Billion Profit Enterprises Ltd. v. Rise Path Investments Ltd. and Another
Read the full judgment text of HCA 711/1999 on BabelCite. This High Court CFI judgment was delivered on 4 August 1999.
1. The Plaintiff vendor brings this action against the 1st Defendant purchaser ("D1") claiming that it breached the agreements reached between them in failing to complete the sale and purchase of certain real properties ("the suit property"). Apart from the sale and purchase agreement ("the Agreement"), a Supplemental Agreement was entered into between the Plaintiff and D1 (collectively "the Agreements"). The 2nd Defendant ("D2") was sued by the Plaintiff on a guarantee dated 25 August, 1997
|
HCA000711/1999 1999. No. A711 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE HIGH COURT ACTION NO. 711 OF 1999 __________
__________ Coram: Hon. Mr. Justice Chung in Chambers Date(s) of Hearing: 4 August 1999 Date of Judgment: 4 August 1999 Date of Handing Down Reasons for Judgment: 12 August 1999 _________________________________ REASONS FOR JUDGMENT _________________________________ Introduction 1. The Plaintiff vendor brings this action against the 1st Defendant purchaser ("D1") claiming that it breached the agreements reached between them in failing to complete the sale and purchase of certain real properties ("the suit property"). Apart from the sale and purchase agreement ("the Agreement"), a Supplemental Agreement was entered into between the Plaintiff and D1 (collectively "the Agreements"). The 2nd Defendant ("D2") was sued by the Plaintiff on a guarantee dated 25 August, 1997 2. The Agreement entered into by the Plaintiff vendor and the D1 purchaser was dated 25 March, 1997. The suit property was sold for a total sum of $72.75 million. Completion was to be on 25 August, 1997. The parties entered into a Supplemental Agreement dated 25 August, 1997 postponing completion to 25 October, 1997. Under the Supplemental Agreement, D1 had to pay to the Plaintiff $7.275 million as part payment of the price on 25 August, 1997. Further, if D1 could not complete on 25 October, 1997, it had to additionally pay $2 million each month commencing on 26 October, 1997. The Plaintiff had the right to serve a notice of completion on D1 asking it to complete the sale. D2 was required to execute a guarantee to guarantee D1's performance of the Agreements and this was done on 25 August. 1997. 3. By the time of the hearing on 4 August, 1999, D1 has paid a total sum of $16.55 million consisting of:-
4. At the end of hearing on 4 August, 1999, I concluded that there was no triable defence to the Plaintiff's claim (save as to quantum of loss) The declaratory relief claimed was granted and interlocutory judgement with damages to be assessed was entered. The following are the reasons for the decision. The Application for Summary Judgment 5. In short, the Defendants contended that the following issues are triable:-
(1) Relevant Terms of the Agreements 6. The suit property to be sold under the Agreement consisted of:-
In order to understand and decide on points (a) to (d) under the preceding heading, it was firstly necessary to consider some of the terms of the Agreement. 7. Clause 5 stipulated that:-
8. Clause 7 provided that:-
9. Clause 8 stated that:-
10. Clause 9 can be divided into several parts. The first part stipulated that:-
The next (second) part of Clause 9 stated that:-
The third part of Clause 9 provided that:-
The fourth part of Clause 9 stated that:-
11. Clause 10 can also be divided into different parts. The first part provided that:-
The second part of Clause 10 stipulated that:-
The third part of Clause 10 stated that:-
12. Clause 25 (which was relied upon by Mr. Kok for the Defendants) provided that:-
(2) Requisitions on Title 13. D1's solicitors raised the following point in a letter dated 21 June, 1997:-
This was repeated again in their letter of 21 November, 1997:-
14. Without going into the details, the Plaintiff's solicitors responded to the above by relying on Clauses 8 to 10 of the Agreement. 15. Mr. Kok submitted at the hearing that Clauses 8 to 10 could not put the matter beyond argument because:-
16. In the letter dated 21 November, 1997, D1's solicitors also raised a requisition regarding a staircase and an opening in the floor slab. The title deeds were delivered to D1's solicitors on 11 June, 1997. The Plaintiff's solicitors responded on 25 November, 1997 by relying on Clauses 8 to 10 of the Agreement as well as stating that this was only raised 4 months after their last reply and two days before completion. I considered this "requisition" invalid because:-
