Schindler Lifts (Hong Kong) Ltd v. Shui on Construction Co Ltd
Read the full judgment text of HCA 7005/1991 on BabelCite. This High Court CFI judgment was delivered on 2 July 1992.
1. I have before me two summons. The first is taken out by the Plaintiff, and this seeks summary judgment for $447,223.50 being the sum said to be due under Certificates 37 and 39 dated respectively 27th June 1990 and 3rd January 1991.
Cites 1 case
|
HCA007005/1991 1991, No. A7005 IN THE SUPREME COURT OF HONG KONG HIGH COURT __________ BETWEEN
__________ Coram: The Hon. Mr. Justice Kaplan in Chambers Date of Hearing: 2 June 1992 Date of Handing Down Judgment: 2 July 1992 ______________ J U D G M E N T ______________ 1. I have before me two summons. The first is taken out by the Plaintiff, and this seeks summary judgment for $447,223.50 being the sum said to be due under Certificates 37 and 39 dated respectively 27th June 1990 and 3rd January 1991. 2. By their summons the Defendants seek a stay of these proceedings in favour of arbitration. 3. By a main contract dated 12th June 1987 entered into between Kornhill Development Limited as employer and the Defendant as main contractor, the Defendant agreed to erect and construct a Hotel Development at Pacific Place Phase 1. 4. By a written sub-contract entered into between the Plaintiff and the Defendant on or about 28th May 1988, the Plaintiff as nominated sub-contractor agreed to supply install and maintain 15 lifts at the said Hotel Development. 5. One of the major issues canvassed before me and was the effect of Clause 11(b) of the sub-contract which provided that :-
6. The Defendants say that in"relation to the sums certified, the subject matter of this action, they have not received payment from the employer because the employer has set off against the total sums due under the Certificates, an equal sum by way of liquidated damages. This set off is disputed by the Defendants. 7. The Plaintiffs say that the Defendant has nevertheless received payment by virtue of the set off of liquidated damages against sums due under the Certificates. 8. This issue arises quite frequently and I am sure that the industry would like an authoritative decision on this form of sub-contract. The point has not yet been decided. In Hong Kong Teakwood v. Shui On [1984] HKLR 235, Hunter J., (as he then was) in 0.14 proceedings, when he gave leave to defend inclined to the view that receipt of payment imported receipt of cash. In Schindler v. Shui On [1985] HKLR 118 the Court of Appeal, without deciding the point, expressed the view that Hunter J., was probably right. 9. In Ryoden v. Paul Y Construction [Con. List 2/1991, Judgment handed down 31st July 19913 the same point came before me in similar but not identical circumstances. In that case I refused 0.14 Judgment and granted the stay because I was satisfied that it was arguable that the Defendant could raise a common law set off against the claim for certified sums and on that basis, I did not rule on the "pay when paid" provision although I acknowledged that a decision on the phrase was desirable. 10. I must, of course, be consistent with my decision in Ryodon unless it can be shown to my satisfaction that I was wrong but Mr. Scott for the Plaintiff submits that there is, in this case, a special feature which does entitle me to decide the "pay when paid" point without having to worry about set off. I will have to explain the chronology in order to consider his submission. Before doing so I should make clear that there is another issue in this case and that is that it is the Plaintiff's case that the agreement between the parties actually provided for payment on Certificate and not payment when paid. This issue revolves around whether a certain document was incorporated into the contract and what precisely it meant in the light of certain question and answers which also had contractual effect. 11. I should also point out that there is no authority in England on the "pay when paid" clause because payment against Certificate is the normal clause used in English sub-contracts. Mr. Aiken for the Defendant relied on the difference between the English and the Hong Kong phraseology as supporting his contention in relation to Clause 11 in the present contract. Relevant Chronology 12. Between August 1989 and October 1991 the Plaintiffs were advancing a claim for loss and/or expense. 13. In August 1989 a claim document was prepared on behalf of the Plaintiffs and this was amended in April 1991. 14. No agreement having been reached as to this claim, the Plaintiff served on the Defendant a notice to concur in the appointment of an arbitrator and this notice was dated 11th March 1991. 15. So far as it is relevant, this notice stated asfollows :
16. These proceedings were commenced on the 13th September 1991. 17. On 2nd October 1991 the Defendant paid into Court $550,000. The notice stated :
18. By an Agreement entered into between the Plaintiff and the Defendant on 7th October 1991, the parties confirmed that it had been agreed to appoint Mr. Terence James Cleary as arbitrator. Clause 2 of this agreement stated as follows :
