Might Foundate Development Ltd. v. Ccecc (H.K.) Ltd.
Read the full judgment text of HCCT23, 24, 25 & 26/2001 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 6 August 2001 before Hon Burrell J in Chambers.
Arbitration Law — Construction contract dispute — Validity and interpretation of Practical Completion certificate and conditions precedent — Extension of time claims and notice requirements under clauses 23, SP 5.03, SP 8.02 — Time set at large due to employer's non-payment — Quantum claims on loss and expense, overheads, fluctuations, interest and general damages — Section 23 leave to appeal and sections 24 and 25 arbitration ordinance applications for remission and removal of arbitrator — Presumption of finality of arbitrator's award — High threshold for court intervention held applicable; issues mostly one-off with no general legal principle requiring clarification. The arbitrator held the Practical Completion certificate valid despite minor defects and unpleaded legal challenge. The arbitrator found inconsistency between SP 5.03 and SP 8.02 and rejected strict notice requirements for extension of time. The arbitrator's factual determinations on expert evidence and calculation methods were upheld, reflecting the technical nature of the dispute. Time at large due to respondent's admitted breaches was accepted lawfully. Loss and expense and other quantum findings were based on reasonable fact assessments without obvious error. The court held the section 25 removal application was meritless, reflecting mere dissatisfaction with adverse findings, not arbitrator incompetency. All applications rejected with costs ordered to the respondent.
Legal issues: Practical Completion Certificate Validity · Extension of Time Notice Requirements · Extension of Time Calculation Method · Time at Large Due to Non-Payment · Loss and Expense Claims under Clause 24 · Site Overheads Double Recovery · Fluctuations Award · Interest Rate Award · General Damages Burden of Proof · Removal of Arbitrator under section 25
Outcome: Applications under sections 23, 24 and 25 are refused; costs to follow the event with an order in favour of the respondent.
|
HCCT000024/2001 HCCT23, 24, 25 & 26/2001 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS --------------------------
--------------------------
--------------------------
Coram: Hon Burrell J in Chambers Dates of Hearing: 23 to 25 July 2001 Date of Decision: 6 August 2001 -------------------- D E C I S I O N --------------------- 1.In this hearing the applicant, Might Foundate Development Limited ("the Respondent in arbitration") seeks orders under sections 23, 24 and 25 of the Arbitration Ordinance. They seek leave to appeal an arbitrator's award pursuant to section 23, an order to remit various issues to the arbitrator for reconsideration under section 24 and the removal of the arbitrator under section 25. The arbitration took place in July 2000 before Mr Colin Wall. It lasted 12 days. The award save as to costs was published on 23 February 2001. It contains 287 paragraphs over 93 pages. 2.Miss Teresa Cheng SC appeared for the respondent in the arbitration and the applicant in these applications. Mr James Lee appeared for the Claimant in the arbitration, CCECC (H.K.) Limited, and was led by Mr Nigel Aiken SC in these applications. The Notices of Originating Motion and grounds of appeal cover 23 pages. In effect, there is very little that the applicant does not complain about or seek leave to appeal against in the award. Mr Aiken described it as "a shotgun gun" approach. 3.Before turning to each of the issues in these applications, I will briefly set out the important legal principles and tests to be applied in applications such as this. 4.It must not be forgotten that parties choose to arbitrate and parties choose their arbitrators. It is their chosen method of resolving their disputes. The threshold that an applicant must reach in order to get leave to appeal an award or an order to remit for reconsideration is set high because of the important presumption of finality of an arbitrator's award. The court's role is supervisory and the circumstances in which it will rebut the presumption of finality are carefully defined and are narrow. 5.The leading Hong Kong authority is the PT Dover Chemical Company Case [1990] 1 HKC 132. It sets out the court's first task, namely to determine where a particular ground of appeal lies on the "sliding scale" :
6.This assessment must be made in relation to each issue before the court. In the applications before me, I have come to the conclusion that all the issues are "one-off" issues about which the court should only intervene where it can be demonstrated quickly and easily that the arbitrator was plainly wrong. There is, however, one factor which prevents these issues from being placed at the "top of the scale" and that is that the arbitrator was not a lawyer. For this reason, the issues slide slightly down the scale. I take this into account. However, I also take into account that Mr Colin Wall is a chartered arbitrator who has considerable experience of Hong Kong, of building arbitrations and of the construction industry. He is a former chairman of the Chartered Institute of Arbitrators (H.K. branch) and an ex-officio of the H.K. International Arbitration Centre. 7.The presumption of finality, albeit rebuttable, was emphasized by Leonard J in Garden Co. Ltd v. On Lee General Contractors Ltd [1995] 2 HKC 89. In that case, Leonard J complained about the length of the hearing (which was approximately half the length of this hearing), the number of arch-lever files and the length of the Notice of Motion (again, they were about double in this case). He concluded with these words :
8.Another general principle to be kept in mind when determining whether to grant leave or to remit a point or points back to the arbitrator concerns what standards an arbitrator should meet when giving a reasoned award. In Robert Merkin on Arbitration Law, the following passage appears :
