Bordon Construction Co., Ltd. v. Chi Lik Window Works Co. Ltd.
Read the full judgment text of HCCT15/2001 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 9 July 2002 before Hon Burrell J.
Construction contract — Sub-contract termination — Failure to obtain architect approval of shop drawings — Breach going to root of contract — Reasonableness of termination — Multiple rejected submissions and failure to comply with architectural requirements — Defendant’s defences rejected — Quantum of damages for cost overrun, wasted expenditure, and indemnity for liquidated damages — Interest awarded on nisi basis. The plaintiff, main contractor for a Peak development, terminated the defendant’s sub-contract for window and door installation due to failure to obtain required shop drawing approvals and non-compliance with architect instructions. The defendant persistently submitted unacceptable designs contravening contract specifications, including failure to provide aluminum folding and sliding doors and use of split mullions in place of one-piece. The court held the termination lawful and reasonable given notices and non-response. Defences of no adverse comment, change of design intent, readiness to perform, and conditional agreement were rejected for lack of evidence, improper pleading, or misinterpretation. Damages awarded included $500,000 excess cost for new subcontractor completion, $47,708 for wasted tendering costs, indemnity for employer’s liquidated damages claim, and interest on a nisi basis. Costs awarded to plaintiff.
Legal issues: Plaintiff's right to terminate the sub-contract · Reasonableness of termination · Validity of defendant’s defences · Quantum of damages
Outcome: The plaintiff’s entitlement to terminate was upheld; the defendant ordered to pay damages and costs.
|
HCCT000015/2001 HCCT15/2001 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS --------------------------
-------------------------- Coram: Hon Burrell J in Court Dates of Hearing: 17 - 21 June 2002 Date of Judgment: 9 July 2002 --------------------------- J U D G M E N T --------------------------- 1.The plaintiff was the main contractor for a residential development on the Peak. The defendant was the sub-contractor to the plaintiff for the installation of windows, doors, louvres, sky light and canopy works. The sub-contract was dated 23 September 2000. Approximately three months later, on 21 December 2000 it was terminated by the plaintiff. The case turns on whether the plaintiff was entitled to terminate at the time it did so, in the manner it did so and for the reasons given. 2.The plaintiff called four witnesses, Mr Victor Kwan (a project manager of Jadespring, the employer), Mr Leung Sing (a director of the plaintiff), Mr Otto Chong (an assistant co-ordinating officer of the plaintiff) and Mr Vincent Chow (the plaintiff's construction manager). Much of the plaintiff's case depended on contemporaneous documents, correspondence and technical drawings. The witnesses, in addition, gave important evidence on key issues of disputed fact. Unless otherwise specifically stated in this judgment, I found their evidence to be accurate and reliable. 3.The defence called one witness, Mr Lee Chun Kong, a director of the defendant company. His manager at the time, Mr Edwin Kam, had been more involved with the project on a day-to-day basis, but had since left the defendant's employ and did not give evidence either by affirmation or in court. Mr Lee was not impressive as a witness. Having given all the evidence a careful evaluation, where there were factual disputes I preferred and adopted the plaintiff's version of events. THE PLAINTIFF'S RIGHT TO TERMINATE 4.The contractual right was contained in clause 8.3(a) and supplementary condition clause 11 :
And
5.The defendant's specific obligations in respect of the preparation of shop drawings and samples were contained also in the supplementary conditions :
6.In my judgment, the evidence clearly shows that the defendant was in actual breach of these clauses. From September 2000 to 4 December 2000, the defendant made six submissions for approval by the architect and/or the developer, none of which were approved. The state of affairs between the parties between the final submission on 4 December and termination on 21 December can be summarized as follows :
7.The two major problems were those referred to at (ii)(a) and (b) above. Firstly, the contract always required certain folding and sliding doors made of aluminum. The simple truth is that Mr Lee, for the defendant, discovered that he could not manufacture such doors in Hong Kong within time and within cost, until it was too late. His efforts to substitute "steel" for aluminum and "sliding only" instead of "sliding and folding" was unsuccessful both with the plaintiff in December 2000 and with the court during trial. Secondly, the contract required the mullions and transoms in the windows to be a single piece of metal. Mr Lee persisted, in his submissions, with drawings and samples which were made of a number of pieces fitting together. They were never accepted or approved. THE IMPORTANCE OF THE BREACHES IN THE CONTEXT OF THE WHOLE SUB-CONTRACT 8.In a nutshell, the defendant's breach was its failure to respond to the architect's comments and rejections and the resulting failure to obtain the architect's approval. It is a breach which went to the root of the sub-contract for the following reasons :
9.The nature of the defendant's actual breach clearly therefore goes to the root of the contract and is of the particular type described by Lord Wilberforce in Federal Commerce v. Moleng Alpha [1979] AC at p.778 :
Mr Lee's persistent attempts to carry out the works in the way he wanted to is a classic example of Lord Wilberforce's remark. THE REASONABLENESS OF THE TERMINATION 10.In determining whether the plaintiff was entitled to terminate the test to be applied is that of the reasonable contractor in the particular contract in issue.
