James Lau & Associates Ltd. v. Tom Ip & Partners Architects, Engineers & Development Consultants Ltd. and Another
Read the full judgment text of HCCT 55/2000 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 20 July 2001 before Hon Burrell J.
Contract law — Construction and professional services — Fee calculation and quantum meruit — Liability for site supervision fees — Implied terms of payment — Agency and personal liability — Illegality defence — Counterclaim for damages — Interpretation of contracts and letters of estimate — Buildings Ordinance provisions — Authority of signatories in contracts. The plaintiff, a structural engineering firm, claimed unpaid fees totaling over $2.8 million for design and site supervision services rendered between 1993 and 1998. The court held that the plaintiff's fees on the Lockhart Road project should be calculated as 0.8% of the total construction cost subject to adjustment, applying a quantum meruit method. The 1st defendant was found liable for supervision fees, rejecting defences of implied 'pay when paid' terms, agency exemption, and illegality under the Buildings Ordinance, noting the late enactment of sanction provisions and no objection from regulatory authorities. The contract sum for the Bonham Road project was reduced by $100,000 on plaintiff's concession. Most claims for additional works outside fixed price contracts were upheld except one disallowed item. The court did not find personal liability of Mr Ip, the 2nd defendant, on the basis of oral warranties, emphasizing proper identification of the contracting entity as a limited company. On counterclaim, several claims for alleged negligence and administration costs were largely rejected except for a structural design issue at Bonham Road, allowing a reduced amount of $150,000. Interest was awarded at prime plus 1% from the date of writ. The plaintiff recovered a net judgment of approximately $2.2 million with costs awarded accordingly, while the 2nd defendant was awarded costs against the plaintiff.
Legal issues: Calculation of plaintiff's fee on Lockhart Road project · Liability of 1st Defendant for Classes A & C supervision fees · Agreement on reduction of contract sums for Bonham Road project · Entitlement to additional works fees despite fixed price contracts · Personal liability of Mr Ip (2nd Defendant)
Outcome: Judgment for plaintiff against 1st defendant for $2,364,313; judgment for 1st defendant against plaintiff on counterclaim for $150,000; net sum due to plaintiff $2,214,313; 1st defendant to pay costs to plaintiff; 2nd defendant to be awarded costs against plaintiff.
|
HCCT000055/2000 HCCT55/2000 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS ----------------------
----------------------- Coram: Hon Burrell J in Court Dates of Hearing: 13-15 June and 18 June 2001 Date of Judgment: 20 July 2001 --------------------- J U D G M E N T ---------------------- 1.For many years prior to 1998 Mr James Lau Chi Wang, a registered structural engineer, and Mr Thomas Ip Fook Chuen, an architect and director of the 1st defendant firm of architects, were both personal and professional friends. Their friendship came to an end as a result of the alleged unpaid fees due to the plaintiff company which are the subject matter of this action. 2.The plaintiff, between 1993 and 1998, was engaged by the defendants (subject to the issue of the 2nd defendant's personal liability with which I deal later in this judgment) on many construction sites around Hong Kong. This action concerns nine of them. The professional services which the plaintiff provided fall, broadly speaking, into two categories, design works and site supervision. The plaintiff's case is that he has submitted invoices totalling $2,816,736.31 for this type of service, which remain unpaid. The plaintiff's case against Mr Ip personally, is based primarily, on oral warranties allegedly given by Mr Ip that he would be personally liable to the plaintiff for his firm's indebtedness. Such oral warranties were given during social meetings when Mr Lau and Mr Ip played badminton at the Craigengower Cricket Club. 3.A number of different and self contained issues arise on the pleadings. Two of those issues take up over $2 million of the $2.8 million claim. Unfortunately, counsel (Mr Graham Chu, for the plaintiff and Mr Anthony Houghton, for the defendants) have not been able to agree a list of issues. However, I shall follow the defendants' list which seems to encompass all the differences between the parties on the claim. A. HOW WAS THE PLAINTIFF'S FEE FOR SERVICES RENDERED TO BE CALCULATED ON THE LOCKHART ROAD PROJECT? 4.The defence relies on the plaintiff's letter of 26 May 1992 which states :
5.The plaintiff's claim is for 0.8% of the final total construction cost (which was $201,185,370) namely $1,609,483. 6.The plaintiff contends that the letter of 26 May 1992 was an estimate, both parties knew the estimate was unrealistically low, the letter provides for an adjustment and the defendant wrote to the plaintiff on 8 March 1995 saying "... we will arrange a meeting with you to discuss about the fee adjustment very shortly." 7.As part of the defence case, it was suggested in evidence by Mr Ip that what was meant between the parties was that the 0.8% calculation was intended to be done on the "structural element" of the total construction cost. He said that the $76.5 million starting point was a reasonable reflection of the "structural element" in the total construction cost. I reject this argument. The letter does not say this. The idea was never advanced at the time nor during the many years that followed 1992. There was no reliable evidence to indicate that such a calculation method was used on other projects or in the trade generally. 