Fook Kwong Construction Co v. The District Officer Islands
Read the full judgment text of HCMP 131/1977 on BabelCite. This High Court CFI judgment was delivered on 8 February 1979.
1. By a contract in writing dated 3rd November, 1975 said to be in standard form the District Officer Islands on behalf of the Government employed the applicant to construct certain works to wit a 5-seater aqua privy at Ngau Au Village, Lantao, for the sum of $42,981.50.
|
HCMP000131/1977
Coram: Zimmern, J. Date of Judgment: 8 February 1979 ----------------- JUDGMENT ----------------- 1. By a contract in writing dated 3rd November, 1975 said to be in standard form the District Officer Islands on behalf of the Government employed the applicant to construct certain works to wit a 5-seater aqua privy at Ngau Au Village, Lantao, for the sum of $42,981.50. 2. The applicant took possession of the site, commenced work and sometime well before completion the Government terminated the contract, regained possession of the site and the applicant disputed the Government's right so to do. In accordance with the contract the dispute was referred to the decision of a single arbitrator. 3. In the Arbitration, pleadings were delivered the applicant contractor being the claimant and the Government the respondent. 4. It is common ground that the Government terminated the contract consequential on the applicant's alleged breach of Clause 19 of the Particular Specification for Construction which reads:
The applicant did not have a mixer on the site and mixed concrete by hand. It alleged three grounds in support of its claim that the Government's termination was wrongful:
It asked for damages for wrongful termination. 5. The Government denied the allegations and counterclaimed against the applicant in damages for breach of contract. 6. The Arbitrator heard the evidence of witnesses called by both sides and by his Decision dated 17th January 1977 found for the Government and awarded it damages and costs of the court proceedings and arbitration. 7. The applicant by motion has sought to set aside the award on the grounds:-
The motion was supported by an affirmation of the sole proprietor of the applicant firm exhibiting an order of Yang J. the pleadings before the Arbitrator and his Decision. 8. As to the first ground, counsel submitted that the Arbitrator did not deal with paragraph 8 of the particulars of claim which reads:
9. It is true that paragraph 8 was not specifically mentioned in the Decision but what he stated was this:
Counsel submitted that the Arbitrator was there only dealing with procedure and that submission to me was no more than a bit of utter pedantry. Furthermore the Arbitrator had said the District Officer was correct in insisting on a concrete mixer to be used. This ground fails. 10. As to the second ground I deal with (a) error of law last. The other two sub-grounds can be grouped together. I can see nothing and I have heard nothing which can justify a finding that the Arbitrator's conclusion under (b) and award of damages under (c) were bad on the face of the decision. This leaves the ultimate sub-ground (a). There is undoubtedly an error of law on the face of the decision for the Arbitrator had said:
11. The Arbitrator had obviously erred in thinking that waiver of one's right to insist on the precise mode of performance fixed by the contract was the same thing as variation of a contract. The former does not require to be in writing but the former under the contract was. His decision leaves one in the dark whether he had in fact applied his mind to the evidence if any on the point or whether he had disregarded the evidence if any because there was no written agreement to waive. The pleadings do not shed any light on what the applicant relied on to constitute waiver. It is just a bare allegation without particulars and reads as follows:
Counsel for the Government did not ask for them. I commented at the hearing that it was quite wrong for the parties to leave the Arbitrator completely in the dark as to the issue before him on this point. I asked counsel for the applicant whether he would supply me with the particulars which he ought to have pleaded in support of his contention of waiver. He was reluctant but did eventually supply them with a copy of a letter written by the District Officer to the applicant dated 4th March, 1976. I have read them but with or without them my conclusion would have been the same. I direct that the Decision be remitted back to the Registrar to consider and find:-
12. After the Arbitrator has dealt with this matter his finding will be added to his decision and referred back to the Court. Representation: Brian van Buuren (H.H. Lau & Co.) for Applicant. B. Barlow for Respondent. |