(Chitty on Contract, 28th Edition) In our case, the plaintiff made time of the essence by the giving of two notices on 6 and 9 December. 11.On 6 December, after the 6th submission had been rejected, the plaintiff requested the defendant to resubmit by 13 December. On 9 December the plaintiff instructed the defendant to comply with the architect's requirement within seven days, failing which the plaintiff would consider terminating the contract. Prior to termination on 21 December, the defendant made no response to either letter. 12.In all the circumstances, the only conclusion that this court can come to is that the termination was reasonable. The evidence from the concerned parties, in the critical period during December 2000, was :
THE REASONS FOR REJECTING THE DEFENDANT'S DEFENCES 13.Mr James Lee, for the plaintiff, complained, in the course of his final submission, that the defendant had "moved the goalposts" by introducing new defences as time went on. The final defence emerged in the course of Mr Keith Mok's final submission for the defence. Whilst there is some merit in Mr Lee's complaint, a better analogy would be that the goalposts were widened rather than moved. It was, however, only the "final" defence (see (d) below) which took Mr Lee by surprise. In all, four defences were advanced. I permitted all to be argued. In my judgment, none were made out. I will deal with each of them briefly in the order that they emerged. (a) "No adverse comment" defence 14.In a letter to the defendant dated 8 November 2002, the plaintiff stated :
15.The defendant also relies on a fax from the structural engineer dated 17 October 2000 which contained the remark that "we generally have no adverse comments". Only the letter from the architect is pleaded in the defence. However, neither are of any real substance when further analysed. 16.The letter of 8 November 2000 from the plaintiff, referred to above, goes on to say :
17.On the next day, the architect confirmed with the plaintiff that it had not made the alleged remark in connection with the defendant's submission for the aluminium windows and doors. Consequently, the plaintiff immediately informed Mr E. Kam of the defendant, both by phone and letter, not to proceed with production pending further instructions. 18.The unpleaded comment from the structural engineer was contained in a fax headed "Canopy and skylight". The work done in respect of the canopy and skylight is not an issue in this case. (b) "Change of design intent" defence 19.The defendant contends that the requirement for "one piece" mullions and aluminium folding and sliding doors arose after the commencement of the contract. The defendant contends that the original intent was for split mullions and steel doors. These defences are not pleaded. In spite of the lack of pleading, they are, once again, not made out on the evidence.
20.I find there to be no documentary support for the contention that the original intent was for split mullions. The submissions of drawings of split mullions were consistently rejected from the outset. The plaintiff's witness from whom the alleged oral instruction for split mullions came, Mr Otto Chong, specifically denied it in cross-examination. There is no evidence of a split mullion ever being approved.