8.Looking at the contract objectively as a whole and against the factual background, I construe the letter of 26 May 1992 to mean that the fee would be 0.8% of the total construction cost but that that fee would be subject to an adjustment. Both Mr Lau and Mr Ip gave evidence to the effect that $76.5 million was unrealistically low for the total construction costs and $201 million was unexpectedly high. Both gave evidence to the effect that, normally, there would be negotiations, hence the defence letter in 1995 stating "we will discuss the fee adjustment". In these circumstances I consider it proper and appropriate to approach the issue of quantum on this issue on a quantum meruit basis. 9.Mr Ip was asked what his first offer in negotiation would have been. He said $800,000. On a quantum meruit exercise such as this it is sensible to use round and approximate figures. A corresponding opening bargaining position of Mr Lau's would, logically have been lower than $1.6 million by a similar amount, $1.4 million. The median figure is $1.1 million. 10.The pleaded claim under this head is $997,483 which takes into account part payments already made. The court's quantum meruit assessment has resulted in a reduction of this claim by $500,000. The sum awarded to the plaintiff will be $497,483. B. WHETHER THE 1ST DEFENDANT IS LIABLE IN RESPECT OF CLASSES A & C SUPERVISION FEES 11.There is no dispute that supervision was required by the Building Authority under the Buildings Ordinance. The different classes of supervision (A & C in these contracts) provided for different levels of expertise and qualifications. There is no dispute either (subject to one issue which I deal with in the counterclaim) that the plaintiff provided these services. There is no dispute either that on most of the contracts the plaintiff has been paid for these services. The major outstanding payment relates to the services rendered at one location, namely Tai Pak Terrace. The claim under this heading is $1,117,037. 12.The 1st defendant resists the claim on three bases. Two of these defences appear in the pleadings as a result of an amendment to the defence made two days before the trial. Firstly, it is contended by way of defence that the contracts contained an implied term that the 1st defendant's liability to pay the plaintiff for Classes A & C supervision fees only arose when the 1st defendant had been paid by the developer for these services. In other words, an implied "pay when paid" term. Secondly, it is submitted that the contract whereby the supervision was provided is tainted with illegality and therefore unenforceable. The third defence is that the 1st defendant was only acting as an agent for the developers. I will deal with the agency argument first.
13.In this case there is plainly a contract between the plaintiff and the 1st defendant. In some instances, the plaintiff's letter offering his services and setting out his scope of works has been signed by the 1st defendant. Where it has not been signed there is acceptance by conduct. The services were provided and payment is sought on the basis of the quotes referred to in the plaintiff's letters. They are unremarkable standard quotations which not surprisingly prompted no, or little, negotiations or debate at the time. It is worthy of note that these invoices were submitted between 1993 and 1995, requests for payment followed up to May 1998 when a final demand letter was sent. The grounds for refusal to pay commenced in June 1998. 14.Mr Chu, for the plaintiff, helpfully referred the court to passages from Sika Contracts Ltd v. Gill &Others 9 BLR at p.17 which, I agree, disposes of the point being made in this case. Per Kerr J :
15.The fact that Mr Lau knew or must have known that there were developers behind Mr Ip who were the ultimate paymasters and that there was no profit element in the payments of Classes A & C supervision to Mr Ip is a red herring. The application of the above principle to the facts of this case make the 1st defendant liable (subject to the next two defences, to which I now turn).
16.The re-amended defence pleads :
17.The factual basis behind this issue is the 1st defendant's evidence that in all projects where he has paid for A & C supervision, he had been paid by the developer first. The very large outstanding payment in respect of Tai Pak Terrace remains outstanding because he has not been paid by the developers. 18.In my judgment this defence must fail. In those projects where payments have been met there is no evidence in the correspondence or other documentation to suggest either directly or obliquely that the timing of the payment to the plaintiff is due to the fact that the 1st defendant has been paid by the developer. Again, the argument only surfaces for the first time many years after the presentation of the invoice. 19.A term may be implied into a contract if the following tests are satisfied :
20.The implied term contended for does not meet these tests. The plaintiff's terms in its original letters provided expressly for payment "within 14 days" of presentation of the invoice. The implied term contradicts this. Further it is not required to give business efficacy to the contract. Neither can it be said to be obvious, when it only emerged as an argument so late in the day in the long chronology of these proceedings. 21.The developer of Tai Pak Terrace was Lucky Wealth. Thus it is the 1st defendant's case that he was waiting to be paid by Lucky Wealth before paying the plaintiff. The fact is that Mr Ip himself, was the owner, or substantial owner of Lucky Wealth. He was therefore waiting to be paid by himself. In August 1997, 999 out of 1,000 shares in Lucky Wealth were held by a company called Oxometric. A company search of November 1997 shows Mr Ip and his wife to be the only shareholders of Oxometric. It is true that an earlier search shows Oxometric to be holding only 30% of the shares in Lucky Wealth. This merely dilutes (but only slightly) the point being made by the plaintiff, namely, that the 1st defendant's plea of "I have not been paid" is disingenuous.
