Sun Kai Engineering Co. Ltd. v. Tileman Asia (HK) Ltd.
|
HCCT000056/1997 HCCT56/1997 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO.56 OF 1997 ----------------------
----------------------- Coram: Mr Recorder Kotewall SC in Court Dates of Hearing: 1, 2, 3 and 6 March 2000 Date of Judgment: 6 March 2000 ------------------------- J U D G M E N T ------------------------- Introduction 1. The plaintiff was a sub-sub-contractor engaged by the defendant on a project referred to as the Lamma Power Station, Phase III, Chimney No.3 ("the Project"). The defendant was a sub-contractor of Nishimatsu Construction Company Limited ("Nishimatsu"), the main contractor of the Project. The employer was the Hong Kong Electric Company Limited. The plaintiff was responsible only for the provision of workers for the concreting operation in respect of, for our purposes, the windshield structure of the chimney to be constructed by the slipform method. 2. The parties entered into a contract in writing by a Letter of Acceptance dated 8 June 1994. This, together with the tender submitted by the plaintiff according to the tender document dated 15 March 1994, was agreed by the parties before me to constitute the only contract between them on this project. The plaintiff's claims 3. The plaintiff's claims are under three heads :-
The defences 4. The defence to the three heads of claim, as pleaded in the amended defence, may be summarized as follows :- 5. First, in respect of the retention claim, the defence initially said that it had already paid everything which was due. In the course of the trial, the defendant which was, with the leave of the court, represented by Mr Leo Leung, an engineer, accepted that the sum claimed is payable, but Mr Leung made submissions as to when the balance of the contract price had to be paid. 6. Secondly, on the extension of time claim, four points are made by the defence :-
7. Thirdly, as for the demonstration claim, the defence says that this was part of the tender process, before the award of the tender, and the plaintiff is not entitled to be paid therefor. The contract 8. First, the terms of the Letter of Invitation of 15 March 1994 from the defendant to the plaintiff. This reads :-
9. Secondly, the terms of the Letter of Acceptance of 8 June 1994 from the defendant to the plaintiff. This reads :-
I note that no further formal sub-contract was entered into and this Letter of Acceptance was treated as one of the operative contractual documents. The retention claim 10. This is for $163,183.50. The Bills of Quantities annexed to the Letter of Acceptance listed the works and the total contract sum at $2,613,670.00. The plaintiff's claim for the retention is simple. It says that the contract price was $2,613,670.00; it was paid $2,450,486.50. There is, therefore, a balance of $163,183.50. The periods prescribed in paragraph 3 of the Letter of Acceptance have long since expired and payment should not have been withheld. 11. The defence is that while the plaintiff is entitled to the sum claimed, the expiry of the 12 months contract maintenance period under the main contract did not expire until much later and the defendant itself did not get paid until late 1998. Mr Leung thought that the retention monies should only have been released to the plaintiff upon the expiration of the Defect Liability Period on 14 September 1998. It is not in dispute that the chimney was certified to have been substantially completed by 31 January 1996. 12. Mr Tsang, for the plaintiff, made detailed and careful submissions on this point. His submissions can be summarized as follows. 13. He submitted that there were different due dates for the payment of different parts of the sum of $163,183.50. First, the limit of retention monies under paragraph 3 of the Letter of Acceptance is 5% of the contract sum, i.e. $130,683.50. This was the actual amount of retention money deducted by the defendant from the plaintiff's interim payments. Only this sum is thus subject to the timing for payment under paragraph 3 of the Letter of Acceptance. The difference, i.e. $32,500.00 is not retention money and represents the remaining unpaid contract sum which was payable upon completion of the plaintiff's contract works which occurred long before the certified practical completion date of the main contract. This sum of $32,500 should therefore have been paid by the latest, together with the first part of the retention money which I consider next. I should add that I agree that this is the correct position under the contract as I read it. 14. Secondly, as for the retention monies, Mr Tsang says that 2.5%, i.e. $65,341.75 should have been paid after the issue of the practical completion certificate. The completion certificate was dated 13 March 1996 certifying completion on 31 January 1996. In my view, this clearly was the contractual due date for this sum under paragraph 3 of the Letter of Acceptance. 15. Thirdly, as to the balance of the retention money, i.e. $65,341.75, this should have been paid on the expiry of the 12 months maintenance period, which would have commenced on the day after 31 January 1996. In other words, the operative date of payment for $65,341.75 was 31 January 1997. 