Hong Kong Housing Society v. China Insurance Co. Ltd.
Read the full judgment text of HCCT104/1999 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 23 March 2000 before Hon Burrell J.
Construction and Arbitration Proceedings — Performance Bond — Liability under unconditional on-demand bond — Interpretation of bond expiry clause relating to certificate of practical completion — Validity of contractor termination notice — Conclusive evidence provision effect — The plaintiff contracted with Hing Lee Construction to build a housing development secured by a performance bond from the defendant. Hing Lee was terminated for default, and the plaintiff engaged a new contractor for completion. Defendant argued bond expired on practical completion certificate issued to new contractor and alleged termination notice was late. The court held the bond remained effective because the certificate related only to the new contract, not the bonded contract with Hing Lee. The termination notice, although dated after the nominal period, was valid because defaults were ongoing and the bond's conclusive evidence clause established default and damages conclusively. The court found no defence and granted summary judgment in favour of the plaintiff for the bond amount plus interest and costs, with a certificate for two counsel.
Legal issues: Expiry of the bond under Practical Completion certificate · Validity of the Notice of Determination under the main contract · Requirement of contract determination to trigger bond liability
Outcome: Summary judgment granted to plaintiff for HK$32,460,000 plus interest and costs
Cited by 1 case
|
HCCT000104/1999 HCCT104/1999 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO.104 OF 1999 ----------------------------------------
------------------------- Coram: Hon Burrell J in Chambers Date of Hearing: 20 March 2000 Date of Judgment: 23 March 2000 ---------------------- J U D G M E N T ---------------------- 1. By this summons the plaintiff seeks summary judgment pursuant to Order 14 of the Rules of the High Court against the defendant in the sum of $32,460,000. The plaintiff contracted with Hing Lee Construction Company ("Hing Lee") in 1996 whereby Hing Lee became the main contractor in a housing development in Tseung Kwan O. The contract required Hing Lee to provide a surety bond to the plaintiff ("the Bond"). The defendant insurance company provided the Bond. The important clauses in the Bond are (3), (4) and (5) :-
2. The bond was for the sum of $32,460,000. 3. Problems emerged between the plaintiff and Hing Lee and by a letter of 31 March 1998 they determined Hing Lee's employment under the contract. The letter stated :-
The letter of 5 March referred to in this letter detailed the alleged defaults in compliance with clause 25(1) of the main contract which provided as follows :-
After determining Hing Lee's employment, the plaintiff entered into a new contract dated 18 September 1998 with Yiu Wing Construction Co. Ltd ("Yiu Wing") to complete the works. The development continued. The architect to the project, Simon Kwan & Associates remained the same. The architect issued its "certificate of practical completion" to Yiu Wing on 21 June 1999 certifying completion on 23 March 1999. 4. The plaintiff's call on the Bond against the defendant, to which this application refers, was by a letter of 13 September 1999 in the following terms :-
5. Because clause [4] (supra) of the Bond contains a conclusive evidence clause, the bond itself becomes, in effect, an unconditional on-demand performance bond, once the conclusive evidence clause has been complied with. There is no dispute that it was complied with. 6. The defence submits that it is at least arguable that there is no liability on it to pay under the Bond on either one of two grounds :-
7. I shall deal with each point in turn. (a) Expiry of the bond 8. I find this argument to be unsustainable. Both a common sense reading of the relevant clause and a recent U.K. authority combine to relegate this submission to the unarguable. 9. Mr Westbrook for the defendant argues that the words in the clause "Architect to the Contract" could be construed in the following way. The "architect to the contract" between the plaintiff and "Hing Lee" was Simon Kwan & Associates. They issued a practical completion certificate in June 1999 because the same architect continued under the new regime with "Yiu Wing". It is submitted that as the architect, Simon Kwan & Associates, issued a certificate and they had been the architect when Hing Lee had been employed, then the Bond comes to an end in accordance with clause 5. 10. I find this submission to be wholly without merit and unarguable. There is no dispute that the certificate in June 1999 was issued to the new contractor, Yiu Wing. It can only have related to a certification of the works completed by them and can only have been given by the architect in its capacity as the architect to the later contract which had nothing to do with Hing Lee. 11. If this conclusion requires any support by authority, it is found in the case very properly and helpfully brought to the court's attention by Mr Westbrook, De Vere Hotels Ltd v. Aegon Ins. Co. (U.K.) Ltd, C.I.L.L. February 1998. He valiantly sought to distinguish it on the facts but the inescapable reality was that on the issue in point, it was on all fours with the case before the court. There were no material differences in the wording of the bonds in question and the argument advanced by the defence was identical. The judge in the Official Referees Business in London, His Honour Judge Lloyd concluded :-
12. Mr John Bleach SC for the plaintiff correctly relies on the commentary to this case when it was said that the judge had little difficulty in :-
(b) Late notice of determination 13. I find this argument also to be unsustainable. Mr Westbrook's submission is as follows. 14. The notice of determination pursuant to clause 25 stated that the alleged failure "has continued during the 14-day period after the receipt of such notice and has been repeated thereafter". The 14-day period therefore runs from 5 March to 19 March. The 10-day requirement in clause 25 therefore runs to 29 March whereas the notice was dated 31 March. 15. He submits that if it is alleged that the defaults were repeated after the 14-day period, the notice should say so and say when. Thus, if the notice, on either view, was late, it is invalid and of no effect. 16. The submissions must fail for the following reasons. The reference to the defaults being "repeated thereafter" can only refer to after 19 March, the end of the 14-day period. The 10-day period in clause 25 is stated to be after the "continuance or repetition". If as alleged, the default is on-going, the 10-day period must also be on-going whilst the default is being repeated. 17. By virtue of the wording of clause 4 of the Bond itself, read together with the wording of the call on the Bond in September 1999, there is conclusive evidence of the default being repeated. The call attached a schedule of damages. The schedule listed the damages caused by the determination of Hing Lee. Thus, the plaintiff's compliance with clause 4 triggers the defendant's inescapable liability. For the sake of completeness, the call on the Bond states :-
18. I find it unarguable to suggest that this does not comply with clause 4 of the Bond. Once triggered, the conclusive evidence clause must be given effect. 19. Finally and in any event, the defendant has no defence to the plaintiff's claim for the following additional reason. A proper determination of the contract between the plaintiff and Hing Lee is not a condition precedent for payment under the Bond between the plaintiff and the defendant. It is proof of Hing Lee's default which creates the liability under the Bond, not the validity of the determination by the plaintiff as against Hing Lee. 20. For these reasons, I am satisfied that the plaintiff has crossed the high threshold necessary for judgment to be entered in its favour in Order 14 proceedings. There are no arguable defences. The defendants were parties to a strict on-demand performance bond. On the facts of the case, there are no conditions upon which they can rely to avoid liability. 21. Counsel also addressed the court on the question of costs and certificates for counsel. I make the following order :-
Representation: Mr John Bleach, SC, leading Mr Stewart K.M. Wong, instructed by Messrs Johnson, Stokes & Master, for the Plaintiff Mr Simon Westbrook, instructed by Messrs Masons, for the Defendant |
Other judgments that cite this case