9.Clearly, a learned legal treatise is neither required nor expected. When two parties cannot agree someone else has to make a decision for them. One party will probably not like the decision but entrusting that decision to a chosen third party is the only way to bring the dispute to a conclusion. Of course, a simple 'Yes' or 'No' is not enough, professional standards must be met. However, in our case, I am far from persuaded that this arbitrator has failed to achieve those standards. 10.On issues concerning the application of general principles, there is a final matter upon which counsel do not agree, to which I now turn. It concerns whether different tests should be applied when deciding whether to 'remit' under section 23(2)(b) and under section 24. 11.Section 23(2)(b) provides that :
12.Section 24 provides that :
13.Miss Cheng submits that the tests under sections 23(2)(b) and 24 are different. Mr Aiken submits they are the same. 14.Miss Cheng submits that The Nema guidelined (as adopted in Hong Kong in the PT Dover case) do not apply to section 24. She refers the court to a passage in Indian Oil Corporation v. Coastal Bermuda Ltd [1990] Lloyds Law Reports at page 414 where Evans J said :
15.Thus, section 24 confers on the court a discretion. Mr Aiken does not suggest that the above passage is wrong but simply invites the court to put it into the Hong Kong context when deciding whether or not to exercise the discretion. He reminds the court of the following case. 16.In A.G. v. Shimizu Corp. [1996] 2 HKC 412, Leonard J held :
17.Later in the judgment he cites, Sir John Donaldson's remarks :
(Section 22 is the same as Hong Kong's section 24). 18.Of course, this does not permit the courts to turn a blind eye to justice. However, whether or not there is a real risk that an injustice has occurred has to be viewed in the light of, and balanced against, the established principles governing applications for leave to appeal. The presumption of finality and the parties' acceptance of the arbitral process weigh heavily in that balancing act. When deciding whether to grant an application under section 24 the court will only do so if there has been an obvious error and that error was so exceptional that a failure to remit would constitute a serious injustice. 19.With all these principles in mind, I now turn to the several grounds of appeal. Broadly speaking, there are two groups of grounds. Counsel have referred to the first group as 'Time' points. The second group is largely concerned with issues of quantum. Given the length of the submissions and the somewhat elaborate nature of the arguments (Miss Cheng's helpful written skeleton is 48 pages) and given the length of the award itself and the notice of motion, it would be unduly onerous to set out in full, all the extracts from the award which are the subject of complaint, extracts from the notices of motion listing the complaints and the grounds of appeal themselves. Mr Aiken's approach has been to summarize and crystallize the issues. I shall attempt the same, although it will be necessary to recite some parts, albeit selectively, of the award which are under scrutiny. THE 'TIME' POINTS
20.The arbitrators award states as follows :
21.The applicant's submissions in relation to this part of the award are firstly, that the arbitrator was wrong to say that Practical Completion does not mean 100% completion (with regard to this contract) and secondly that he failed to consider all relevant circumstances when assessing practical completion. (a) What does practical completion mean in this contract? The complaint is that the arbitrator ignored SP 17.28 and SP 17.22. It is submitted that these are conditions precedent to the issuance of practical completion. For example SP 17.28 provides that "prior to the issue of a certificate of practical completion, the Main Contractor shall submit to the Architect the following:". One of the things then listed is "Maintenance and Instruction Manuals". It is a fact that all such manuals had not been submitted prior to 24 June. The effect of SP 17.22 was never argued before the arbitrator, however the answer in relation to both is the same, as follows. 22.Firstly, it is plainly a "one-off" issue and of no general interest to the construction industry or legal profession. It concerns this contract only. In any event, there is a strong argument that the arbitrator was right. Practical completion means completion for practical purposes. It does not mean final completion. SP 17.28 was not overlooked by the arbitrator, he refers to it earlier in the award, before coming to his decision. SP 17.28 places an onus on the Main Contractor to provide documents to the Architect. The Architect is not compelled to wait for each and every single piece of paper. The Architect is entitled to them all before certifying but is not prevented from certifying if one is missing or lost. (b) Did the arbitrator fail to consider all the relevant circumstances when assessing practical completion? In my judgment this issue falls at every fence. It is primarily a question of fact, it is a one-off point, it is not of any general interest and the arbitrator did not fall into error in making his decision. 23.The primary suggestion is that the arbitrator, once the certificate is challenged, should simply ignore it and start the assessment process from scratch. Not so. The arbitrator's approach, which in my judgment cannot be faulted, was to consider the architect's decision, then consider the respondents' arguments in relation to it, he then decided the architect was right and therefore declined to substitute any other view. It seems to me he followed the approach referred to at p.113 in Merton v. Leach 32 BLR 51 :