16. In my judgment, this is the correct analysis of the contractual position and the different sums ought to have been paid on the dates set out above. The extension of time claim 17. This is for $720,000. This is the sum the plaintiff claims as damages for breach of contract by the defendant. The plaintiff relies in particular on clauses 4, 5 and 6 of the Letter of Acceptance and the second paragraph of the Invitation Letter dated 15 March 1994. 18. The plaintiff accepts that it was obliged to comply with the defendant's programme. No separate programme was attached to the Letter of Acceptance. I have been shown programmes of the defendant which show clearly that it was planned and envisaged that the windshield would be constructed in one continuous eight-week or two-month period. The crucial point, as it seems to me, turns on the construction of paragraph 6 of the Letter of Acceptance. On this point, it is to my mind clear that the contract period for the construction of the windshield was two months. Paragraph 6 does not provide for an estimate. It would be completely unmanageable for the plaintiff if it had to make all the necessary arrangements and pay for workmen only to be told, apparently at any time, that the defendant was entitled to suspend work or call for stoppages and presumably for which the plaintiff would have no recourse or recompense. In my judgment, the effect of clause 6 is clear. The plaintiff was to carry out the works within two months of the commencement date, which turned out to be 3 June 1994, and it had two months from 3 June 1994 with which to do so. 19. Mr Tsang submitted that a superior contractor has an implied duty not to prevent or hinder the sub-contractor from carrying out sub-contract works in accordance with the contract, and he relies on Jardine Engineering Corp. Ltd & Ors v. Shimizu Corp. [1992] 2 HKC 271. He says that the first defence, already averted to, raised by the defendant clearly has no merits. While the defendant could have opted for a different commencement date, once the work commenced, the plaintiff was entitled to carry out the work free from hindrance or prevention on the part of the defendant. 20. Here the evidence before me is to the effect that there were various stoppages arising out of a number of factors, none of which are the responsibility of the plaintiff. These are the delay or short supply of concrete, the breakdown of the hoist and the re-installation of another hoist which had been installed too close to the structure. 21. There was no issue as such on quantum and the defence to this part of the claim is as I have earlier summarized. 22. In the Jardine case, Kaplan J had to consider a number of issues including the scope of implied terms on the contract before him. Having summarized the law at pages 305 onwards, the learned judge referred to the well known dictum of Lord Blackburn in Mackay v. Dick (1881) 6 App Cas 251 at 263 as follows :-
23. I read this passage as a statement of the general law rather than, strictly speaking, an implied term based on the Moorcock (1889) 14 PD 64, and I accept its applicability on the facts and terms of the contract before me. 24. At page 314 of his judgment, Kaplan J considered and accepted submissions based on the decision in Wells v. Army & Navy Co-operative Stores Ltd [1903], Hudson's Building Cases, 4th Ed. at page 354. The learned judge said this :-
25. I should also refer to a passage from the judgment of Vaughan Williams LJ in Wells v. Army and Navy Co-operative Society as follows :
In my judgment, these passages contain useful guidance and are applicable to dispose of the first limb of the defence based on the extension of time claim. 26. As to the second head of defence, that is the so-called back-to-back defence, the only possible effect of the provision is to incorporate certain of the terms in the standard forms of the main contract and the subcontract into the contract. It may be that some of the terms of the different contracts are similar. It is not entirely clear which were the terms incorporated, or the effect of any of them. Be that as it may, none of the terms which may be incorporated can mean that the failure of the defendant to enforce a right under its contract with Nishimatsu can deprive the plaintiff of its rights under its contract with the defendant. 27. As to the third defence raised, whether the slabs might be cast at any time is not to my mind relevant since they do not form part of the same process for the construction of the windshield. They are separate items with different time frames as illustrated in the programmes which I have been shown. The Bills of Quantity show that the windshield was to be worked on a 24-hour basis but the slabs were not. Paragraph 6 of the Letter of Acceptance shows that the two items were considered quite separate and different as to when they have to be constructed. 28. The fourth defence is that there were no rates in the Bills of Quantities for daily wages of labour. This cannot, in my judgment, be relevant to a claim for damages in the circumstances obtaining. In any event, it was provided in clause 9.2(2) of the Standard Form of Subcontract that :-