21.The defendant relies on a drawing dated September 1999 which was headed "for information" which refers to "steel" doors. It is plain that this was an outdated document which, in any event, did not form part of the contract. All the contract drawings were for aluminium doors of a sliding and folding design. The defendant had quoted a price based on aluminium not steel. None of the many submissions of drawings contained steel doors. Quite simply, the defendant realised too late that finding a Hong Kong manufacturer for aluminium doors was going to be a problem. The problem had been discussed at a meeting on 11 November 2000. The defendant always knew that he was contractually obliged to provide aluminium. Even after the notice of termination had been served on him, his letter of 28 December 2000 to the plaintiff shows his state of knowledge :
(c) "Ready willing and able" defence 22.It was the defendant's case that, throughout, he was ready willing and able to carry out the sub-contract works. This defence primarily falls down on the contention that the defendant was "able" to perform the contract. There is plentiful evidence pointing the other way, namely to his inability. Shop drawings for folding and sliding doors were never produced. The drawings that were produced and submitted were never approved by either the architect or the employer. A request for yet another submission of drawings after the 6th submission (on 4 December 2000) met with no response. (d) "Conditional agreement" defence 23.Mr Mok argued, in his closing submissions, that even if the plaintiff was entitled to terminate the contract on 21 December 2000 for failure to respond to the architect's comments and failure to obtain the architect's approval, the plaintiff would not be entitled to any damages because a consequence of the termination was that both parties were discharged from any further liability. In support, he relied on paragraph 4 of Annexure 1 to the contract, which states :
24.Mr Mok submits that the effect of this provision was to make the sub-contract a conditional agreement, the condition being the obtaining of approval by the architect or employer. He submits that no approval (reasonably sought) equals no contract. He further relies on the provision that Annexure 1 takes precedence over other terms as follows :
25.I reject this defence on two separate grounds. Firstly, it was not pleaded. The Hong Kong White Book states (18/8/5) :
26.In this case, the defence was raised for the first time during Mr Mok's closing submission. The plaintiff had been deprived of any opportunity of dealing with the point through his witnesses. 27.Secondly, a proper construction of paragraph 4 does not afford the defendant the defence he seeks to rely on. The following points militate against the defendant's interpretation and effect of paragraph 4 :
QUANTUM 28.Under the heading of quantum, four issues arise : (1) Cost of completing the works 29.The defendant was replaced with a new sub-contractor called "Lucking". They completed the sub-contract for $8,063,250.00. This sum exceeds the original contract price by $553,472.00 (or approximately 8%). Bearing in mind that they only came in, in January 2001 and did the work expeditiously, and bearing in mind also that no evidence was adduced concerning the reasonableness or otherwise of the new sub-contractors' costs, I think it should be allowed but with a small discount. The evidence was that Lucking probably started with the advantage of some approved drawings for the canopy and skylight. However, the evidence was not clear about the exact value of this benefit, save that it would not be more than $75,000. I consider a reasonable discount therefore to be one which reduces the amount under this heading to $500,000. (2) Wasted expenditure 30.$47,708.48 was claimed for the cost of preparing for a new tender. The sum was not challenged and will be allowed. (3) Indemnity against further liquidated damages claim 31.There is no doubt that (a) the defendant's breach will have caused a delay in progress, and (b) the employer will make a claim against the plaintiff for the liquidated damages provided for in the contract between them. Such a head of damage is "fair and reasonable and arises naturally, according to the usual course of things from the breach of contract". (Hedley v. Baxendale) 32.I am satisfied that Mr Lee Chun Kong, for the defendant, would have been aware that such a clause exists in the main contract and that any delay in progress would make the plaintiff vulnerable to a claim being levied against them. Mr Lee has had over 20 years in the industry and although he was reluctant to admit that he realised the main contract contained a liquidated damages clause, it is safe to impute such knowledge or awareness to him. (4) Interest 33.The pleadings contain a claim for interest but the issue was not canvassed. I hope the parties can agree a rate and a period. In order to assist I will make a nisi order (infra) . JUDGMENT
Representation: Mr James Lee, instructed by Messrs Deacons, for the Plaintiff Mr Keith Mok, instructed by Messrs C.P. Tsang & Co., for the Defendant |