Mr Wall did not consider it "appropriate". 24.The next submission made by the respondent is that the practical completion certificate was conditional and as the condition had not been complied with, the date could not be set. Again, this is primarily a matter of fact. The arbitrator was aware of the argument and rejected it. He recongized that a date had to be fixed so that the parties would know when the 12-month defects liability period would start to run. It is true that the certificate itself refers to two items which are specifically required to be done thereafter. To suggest that this should in some way erase the date of certificate is an untenable argument. The two matters referred (general cleaning and repairs to the curtain wall glazing) are typical of jobs done within the defects liability period. The arbitrator's findings amount to a finding of fact that the certificate was not and could not be for all practical purposes a conditional certificate. 25.It is further suggested that he should have chosen a later practical completion date because of other post 24 June events. The submission being that certain subsequent events rendered the certified date incorrect and the arbitrator failed to take them into account when he confirmed the date of 24 June. I find there to be no substance in this complaint. The subsequent events relied on did not escape the arbitrator's notice and are, in any event, items which are typically dealt with in the defects liability period. They were items such as, a problem with the water connections, a teething problem with the fire alarm system, cosmetic damage to the glass walling, general cleaning and other minor defects. 26.In short, on none of these matters can it be said that the arbitrator made an obvious error of law or that an obvious injustice may have occurred meriting a remission of the points for his reconsideration.
27.Selected extracts form the award which are the subject of complaint by the applicant under this heading are :
28.It is necessary to set out the relevant parts of clause 23, SP 5.03 and SP 8.02.
((a) to (k) are then set out)
29.In short, two issues arise under this heading. The arbitrator held that SP 8.02 did not modify clause 23 because SP 8.02 and SP 5.03 are inconsistent with each other. It was not disputed that the respondent did not comply with the notice requirements. The two points of law which the applicant submits are of importance and should be remitted together with an opinion from this court are :
The award gives negative answers to both. The decision is premised on the inconsistency between the two SPs. 30.Miss Cheng's submissions on the point have been carefully and thoroughly advanced but again, in my judgment, do not pass the basic tests. Taking the "notice" point first, I agree with Mr Aiken that it is a "one-off" point. The interaction of clause 23 with SP 5.03 and SP 8.02 concerns this contract only. The applicant has exhibited a single page from another contract as evidence that the profession would welcome clarity and certainty on the point. As Mr Aiken points out not only is only a single page exhibited but even that single page provides for a different time period. It refers to "within 28 days", SP 8.02 requires it to be "within 14 days" and SP 5.03 requires "notice forthwith". 31.In any event, I consider the arbitrator's finding of an inconsistency between SP 5.03 and SP 8.02 to be a finding of fact, with which this court would not interfere. Moreover, the effect of the finding, namely that SP 8.02 does not modify clause 23, is not unreasonable. It is the sort of issue where one can see that in front of another arbitrator the opposing arguments might have found favour. However, given the stringent tests to be applied, it is not the sort of issue which this court could or should revisit and reverse. Mr Wall's analysis recognized that SP 5.03 is called an "amendment" whereas SP 8.02 is not. Also, it is no more than logical to conclude that if contracting parties wished to make an amendment to a particular part of clause 23 they would not do so twice in different places and in different terms. 32.It is worthy of note also that the arbitrator, when considering this issue, rightly applied the contra proferentum principle. The employer was seeking to rely on the notice point and the arbitrator construed it against him. 33.Finally, even if there was an appealable point, the law supports the arbitrator's decision namely that there is no general requirement of giving notice as a condition preceded for the granting of an extension of time. The commentary on issue 14 in Merton v. Leach contains the following :
34.The second issue concerns the method of calculating the extension of time. The complaint is that the method proposed by the applicant's expert, Mr Battersby, was the correct method in law and should have been followed. 35.It is not appropriate for this court to enter the arena of the differences between the experts. Both were respected experts. They had different opinions about how the critical path should be drawn and which critical path should be used as the basis of the calculations. It has not been demonstrated to this court that the difference between them is a well known bone of contention in the industry or that the law clearly shows one method to be correct and the other incorrect. Experts frequently use different methods and disagree over how a calculation should be made and what produces a fair result. Different situations often call for different methods. It is a highly technical area into which the courts should fear to tread. In this context a non legal arbitrator is far better equipped to make a preference between experts than a legally qualified arbitrator or judge. The particular difference of opinion between Mr Battersby and Mr Chan is relevant to this dispute only. It is obviously a one-off issue which the arbitrator addressed and made a decision about. He had to choose one or the other and he made a number of comments which illustrate why he chose Mr Chan. For example :
