Connected Successful Investment Ltd v. Sit Kwok Wai Carol t/a Concourse Engineering Co and Another
Read the full judgment text of HCCT 102/2002 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 30 June 2003 before Hon Burrell J in Chambers.
Civil procedure — Summary judgment under Order 14 — Interim payment under Order 29 — Construction and arbitration proceedings — Dispute over subcontract payments — Counterclaims and disputed contractual terms — Leave to defend granted. CONNECTED SUCCESSFUL INVESTMENT LTD sought summary judgment or interim payment against SIT KWOK WAI CAROL trading as CONCOURSE ENGINEERING CO. and KEUNG KEE CONSTRUCTION LTD in relation to claims under the Choi Yuen and Tsing Yi sub-contracts. The plaintiff’s claim was challenged by the 1st defendant on substantive issues including disputed counterclaims for unpaid loans and questioned reductions in contract sums. The defendant raised a pleading issue on omission of the payment clause from the Statement of Claim, left unresolved without dismissal. The court found that the plaintiff’s evidential foundation was insufficient to satisfy the thresholds required for summary judgment or interim payment, based on arguable points that required trial resolution. The court accordingly granted the 1st defendant unconditional leave to defend and ordered costs in the cause.
Legal issues: Summary judgment application under O.14 · Interim payment application under O.29 · Pleading point on omission of payment clause in Statement of Claim
Outcome: 1st defendant granted unconditional leave to defend; plaintiff’s applications for summary judgment and interim payment refused.
|
HCCT000102/2002 HCCT102/2002 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS ---------------------
---------------------- Coram: Hon Burrell J in Chambers Date of Hearing: 24 June 2003 Date of Decision: 30 June 2003 ----------------------------- D E C I S I O N ----------------------------- 1.This is an application by the plaintiff for summary judgment under O.14 or an interim payment under O.29. 2.For the purpose of these proceedings, the plaintiff accepts that the 1st defendant sub-contracted works to the plaintiff, the ultimate employer for which was the Housing Authority. The writ seeks a sum of over $29 million but these proceedings relate to a relatively small part of that claim. 3.The claim concerns two sub-contracts, called the Choi Yuen sub-contract and the Tsing Yi sub-contract. 4.The plaintiff puts its case on two bases. On its first position, it quantifies its O.14 claim in the sum of $3,331,953.44. In support of that claim, the plaintiff does no more than to refer the court to an arithmetic calculation contained in a plaintiff's affirmation. No further attempt has been made to justify it. All the plaintiff's submissions in support of its contention that the defendant has no defence are in relation to their second position which is for $1,343,536.92 which Mr Geoffrey Shaw for the plaintiff describes as a "stronger" claim. 5.As will be seen from this decision, I find for the defendant on the plaintiff's second "stronger" position. There is therefore no need to consider the weaker first position. 6.The second position requires a brief analysis of each of the constituent parts of the claim, to which the plaintiff submits either there is no defence or that there are grounds for awarding an interim payment. 7.Firstly, however, the defendants, represented by Mr Andrew Bullett took a pleading point. He submitted that the basis of the plaintiff's application was based on an obligation on the defendants to pay the plaintiff whereas the Statement of Claim is silent as to Clause 5 of the contract wherein the obligation to pay is contained. Thus, the submission is that the claim for which summary judgment is claimed is not "a claim included in the writ" as required by O.14, rule 1. 8.As already stated, I have concluded that the defendant be granted unconditional leave to defend for reasons which follow. I therefore do not dismiss the plaintiff's claim on the point of pleading. I leave it unresolved. The plaintiff may, in due course, if so advised, seek leave to amend the Statement of Claim. However, I make no ruling in this decision as to whether it is necessary or not. 9.I turn now to the merits of the plaintiff's application item by item. 1. The Choi Yuen sub-contract 10.The issue here is whether or not the 1st defendant's counterclaim of $735,013.00 is sustainable or not. It falls into two parts. $35,013.00 relates to an outstanding loan which the plaintiff accepts is due. It is the balance of $700,000.00 which is contentious. The plaintiff says payments, totalling $700,000.00 were not made on the Choi Yuen sub-contract but concerned a different contractor. In support the plaintiff relies on a written agreement dated 22 November 1999 between the 1st defendant and the other contractor. The difficulty facing the plaintiff is that the agreement in question contains two clauses. The first clause supports the 1st defendant's position that it is not liable for this sum and the second clause, upon which the plaintiff relies, is unclear and vague in its meaning. The meaning contended for by the plaintiff is disputed by the 1st defendant, and on arguable grounds. It is a matter for legal argument at trial. 2. The Tsing Yi sub-contract 11.The starting point for this sub-contract is the plaintiff's case that the 1st defendant owes it $1,343,536.92. This is made up as follows :
12.The 1st defendant submits that it is arguable that this figure could be reduced at trial by four separate amounts.
13.Mr Bullett concedes that there are no particulars or further substantiation of this claim. However he submits (a) there will very probably be some further loss and expenses and (b) the triable issues thus far have reduced the plaintiff's O.14 claim from $3,331,953.44 to $235,341.62 which is likely to be reduced further. Therefore, unconditional leave to defend should be granted. 14.The plaintiff finally submits that the value of the variations carried out by the plaintiff under this sub-contract have plainly been undervalued. Therefore, there is a high likelihood of the sum due to it to being ultimately increased. This, submits Mr Shaw, would provide the court with some comfort if it were minded to make an interim payment over and above even the lowest figure conceded by the 1st defendant. Mr Bullett simply disagrees and says it is impossible for this court, on affirmation evidence, to make a final determination that the variations have been undervalued. 15.The legal principles to be applied to O.14 and O.29 applications are well settled. Suffice it to say, that for all the above reasons, the plaintiff has failed to reach the thresholds necessary to enable this court to make either of the orders it seeks. 16.I give the 1st defendant unconditional leave to defend with an order for costs in the cause.
Representation: Mr Geoffrey Shaw of Messrs Deacons, for the Plaintiff Mr Andrew Bullett, instructed by Messrs Tsang & Wong, for the 1st Defendant |