, being all the monies paid by the Plaintiff under the Agreement. Sir John Swaine, SC, who appears for the Plaintiff, informed me that the Plaintiff seeks to recover only HK$5,040,000.00 being the two part payments, which was the position taken by the Plaintiff's solicitors in their letter dated 26 April 1997. Two points were taken by him in his submissions:
15. Mr Warren Chan, SC, who appears for the Defendant, does not dispute that the Defendant would have no right to retain the monies received as part payment outside of Clause 16 in the event of a termination of the Agreement. This is well established by the authorities and I was referred by Sir John Swaine, SC to Harrison v. Holland [1921] 3 KB 297 and [1922] 1 KB 211 and Mayson v. Clouet [1924] AC 980 (a decision of the Privy Council on appeal from Singapore). I agree with the Plaintiff's submissions that any right of the Defendant to retain the part payments in the event of determination of the Agreement could only have arisen from the terms of the Agreement. In the absence of any such term, the Defendant would not be entitled, on the termination of the Agreement, to retain the part payments as security for any loss it might sustain on a resale. The suggestion to imply a term in the contract to the effect that the Vendor be at liberty to retain instalments for a reasonable time as security against loss in the event of default was rejected by the English Court of Appeal in Harrison v. Holland, supra. 16. In the present case, the Defendant had not complied with the pre-condition in Clause 16 in that the resale did not take place within 6 months of the termination of the Agreement by the Defendant. The Defendant cannot therefore rely on the right given to it under Clause 16 to retain the amounts received as part payment. This, however, is not the end of the matter as the Defendant has brought a counterclaim in this action claiming damages at common law in the sum of HK$10,200,000.00, being the difference between the contract price of HK$25,200,000.00 and the market price of HK$15,000,000.00 in July 1995, which brings me to the second point taken by Sir John Swaine. 17. It is the Plaintiff's contention that Clause 16 is a comprehensive and exhaustive provision of the Vendor's rights and remedies in the event of the Purchaser's breach. If the Defendant should fail to comply with the pre-condition in that provision, the Defendant is not entitled to claim damages at common law. 18. Clause 16 is, for all intents and purposes, identical to the provision cosidered by the Court of Appeal in Woomera Co. Ltd v. Provident Centre Development Ltd [1985] HKLR 263. The critical question considered in that case was whether the Vendors would be entitled to claim common law damages in the alternative for the purchasers' failure to complete in view of Clause 16. The Court of Appeal ruled unanimously that Clause 16 was not an exhaustive statement of the Vendors' rights and did not preclude a claim for common law damages. I set out the relevant parts in the judgment as follows:
19. Faced with Woomera, Sir John Swaine submitted that this decision is not binding on me because it was an interlocutory appeal concerned with whether amendments to a pleading were useless and immaterial and should not have been allowed by the trial judge, who did not make any final ruling on the construction point. This is of course correct. However, if one reads the judgment of Sir Alan Huggins, it would appear that the Court of Appeal had made a decision on the question of construction of Clause 16. Sir Alan Huggins has this to say in his judgment:
20. The decision of the Court of Appeal in Woomera on a construction of a provision which is identical to Clause 16 for all intents and purposes is binding on me. In any event, I agree entirely with the reasoning and the construction of the Court of Appeal. I was also referred by Mr Warren Chan to a decision of Waung J in Ford Joint Ltd v. Keen Lloyd Market (Holdings) Ltd HCA No. 21393 of 1998, 27 August 1999, in which Waung J drew on the "powerful support" of the Court of Appeal in Woomera and came to the conclusion that there is no arguable case of legal displacement of common law damages as the clause he was concerned with (which was similar to Clause 16 but worded differently) is not exclusive or exhaustive of the remedy available to the Vendor. 21. Having reached the conclusion that the Defendant has no right to retain the part payments by virtue of Clause 16 and that Clause 16 does not preclude the remedy of common law damages, where does that leave the parties? 22. There is undisputed evidence before me in the form of a valuation report that the open market value of the property as at 6 July 1995 was HK$15,000,000.00. Hence, the difference between the contract price and the market price at the day of termination is HK$10,200,000.00. The Defendant is entitled to recover the difference in price being damages based on the Plaintiff's repudiation at common law. Mr Chan informed me that the Defendant has abandoned the claim for legal and other costs and expenses relating to the aborted sale and purchase pleaded in the Counterclaim. 23. The net result of this is that although the Defendant cannot deduct the unliquidated damages from the part payments, the Defendant has a good cross claim for such damages in the Plaintiff's action. In this regard, I set out the dicta of Dixon J and Millett J in the following cases:
24. The counterclaim raised by the Defendant is sufficient to extinguish the Plaintiff's claim for return of the part payments in the sum of HK$5,040,000.00. The Defendant would also have to give credit for the deposit forfeited in the sum of HK$2,520,000.00. The net sum the Defendant is entitled to recover from the Plaintiff is HK$2,640,000.00. As against a claim arising out of a transaction between the parties, there could be set-off in equity a cross claim arising under the same transaction whether sounding in debt or unliquidated damages, which is the case here (Hanak v. Green [1959] 2 QB 9). There being an equitable set-off so that the Plaintiff's claim is extinguished, the proper order I should make is to enter judgment for the Defendant with costs on the claim and for the balance of the amount of the counterclaim in the sum of HK$2,640,000.00 with costs. I would add that if there were no equitable set-off of the counterclaim, I would still have given judgment for the Defendant for the balance of HK$2,640,000.00, under O. 15 r. 2(4) of the Rules of the High Court. 25. I would award interest on HK$2,640,000.00 at the rate of 1% above the prime rate of the Hong Kong and Shanghai Banking Corporation from 6 July 1995 to the date hereof. The order nisi I make as to costs shall become absolute 14 days after this judgment if no application is made in the meantime to vary that order.
Representation: Sir John Swaine, SC instructed by Messrs Van Langenberg & Lau, for the Plaintiff Mr Warren Chan, SC and Ms Jennifer Tsui, instructed by Messrs Deacons Graham & James, for the Defendant |
Cases cited in this judgment
Other judgments that cite this case