36.It is not for this court to go behind these findings and comments. To do so would involve re-opening all the expert evidence and re-evaluating it - a task which is neither possible nor permissible on appeal. 37.If the applicant's argument found favour with the court on this issue, the court would have to embark on a task, virtually amounting to a codification of methods of calculation. In truth it is incapable of codification or even of statements of hard and fast rules. The task would be monumental, of no value and dangerous. The applicants are understandably disappointed that their expert's evidence was not preferred. His method would have resulted in no extension of time being granted at all. The arbitrator allowed 703 days (compared to just under 300 days allowed by the architect). The difference is very substantial and has very large financial consequences, but, it is a classic example of a dispute being entrusted to an arbitrator whose decision has to be lived with by the losing party.
38.On this issue the arbitrator found :
39.The complaint being made in this application is threefold :
40.A general point should be made first. The applications under B. Extension of Time and C. Time at Large should be viewed in tandem. If the arbitrators conclusions in respect of either are unappealable then giving leave to appeal the other would be academic. As it happens, my decision is that the applications under both heads must fail. If I am wrong on one or the other, the effect of the award remains unaltered by virtue of the correctness of the other finding. 41.However I now consider the time at large application as a discrete point. In my judgment, each complaint, listed above and carefully enlarged upon by Miss Cheng for Might Foundate in her submissions, can be succinctly dealt with (and were succinctly dealt with by Mr Aiken for CCECC). 42.Firstly, this ground gives rise to no general principle of law which the arbitrator got wrong or that requires clarification for the benefit of the industry. In fact, it is submitted, with some force, that the arbitrator was fully aware of the correct approach and applied it to the facts as he found them. At paragraph 158 of the award he said :
43.The complaint arising from this statement that there was no evidence of causative delay is simply not made out. Many letters from complaining sub-contractors were exhibited. 44.It is clear from a reading of the award that the arbitrator was aware of the issues. Miss Cheng complains that it is not good enough simply to aware of the issues, the arbitrator must deal with and give reasons for his decision on each and every issue. In my judgment, on this issue, the arbitrator plainly discharged his duty in a sensible and proper way. He identified the issues, referred to authorities which he considered and decided the time at large issue reasonably, sensibly and correctly. For example he considered Findlay J's obiter remarks in Wui Fu Development Co. Ltd v. Tak Yuen Construction Co. Ltd CT40/1998 where he said :
45.In our case, there were admitted late payments running into millions of dollars. Sub-contractors depend very heavily on these interim payments. The arbitrator cannot be faulted for making a finding, in this particular set of facts, which recognized the fact that, very often, in Hong Kong a sub-contractor's lot is not a happy one. 46.Next, the applicant makes a particular complaint in relation to paragraph 170 of the award :
47.Miss Cheng points out that the practical completion date of 24 June is 763 days after the contractual date. If therefore this has to be reduced by 60 days (as found) for the reinforced concrete problem how can the reasonable time for completion still be 24 June? (703 days was the amount allowed by the arbitrator). The answer is simply as follows. If there is an inconsistency in the arithmetic it is the type of error which the parties must live with. What is more, it does not matter. 60 days was disallowed on two grounds, once in the extension of time argument and secondly as a pleading point. It is simply logical to determine, for quantum purposes, that having found time at large, the date for practical completion and the date for reasonable time for completion should coincide. It is not a matter that can or should be re-opened by this court. 48.The final complaint concerns the arbitrator's remarks in paragraph 156 :
49.I do not propose to recite clause 26. The applicant complains that the arbitrator did not deal with this issue. I however agree that, by implication, the arbitrator rejected the argument being advanced. It cannot be said that in doing so there is a strong prima facie case that he was wrong. Neither is it a legal point of general interest requiring resolution. It is true that clause 26 envisages a two-stage process and that the claimants only invoked the first stage. The question, which very probably should be answered in the negative, is, by failing to pursue the entire process under clause 26 did the claimants waive such rights as they already had. It is not surprising that the arbitrator impliedly rejected the argument because he recognized that the simple reason the second stage was not pursued was because the claimant received some payments. 50.In conclusion on all the "time" points, I find them all to fall into the "one-off" category. No point of law requiring clarification has been identified. The presumption of finality should apply to those findings of the arbitrator which have been the subject of challenge. THE "QUANTUM" ISSUES 51.In all the following issues, I agree with the submission of the respondent that these are either one-off issues where it cannot be said that the arbitrator was obviously wrong or are questions of fact which generate no important issue needing clarification.