A point was made in a similar way about an alleged difference between the physical layout of the Shop and that shown in the documents. For the same reasons set out above, I would also find this point invalidly made. The "Disclosure" Point 17. Mr. Kok argued that the need for the Plaintiff to make full disclosure of the unauthorized structure and/or unpermitted user arises from a rule in equity upon which the decisions of Rignall Developments Ltd. v. Halil [1987] 2 All E.R. 170 and Becker v. Partridge [1966] 2 Q.B. 155 were based. 18. In Rignall, the defendant's property was put up for auction and the agreement entered into contained a condition that the purchaser "shall be deemed to have made Local Searches and Enquiries and to have knowledge of all matters that would be disclosed thereby and shall purchase subject to such matters." The defendant in fact knew of a charge. When the plaintiff discovered the charge it refused to complete. The plaintiff commenced an action seeking a declaration that the defendant was not entitled to serve a notice to complete because good title had not been shown. In deciding in the plaintiff's favour, Millet J. said:-
19. In Becker, the contract contained the Law Society's Conditions of Sale which provided that "the vendor's title which has been accepted by the purchaser shall commence with an underlease ... and the purchaser shall raise no requisition or objection thereon". Unknown to the vendor, there were covenants not to make alterations or underlet without the landlord's written consent. Shortly after the purchaser went into possession, her solicitors were informed by the head lessee's solicitors of breaches of covenant in the superior underlease, namely, failure to pay rent, underletting without consent, and unauthorized alterations. In an action commenced by the purchaser for rescission of the contract, the vendor relied on the said clause of the contract and counterclaimed for specific performance. The Court of Appeal decided in the purchaser's favour holding that unless the vendor had disclosed to the purchaser defects of which he knew or ought to have known, the said clause was not a bar for rescission. 20. The vendor's duty to disclose was further discussed in Barnsley's Conveyancing Law and Practice (1996) 4th ed., pp. 153-4 where it was said:-
21. Comments on the above aspects can also be found in 42 Halsbury's Laws of England (1999) 4th ed. Reissue, 41-61 (especially at para. 55-57), and Emmet on Title 19th ed., para. 1.016, 1.032, 4.026 and 4.027. 22. In Summit Investment Ltd. v. Shia Ning Enterprise Ltd., H.C.M.P. No. 1532 of 1998, I have decided that a mere discrepancy between the user described in the occupation permit and the actual user is not per se a defect in title: see pp. 5-9 of the transcript of the Summit Investment case. Unauthorized building works (which are not exempted) must have been carried out in order that s. 25(4) (and therefore s. 25(1)) of the Buildings Ordinance, Cap. 123 can be invoked to enable the Building Authority to act under s. 25(2) (and possibly also under s. 24). 23. The Defendants have not alleged (or proved) that unauthorized building works had been undertaken in relation to the karaoke business. On the other hand, the Plaintiff's solicitors did not argue that the "requisition" was not properly raised. In his written submissions, Mr. Li for the Plaintiff argued that it was nevertheless open to the Plaintiff to raise this point at the hearing. I do not agree. The requisition raised in relation to the karaoke lounge business was not so blatantly irrelevant and therefore a proper answer should be provided at least by a reasonable time before completion. 24. However, I rejected Mr. Kok's non-disclosure argument on other grounds. First, the karaoke business was not a latent defect. On the contrary, it was or ought reasonably to have been obvious to anyone who inspected (or surveyed) the suit property; the fact that D1 was able to raise this requisition speaks for itself. Mr. Kok argued that although the nature of the business was obvious, the restrictions in the occupation permit were not known to D1. I did not find this to be a valid argument, especially when D1's attention had been drawn to this potential problem by Clauses 8 to 10 of the Agreement. 25. Even if the karaoke business could be viewed as a latent defect, I did not agree with Mr. Kok that the Plaintiff had not made the requisite disclosure. First, although the relevant clauses of the Agreement were not explicit, they were clear enough for a reasonable purchaser to have been put on notice regarding (a) the user of, and/or (b) any unauthorized structure(s) in, the suit property. Not only did these clauses state that the vendor did not make any representation or give any warranty regarding these matters, the second part of Clause 10 actually stipulated the purchaser "should rely upon his own inspection and survey". As quoted earlier, it was stated in Barnsley that "Express reference to an adverse right, though clearly preferable, is not vital". The same conclusion could be reached by saying that it would be inequitable for such a purchaser to be able to allege non-disclosure when he ought reasonably to have been put on alert, and exercised due diligence, regarding this by reason of the insertion of the relevant clauses. 26. If the law were that each and every burden (in particular, illegal structure) needs to be precisely pinpointed, dispute can arise as to how far a vendor needs to disclose:-
