F & D Buildings Services Engineering Co Ltd v. Chevalier (E & M Contracting) Ltd
Read the full judgment text of HCA 9327/2000 on BabelCite. This High Court CFI judgment was delivered on 23 February 2001.
1. This is an application to stay proceedings in favour of arbitration pursuant to section 6 of the Arbitration Ordinance. Section 6 provides that :
Cites 1 case
|
HCA009327/2000
IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO.9327 OF 2000 -----------------
----------------- Coram: Hon Burrell J in Chambers Date of Hearing: 21 February 2001 Date of Decision: 23 February 2001 ----------------- DECISION ----------------- 1. This is an application to stay proceedings in favour of arbitration pursuant to section 6 of the Arbitration Ordinance. Section 6 provides that :
2. Article 8 states that the court :
3. The present case concerns three contracts between the parties. There is no dispute that each contains a similar arbitration clause as follows :
4. There is no dispute either that the plaintiff's claims all relate to the value of variations completed by the plaintiff. 5. The plaintiff resists the application for a stay in this case on the basis that there is "no dispute" between the parties which is referable to arbitration. The plaintiff's case
As evidence that the parties have reached an agreement in relation to the sum claimed (and therefore there is no dispute), the plaintiff points to a letter from the defendant dated 4 September 1999 which stated as follows :
6. Enclosed was a schedule which stated : "outstanding amount to be issued $1,287,624". The sum claimed under the 1st contract is $2,120,394.30. The plaintiff says the balance in issue has also been settled by agreement.
$1,096,245 is claimed. The plaintiff points to a similar letter dated 27 August 1999 :-
A smaller sum of $108,275 is claimed. Although there is no letter in relation to this claim, the plaintiff submits that the defendant had agreed with the costs for the variations by amending the figures in the quotations and returning them to the plaintiff. Also, some of the retention money for their work has been released which can only occur after the issue of the Practical Completion Certificate. It is argued that the defendant would not have released any retention money if they disputed the value of the works. 7. Counsel for the plaintiff also relied on the decision in Peter Leung Construction v. Tai Poon Co. Ltd [1985] 1 HKC 285 which held that :
8. In the present case, it is submitted that at the time of the writ, 4 October 2000, there is no evidence that the defendant had disputed the value of the works claimed, nor had it indicated an intention to arbitrate. The defendant's submission in favour of a stay 9. I have come to the conclusion that the submissions advanced by the defendant, through its counsel Mr Anthony Houghton, are correct and that, accordingly, a stay will be granted in this case. The key points made are these : (a) The present law is that if there is a "dispute", as currently defined, the stay is mandatory. The law leans heavily in favour of stays pending arbitration being granted. In Louis Drefrus Trading v. Bonarich International [1997] 3 HKC 597, Waung J held :
10. In Zhan Jiang E & T Dev Area Service Head Co. v. An Hau Co. Ltd [1994] 1 HKC 539, Kaplan J held :
(b) In respect of all three contracts, it cannot be said that there is no dispute. The plaintiff does not deny that the variations were done as a result of the defendant issuing purchase orders to the plaintiff. The purchase orders showed the "assessed amount" in each case which was ultimately always subject to certification by the consultant or project quantity surveyor. Each purchase order stated :
11. Each order was expressly stated to be "provisional". The practice was that 75% of the estimated amount was allocated, then the exact final amount would depend on the consultant's certification. The defendant contends, and this is the issue in dispute, that the "assessed amount" was not a fixed lump sum but an estimated sum which might vary depending on the consultant's certification. (c) Thus the meaning of the "assessed amount" is in dispute, the amount of works done is not agreed and neither is the appropriate rate of payment. All this leaves the plaintiff well short of showing that there is an unequivocal admission on liability and quantum. (d) The defendant also notes in support, that no admission of liability is clamed in the Statement of Claim and no Order 14 summons has been filed, to be heard immediately following the stay application. Should a stay application fail on the grounds that there is "no dispute", a successful Order 14 summons is usually a formality. (e) In answer to the Peter Leung's case (supra), Mr Houghton invites the court to consider and apply the decision of Kaplan J in Big Island Construction (HK) Ltd v. Abdoolally Ebrahim & Co (HK) Ltd [1994] 3 HKC which expressly did not follow the Court of Appeal's decision in Peter Leung v. Tai Poon. Kaplan J held :
12. The law, in 1986 when the Peter Leung's case was decided and in 1994 when the Big Island's case was decided, was different to the present law. Even in 1994, however, Kaplan J made the following observations :
(f) Even if it could be said that some of the sums claimed are indisputably due, it would be wrong to refuse a stay for part of the claim and allow the balance to go to arbitration. It would be wrong in principle and impossible to calculate in this case. 13. In all the circumstances, the mandatory stay will be granted with costs of the summons to the defendant.
Representation: Mr Joeson Wong, instructed by Messrs Lau & Leung, for the Plaintiff Mr Anthony Houghton, instructed by Messrs Wong & Fok, for the Defendant |
Cases cited in this judgment