29. The plaintiff is, of course, not claiming for works pursuant to an authorized variation; it is claiming damages for breach of contract. It must be unlikely for contracts of this nature to contain unit rates in anticipation of claims for damages for breach of contract. 30. For completeness, I ought to set out that I find proved the following :
31. I find that as a result of the foregoing, instead of completing the windshield in two months, it took the plaintiff from 3 June to 22 August 1994 to complete the work, in other words, the plaintiff took an extra 20 days and incurred extra costs, which it claimed, of $720,000, calculated at $1,000 per shift per workman with two shifts each day for a total of 20 days. Except for an item of $1,000, I find this part of the claim substantiated. As I said earlier, quantum was not seriously in issue. The amount I find proved is $710,000. The demonstration claim 32. This is for an amount of $39,000. This arose out of the defendant's instructing the plaintiff to arrange for 39 concretors to attend a concrete demonstration for the chimney No.3 on site on 24 May 1994. That, in essence, is the plaintiff's evidence of what happened and which is supported by a letter of 5 June 1994 asking for payment. 33. The defendant proffered very little by way of evidence of the circumstances surrounding the demonstration or the events or negotiations leading up to it. There is some inadmissible hearsay and an unsigned statement by a Mr Louie Lau on whose evidence I am unable to attach much weight. Mr McCrickard had no personal knowledge of what happened either. His oral testimony was to the effect that he thought that the demonstration was so that the plaintiff could prove that it was able to supply sufficient workmen to do the job, and that the defendant only agreed the contract price after that. When pressed with the defendant's tender analysis, Mr McCrickard very fairly accepted that it would seem that by 20 April 1994, the price had already been agreed. At the prompting of Mr Leung, he later modified that conclusion by saying that the defendant must have agreed the contract price at some time between 20 April 1994 and 9 May 1994, in other words, some considerable time before the demonstration. Mr McCrickard was not able to remember if the plaintiff was told that it would be paid or would not be paid for the demonstration and Ms Ng's evidence for the plaintiff is not inconsistent with that. 34. I find that there was no discussion as such as to payment, but Mr McCrickard emphasized and underlined the fact that the defendant had to satisfy itself of the plaintiff's capacity because the defendant had to demonstrate to Nishimatsu that the numbers of workmen required were available. He thought that representatives of Nishimatsu would have been present on 24 May 1994 to satisfy themselves of the numbers, that is to say the 39 workmen which the plaintiff arranged to bring on to the site at the defendant's instructions. 35. Mr Tsang submitted that a mere request from the defendant to the plaintiff in the absence of any clear expression or understanding that no reimbursement would be made to bring the 39 workers to Lamma Island would be sufficient to ground a claim based on quantum meruit. A fortiori, he says, if the request was for them to go and construct a mock-up. I agree. While the evidence does not indicate that much was done when the workmen got onto the site, I do not think that that matters overmuch. What matters is the request. 36. Mr Tsang referred to Keating on Building Contracts, 6th Ed., 1995 at pages 84-86. Although the principles on quantum meruit claims are not exactly esoteric, it is probably a useful exercise to refer to some of the passages in the text :
37. In all the circumstances, I find the plaintiff's claim on a quantum meruit made out in respect of the demonstration claim and I award under this head the sum of $39,000 on the basis of $1,000 for each concretor on 24 May 1994. 38. To summarize, the plaintiff succeeds :
It is entitled to interest on both these sums at the rate of 11.5% from the issue of the writ on 5 July 1996. The plaintiff has also succeeded on its claim in respect of the retention monies of $163,183.50. As to $97,841.75, interest will run from 31 January 1996 and as to $65,341.75, interest will run from 31 January 1997, in respect of both parts at the rate of 11.5%. All the awards of interest at 11.5% are up till today and thereafter at the judgment rate. Unless Mr Leung is able to persuade me to the contrary, the plaintiff is to have the costs of this action.
Representation: Mr David Tsang, instructed by Messrs Fung, Wong, Ng & Lam, for the Plaintiff Defendant in person, represented by Mr Leo Leung Kwok Kee of Tileman Asia (HK) Limited |
Cases cited in this judgment
Other judgments that cite this case