Schindler Lifts (Hong Kong) Ltd. v. Ocean Joy Investments Ltd.
Read the full judgment text of HCCT 81/2001 on BabelCite. This High Court CFI judgment was delivered on 10 January 2003 before Ma J.
Civil procedure – summary judgment – construction contracts – nominated subcontractor – letter of intent – whether triable issues exist – plaintiff claimed balance of $1,166,100 for lift installation work at a commercial development at 7-11 Li Yuen Street East, Central – defendant was the employer under the development – letter of intent dated 8 June 1998 from defendant's agent LCT Associates Limited accepted plaintiff's tender for nominated subcontract with contract sum of $3,780,000 – clause 9 envisaged plaintiff would be nominated to the main contractor and required entry into subcontract with main contractor – clause 12 required performance bond – clause 14 stated letter of intent together with listed correspondences shall constitute binding contract between plaintiff and employer until formal agreement prepared and executed with main contractor – main contractor Free Form Construction Company Limited appointed and written contract between defendant and Free Form dated 12 January 1999 – first issue whether subcontract existed between plaintiff and Free Form – court held triable issue existed based on performance bond dated 24 August 1998, warranty dated 5 August 1998, extensive correspondence, and payment claims – second issue how clause 14 affects position if subcontract existed – court held triable issue on true construction considering clauses 9 and 12 and commercial context, referring to Stent Foundations v Carillion for the importance of looking at whole contract and factual matrix – third issue whether estoppel by convention arose – court held should go to trial as facts may show common assumption communicated between parties – estoppel by convention arises when parties act on agreed assumption as to facts or law – requirement that mistaken assumption be common and communicated – application for summary judgment refused – defendant given unconditional leave to defend – costs of plaintiff's application to be costs in the cause (order nisi)
Legal issues: Whether a subcontract existed between the plaintiff and Free Form · Effect of clause 14 of the Letter on the defendant's liability · Whether an estoppel by convention arose
Outcome: Summary judgment refused; defendant given unconditional leave to defend the action
Cites 4 cases
|
HCCT000081A/2001 HCCT 81/2001 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO. 81 OF 2001 ______________
______________ Coram: Hon Ma J in Chambers Date of Hearing: 24 September 2002 Date of Judgment: 10 January 2003 _______________ J U D G M E N T _______________ The plaintiff's claim 1.By a summons dated 25 February 2002, the plaintiff seeks summary judgment in the sum of $1,166,100.00 and interest, being the balance allegedly due to it from the defendant in relation to some lift installation work that had been carried out by the plaintiff at the commercial development situate at 7-11 Li Yuen Street East, Central, Hong Kong. 2.The defendant was at all material times the employer under the said development. The plaintiff's claim is based on a letter of intent dated 8 June 1998 from LCT Associates Limited (the defendant's agent) to the plaintiff ("the Letter"). 3.In the Letter, the plaintiff was informed that its tender for the lift installation nominated subcontract in relation to the said development had been accepted by the defendant (as the employer). The contract sum was stated to be $3,780,000.00. 4.The Letter went on to set out various terms of the plaintiff's engagement. The following terms should be noted:-
5.At the time the Letter was issued and signed by both parties, the main contractor for the development had not as yet been appointed. Later in 1998 or early 1999, Free Form Construction Company Limited ("Free Form") was appointed the main contractor for the project. The written contract between the defendant and Free Form was dated 12 January 1999. The issues in the present application for summary judgment 6.The plaintiff's case is simply put by Mr Geoffrey Shaw who appears on its behalf: the said balance of $1,166,100.00 is indisputably due under the agreement contained in the Letter. 7.The defendant raises a number of defences in its Amended Defence. Principally, its stance is that any agreement between the plaintiff and the defendant as contained in the Letter (which is denied), fell away once Free Form was appointed the main contractor and had entered into a contractual relationship with the plaintiff. Mr Thomas Lee, who appears for the defendant, submitted that this was so for the following reasons (and that there were therefore triable issues):-
8.The plaintiff joined issue with these submissions. Mr Shaw contended in the first place that there was no subcontract between the plaintiff and Free Form anyway. Even if there was, this did not mean that the agreement contained in the Letter became irrelevant because clause 14 was explicit in this respect: only if a formal agreement was executed between the plaintiff and Free Form would the agreement in the Letter fall away. Finally, it was argued that the facts in the present case did not bear out any estoppel by convention. 9.Three issues can therefore be identified for consideration in the present application for summary judgment:-
10.In deciding whether or not summary judgment should be given, I bear in mind the standard approach in such applications:-
Was there a subcontract between the plaintiff and Free Form? 11.In my view, this is clearly a triable issue:-
12.There may be some dispute as to the exact terms of the subcontract between the plaintiff and Free Form, but the existence of a subcontract is a matter that ought to be tried. The impact of clause 14 of the Letter 13.Mr Shaw argues with some conviction that even if there was a subcontract between the plaintiff and Free Form (which the plaintiff denies), the terms of clause 14 are clear. Unless there is in existence a formal contract that has been executed by the plaintiff and Free Form, the defendant remains liable to the plaintiff under the agreement contained in the Letter. 14.Mr Lee submitted that on a true construction of the Letter, the defendant's liability thereunder (if this existed in the first place) fell away once a subcontract was made between the plaintiff and Free Form. 15.I am of the view that the defendant's position here is likewise a matter that should go to trial for the following reasons:-
Estoppel by convention 16.Even if Mr Shaw's construction of clause 14 is correct, the defendant's case on estoppel by convention should also go to trial. As pleaded, the estoppel relied on is the common assumption on the part of the plaintiff and the defendant that "they did not have or after the end of 1998 no longer had, a binding agreement with each other and that the plaintiff entered into the Sub-Contract with Free Form Construction Co. Ltd.". 17.Estoppel by convention arises when parties have acted on an agreed assumption as to a state of facts or of law (which includes the construction of a document):- see Chitty on Contracts (28th Edition) Volume 1 at paragraphs 3-100 to 3-103; Amalgamated Investment & Property Company Limited v Texas Commerce International Bank Limited [1982] QB 84, at 120H-122D, 126A-B, 130G-131A; The Vistafjord [1988] 2 Lloyds Rep 343, at 349(2)-353(1); Hiscox v Outhwaite [1992] 1 AC 562, at 574H-575H; Yuen Ching Yuen v Union Insurance Society of Hong Kong Limited [1998] 2 HKC 294, at 304-5. 18.I should perhaps highlight two aspects of estoppel by convention:-
19.The following facts and matters in the present case are relevant and should go to trial:-
Conclusion 20.For the above reasons, I order that the defendant should be given unconditional leave to defend the present action. 21.Although Mr Shaw appeared to accept that costs should follow the event, in view of the order sought by the defendant being unconditional leave to defend, I shall make an order nisi that the costs of and occasioned by the plaintiff's application be costs in the cause.
Representation: Mr Geoffrey Shaw, of Messrs Deacons, for the Plaintiff. Mr Thomas Lee, instructed by Messrs Simmons & Simmons, for the Defendant. |
Cases cited in this judgment
Further hearings and rulings under HCCT 81/2001