27. Further, in Hong Kong, it is a usual practice that a preliminary sale and purchase agreement was entered into between the parties to be followed by a formal sale and purchase agreement. Although there was no direct evidence that such practice was adopted in the present action, I noticed that an initial deposit of $2 million had been paid prior to the Agreement, which is consistent with the usual practice of an earlier provisional agreement. 28. When doctrines of equity were called upon, it must be borne in mind that a purchaser (who, for example, had been alerted to possible "breach" of user and/or unauthorized structures by terms in the draft formal agreement) could and should inspect or survey the suit property prior to entering into a formal sale and purchase agreement which contains clauses specifically extinguishing or limiting a vendor's duty relating to user and/or unauthorized structures. If he enters into the formal agreement without doing so, he should not be heard to complain that there had been "non-disclosure". The "Drafting" Point 29. I also did not agree with Mr. Kok's argument that the relevant clauses were not clear or wide enough to alleviate the Plaintiff from its duty to prove good title regarding "breach" of user and/or unauthorized structures. 30. Mr. Kok relied on the difference in the wordings between Clauses 8 to 10 on the one hand and Clause 25 on the other. He submitted that Clause 25 explicitly provided there was no need for the Plaintiff to prove title relating to certain part of the suit property, but Clauses 8 to 10 did not expressly say so. That is factually correct. However, differences in the wordings of different clauses, or whether something is or is not explicitly stated, are only matters to be taken into account when ascertaining their true meaning. Bearing in mind Mr. Kok's argument, I considered that the wordings of Clauses 8 to 10 were clear enough to show that in effect, the Plaintiff's duty to prove good title had been obviated in relation to "breach" of user and/or unauthorized structures. In this connection, I find that the phrase "The Purchaser shall not be entitled to rescind this Agreement or to annul the sale" in the fourth part of Clause 9 and the phrases "the Purchaser shall not be entitled to rescind this Agreement" in the second and third parts of Clause 10 to be material. 31. Mr. Kok's second argument was that Clauses 8 to 10 did not explicitly state that the Plaintiff did not need to prove good title. However, the answer to this question was whether upon a true construction, these clauses could be found to have such effect. Because of the matters stated in the preceding paragraph, I concluded that they had such effect. (3) Admission of Repudiation/Agreement to Discharge the Defendants 32. It was alleged in the Defence and Counterclaim as well as in an affirmation filed by Mr. Kok (but not the witness himself) that in early November, 1997, the Plaintiff's chairman, Mr. Fung, orally admitted the Plaintiff's liability to repay the sums received from D1. At the hearing, Mr. Kok said that it was a Mr. Au Chi Kuen of D1 who actually heard it from Mr. Fung. 33. I did not find this part of the Defendants' case to be believable because:-
(4) Abandonment of the Agreements 34. This argument was based on the following:-
35. Mr. Kok argued that it was open for the Court to infer that the Agreements had been abandoned after 27 November, 1997. I disagreed because, having rejected the alleged "admission" of the Plaintiff, there was no evidential basis for doing so. (5) Quantum 36. In the Statement of Claim (and this application), the Plaintiff claimed a quantified sum of $57.15 million which consisted of:-
37. I did not agree that final judgment in the sum claimed should be entered. The proper order should be for an interlocutory judgment with damages to be assessed because (without prejudice to any other issues to be determined at the time of assessment):-
The Application for Security for Costs 38. In view that the Plaintiff has succeeded on liability in this action, there was no ground for ordering security for costs to be provided by the Plaintiff and this application was therefore dismissed. Costs 39. There was no reason to depart from the normal rule that costs should follow the event. The costs of the action (including the costs of the applications) are to be paid to the Plaintiff to be taxed if not agreed.
Representation: Appearances: Mr. C.Y. Li i/s by Messrs. Or, Ng & Chan for the Plaintiff Mr. Christopher L.S. Kok of Messrs. Kok & Ha for the Defendants |