19. On 14th October 1991 (i.e. within the 14 days period specified in 0.73) the Plaintiffs accepted the payment into Court. 20. The payment in which was thus accepted was paid in before the Defendants had served a Statement of Defence and counterclaim. The Issue 21. The Plaintiff contended that by accepting the payment into. Court, the Defendants are now precluded from raising as a defence and counterclaim to these proceedings, what was open to them to raise in the arbitration, namely, a set off for damages for delay which they contend was caused by the Plaintiffs. Mr. Scott has pointed out that in the claim document which was submitted some time ago, there was no mention of a claim under these Certificates and indeed the claim under them did not arise until after the original claim document. Mr. Scott submits that the Plaintiff has been very careful to keep out any claims under Certificates from the arbitration proceedings and he submits that by the payment into Court in satisfaction of all of the matters in dispute in the arbitration and satisfying any counterclaim which the Defendant may have this effectively precludes the Defendant from raising in these proceedings any claim for set off for delay. 22. Mr. Aiken submits that the Plaintiff must have been aware and appreciated that the payment in was in satisfaction of all matters currently in dispute. He submits that the Plaintiffs were well aware that the Defendant intended to set off and counterclaim. He reminds me that when the second notice to concur was served the c dispute with regard to the certificates had arisen. Mr. Aiken further questions why the Plaintiffs issued the writ at all. He said that it could not be for the purposes of obtaining the benefit of 0.14 because they could always ask the arbitrator to rule as a preliminary issue on the question "pay when paid". He submits that the Defendant could not have behaved in such a way as Mr. Scott describes which would be effectively abandoning a counterclaim which they had always asserted. Mr. Aiken submits that the payment in was intended to dispose of the claim on the Certificates. He goes on to submit that this does not mean that the Plaintiff would never be paid under this Certificate because all that he is submitting is that the claim was premature. As soon as the Defendant has been paid by the employer, they would then pass on to the Plaintiff such part as is due to them. In fact I was told that this is what had recently happened because in January of this year, the Defendant paid the Plaintiff $49,074.50 which was part of the claim of $447,223.50 which is precisely what the Plaintiffs are claiming in this action. Mr. Scott submitts that these stances are somewhat inconsistent. Either the payment in was intended to dispose of the claim on the Certificates, once and for all or was not. It appears, according to Mr. Scott, that the Defendants are taking an inconsistent position. 23. Mr. Scott submits that the result for which he contends is somewhat strange but it is as a result of rather strange conduct on the part of the Defendant. It seems clear to me that the claim on the Certificates was never part of the claim in the arbitration. The claim in the arbitration was for some $2,990,413.96 and it also seems clear to me that if this matter had proceeded, the Defendant would have put in a counterclaim alleging, as they have done in the proceedings before me, although somewhat vaguely, that the Plaintiff was responsible for part or all of the delay alleged. It seems to me that it is strongly arguable that the Defendants have indeed precluded themselves from raising any counterclaim based on delay in the proceedings before me. The terms of the payment into Court are wide enough to cover their counterclaim for delay. It is true that as at the date they paid the money in to satisfy any counterclaim which Shui On may have they had not actually put in a counterclaim but they had alleged that delay had been caused by the Plaintiffs and it is difficult to see what other counterclaim could have been referred to when the payment into Court was made. 24. That being the conclusion at which I have arrived it follows that the position before me now could be said to be different to that which was before me in the Ryodon case. On this basis the first decision I have to make is whether I should embark upon a construction of the "pay when paid" provision or whether I.should leave that to be decided by the arbitrator taking into account, of course, that the parties have agreed to have all differences under this contract resolved by arbitration. No useful purpose can be achieved by referring to the various authorities to which I made ample reference in the Ryodon case. I, of course, take into account the observations of Kerr L.J. in Sethia Limited v. India Trading Co. Ltd. [1986] 1 WLR 3098 at 1401 and 1402 and I further have regard to the observations of the Court of Appeal in Home and Overseas Insurance Limited v. Mentor Insurance Co. (UK) Ltd. [1989] 3 AER 74. It is also necessary to have regard to Hayter v. Nelson & Home Insurance Co. [1990] 2 Lloyds Rep. 265. In that case Saville J. referred to an observation of Templeman, L.J. in Ellerine v. Klinger [1982] 1 WLR 1375 where he said :
Saville J. went on to say this at p.271 :