52.The arbitrator held :
53.The ground of appeal is that :
54.Clause 24 was amended by SP 5.03. There was no evidence that this amendment was anything other than peculiar to this contract. It was a "one-off" amendment. It is basically the same point as hitherto dealt with under the "extension of time" arguments. Here also it is plain that the arbitrator was aware of what was being contended for. He did not accede to the argument and therefore rejected it. He did not reject it in one line. It can be seen he considered and commented on the issues by way of footnotes to his award (at pages 60 and 61 of the award). He construed the notice point under clause 24 against the applicant. In doing this he applied the principle of contra proferentum and common sense. He was not plainly and obviously wrong to do so.
55.The complaint here is that the arbitrator's assessment used the wrong approach because it resulted in an inevitable element of double recovery. It was acknowledged that there would be some double recovery. The experts were unable to say what that element was. The arbitrator therefore concluded it would be wrong for him to speculate and made no allowance for double recovery. The applicant now contends that if it was impossible to calculate double recovery, then any assessment would be inaccurate and therefore no award should be made under this heading at all. I do not consider this to be a reasonable approach. The arbitrator's approach was better and does not create grounds for giving leave to appeal.
56.The arbitrator made an award of $148,071 under this heading. The applicant criticizes the way he did it. It is said he did not construe the contract properly and did not base his finding on evidence. This is clearly more a question of fact than law. In as much as it gives rise to questions of construction they are one-off issues concerning this contract. The arbitrator adopted a sensible and rational method "in the absence of any other evidence ...." (paragraph 204 of the award). Further consideration of this issue is not merited.
57.The awarding of interest is discretionary. The arbitrator allowed simple interest at 11.26%. He explained his reasons. It is substantially a question of fact. Even if questions of law are involved in coming to his decision it is unsustainable to suggest that in exercising his discretion the way he did he was obviously wrong. This court certainly cannot substitute a different rate nor should direct the arbitrator to reconsider the rate.
58.No general point of interest arises here either, nor can it be said that the arbitrator made a serious, or indeed any, error. The applicant complains he failed to evaluate the evidence properly. What he said (at paragraph 283) was :
59.It is clear that he was aware of the issue, dealt with it in a conventional and reasonable way and made a factual finding. There is no basis on which this court should interfere. It was the respondent's alternative claim, their evidence in support was, quite simply, found to be lacking. Section 25 application 60.In view of this court's refusal to grant leave to appeal under section 23 and refusal to remit under section 24 the application to remove the arbitrator under section 25, cannot arise. 61.Even if there had been grounds to grant leave or reasons to remit some or all of the points raised by the applicant, I would not have granted the application under section 25. 62.It is a serious application to make and would only be granted in exceptional circumstances. In this case, it seems to me that the application is made for no better reason than the arbitrator consistently made findings contrary to the applicant's submissions (which they no doubt felt were correct) and they therefore lost confidence. What they lost confidence in was not the arbitrator's ability to discharge his duties properly but in the prospects of him making findings in their favour. In my judgment, the section 25 application was a make-weight to the sections 23 and 24 applications and should not have been made. 63.The applications under sections 23, 24 and 25 are refused. I see no reasons why costs should not follow the event and so there will be a costs order in the respondent's favour. I am grateful to Miss Cheng and Mr Aiken for their comprehensive and helpful submissions. I understand there are other summons outstanding which have been stayed pending the outcome of these proceedings. I hope it will now be possible for the parties to agree orders under those summons consequent upon the conclusion of these applications.
Representation: Miss Teresa Cheng, SC, instructed by Messrs Joseph C.T. Lee & Co., Mr Nigel Aiken, SC, leading Mr James Lee, instructed by Messrs Fung, Wong, Ng & Lam, for the Respondent in HCCT 24, 25 & 26/2001 and Plaintiff in HCCT 23/2001 |
Further hearings and rulings under HCCT23, 24, 25 & 26/2001