22.The third ground for disputing liability, namely illegality, is, at best, ingenious and technical, at worst, an afterthought. Whichever it is, I find it to be unmerited. 23.The claim of illegality relates only to the Class C supervision. In relation to Class C the following condition applied :
24.The objection being taken by the 1st defendant is that in respect of the Tai Pak Terrace Project (and also at Bonham Road) the contractor was a company called Fong On Construction & Engineering Co. Ltd. This was a family business run by James Lau and his brothers. Employees of the plaintiff acted in a Class C supervisory capacity on these projects. 25.A number of points can be made in the plaintiff's favour on the issue :
26.Mr Chu cites in support of this plea passages from Mohamed v. Alaga & Co. (a firm) [1999] 3 All ER at page 707 onwards, a case which is distinguishable on its facts, but nonetheless of assistance on the application of principle, in particular where Lord Bingham CJ says :
27.So also in our case, it was the 1st defendant who, as authorized person, employed the supervisors and the plaintiff, in truth is suing for services reasonably, properly and professionally provided. 28.For all these reasons, the 1st defendant is liable for all invoices presented for Classes A & C supervision. C. WAS THERE AN AGREEMENT THAT THE CONTRACT SUMS FOR THE BONHAM ROAD PROJECT WERE REDUCED FROM $660,000 TO $560,000? 29.When giving evidence Mr Lau conceded that his partner must have made this agreement at the material time. By consent therefore, the plaintiff's claim is reduced by $100,000. This concession also provided an example of Mr Lau's frankness and candidness. I found him to be an impressive witness. He did not treat every question in cross-examination as a hidden trap. He answered questions, in my judgment, honestly and fairly. He had a good memory for and a good grasp of facts and events which, in some cases, went back many years. Although, Mr Ip, was also a respected and professional man, in most instances where there was a conflict of evidence or a difference in recollection, I preferred and relied on the evidence of Mr Lau. D. WHETHER THE PLAINTIFF IS ENTITLED TO SUMS CLAIMED AS "ADDITIONAL WORKS" 30.In respect of a number of smaller items which the plaintiff invoiced as additional items, in some cases years after the original lump sum offer letter, the 1st defendant submits there is no liability to pay because they were "fixed price" contracts. This contention does not accord with the reality of the situation. It is necessary here, to deal with each item, albeit briefly. As a matter of principle a fixed price contract which sets out the scope of the works, does not preclude liability for future additional works which fall outside the original scope and which are carried out much later than the original works.
E. WHETHER MR IP, AS 2nd DEFENDANT IS PERSONALLY LIABLE 31.At C. above I said that, in most instances, I relied on Mr Lau's evidence. On the question of Mr Ip's alleged personal liability I find that Mr Lau's evidence, bearing in mind the onus of proof is on him, falls short of the standard required for this court to hold Mr Ip personally liable for all those items for which the 1st defendant has been held liable. His evidence was genuinely given but balancing against Mr Ip's account, I am not persuaded that Mr Ip made binding oral warranties in the changing rooms at Craigengower Cricket Club after an earlier morning friendly game of badminton. 32.There are two limbs to the claim against the 2nd defendant. Firstly, that there was a personal undertaking accepting a personal liability to pay and secondly, that the plaintiff always wrote letters to "Tom Ip & Partners, Architects" and that Mr Ip never pointed out to him that in fact he was dealing with a limited company.
33.I do not find Mr Ip to be personally liable. The claim against the 2nd defendant must fail. Counterclaim 34.In the re-amended defence and counterclaim damages of $917,500 plus damages for negligence were claimed. At trial this was reduced to a claim for $586,000. This is made up as follows :
Interest 35.In this case, I consider the appropriate rate of interest should be prime plus 1% from the date of the writ. Summary 36.On the claim there will be judgment for the plaintiff against the 1st defendant in the sum made up as follows :
37.On the counterclaim there will be judgment for the 1st defendant against the plaintiff for $150,000. 38.The net sum due to the plaintiff is $2,214,313. 39.In view of the small amount of the judgment on the counterclaim, I make a costs order nisi in the plaintiff favour against the 1st defendant. He has been substantially successful on both the claim and the counterclaim. The 2nd defendant is awarded his costs against the plaintiff.
Representation: Mr George Chu, instructed by Messrs P.H. Chin & Co., for the Plaintiff Mr Anthony Houghton, instructed by Messrs Fung, Wong, Ng & Lam, for the Defendants |