25. It is implicit in the decision in The Channel Tunnel Group v. Balfour Beatty [1992] 2 WLR 741 that the Court of Appeal approved Saville J.'s approach. (On 11th June 1992 the appeals committee of the House of Lords gave leave to appeal in The Channel Tunnel case). 26. In Icos Vibro Ltd. v. SFK Management Ltd. & Sung Foo Kee (Civil) Ltd. [Con. List 9 of 1991 - judgment dated 26th February 19921 I had cause to consider Hayter and in following it I concluded that it was not inconsistent with the Home v. Overseas case. I have to ask myself the question whether the defence based on non payment is misconceived. In my judgment, I cannot say that. The next question is whether after relatively short argument, I can be satisfied that the point is 'plainly unsustainable'. [Parker L.J. in Home v. Overseas]. I have given this matter long and anxious consideration and I am left in this state of mind. I have formed a view as to what 'receipt of payment' means in the context of this contract. On the other hand, I cannot characterise the contrary argument as being unsustainable or misconceived. It is one of those points where there exists the reasonable possibility of differing views. 27. As I said in Ryoden I would like to decide thispoint given that I have formed a view as to the meaning of the relevant phrase and the fact that it is important for this point to be resolved. If there had been no arbitration clause in this case, I would have decided it. However, I am very conscious of the fact that the parties have chosen arbitration to settle their disputes and this covers the present dispute on the onstruction of this clause. As Parker L.J. put it in Home v. Overseas,
28. I believe that this passage accurately reflects the position where, as here, there is an arbitration clause. If I were to decide this point myself I would be arrogating to myself a power which the parties had by their contract vested in the arbitrator. I am not prepared to interfere with the contractual mechanism for dispute resolution having decided that the point is arguable even though I know which way I would have decided it. 29. I was faced with a similar situation in On Lee General Contractor v. The Garden Co. Ltd. (1992 A328 & 330 6th March 1992] where I refused 0.14 judgment and granted a stay in order that a point of construction should be decided by the arbitrator. Although I found the Plaintiff's arguments attractive, I could not conclude that it was 'readily and immediately demonstrable that the (defendants) had no grounds at all for disputing the claim". The point at issue there was whether the existence of the defects liability period excluded the right to claim damages for those defects. It appeared to me that there was a point of construction which had to be decided by the arbitrator who was invested with power by the parties to resolve all disputes arising out of that contract. 30. The correct procedure in the present case, as it seems to me, is that the parties should invite the arbitrator to rule on this matter by way of interim award if necessary and then leave it to the dissatisfied party to apply for leave to appeal if so advised. If leave is granted then the Court would be able, perfectly properly, and within the Arbitration Ordinance and within the spirit of the parties contractual arrangements to give its views on the construction of this vexed phrase. 31. In relation to the other point namely' that the parties agreed to payment on certificate, I am likewise satisfied that this is arguable and this should also be decided by the arbitrator. It may well be that on this point some evidence may be required. 32. I have felt some concern that on two occasions I have declined to decide an important point of construction in a standard form of sub contract in use in Hong Kong. My concern is to some extent assuaged by the fact that the parties to this dispute have themselves brought about this position. Their standard form contract contained an arbitration clause. If they had wanted this particular point decided by the court two courses of action were open to them. They could have invited the Chief Justice to appoint a judge arbitrator under s 13A of the Arbitration Ordinance. Alternatively they could have agreed to waive their arbitration agreement to enable this point to be decided by the court. They have not agreed on either of these two courses of action and in those circumstances I see nothing wrong in them being bound to honour the dispute resolution method agreed in their contract. 33. It follows therefore that I have come to the conclusion that I must refuse this 0.14 application and grant a stay of these proceedings as sought by the Defendants. I should make it clear that the only ground upon which the stay was opposed was that there was no dispute or difference which needed to go to arbitration. Having decided that there was such dispute or difference the Plaintiffs have got no other grounds upon which to oppose the stay in favour of arbitration. Therefore, in the exercise of my discretion under s.4 of the Arbitration Ordinance, Cap. 341 1 grant the stay sought. 34. I propose to make a costs order nisi in favour of the Defendants both in relation to the Plaintiffs 0.14 summons and the Defendants application for a stay.
Representation: Mr. John Scott instructed by Deacons for Plaintiff. Mr. Nigel Aiken instructed by Masons for Defendant. |
Cases cited in this judgment