Schindler Lifts (Hong Kong) Ltd v. Shui on Construction Co Ltd
Read the full judgment text of HCA 2270/1984 on BabelCite. This High Court CFI judgment was delivered on 26 July 1984.
1. The Plaintiff in this matter, Schindler Lifts (Hong Kong) Limited, was the sub-contractor for the installation of lifts and escalators in a building situated on the corner of Harbour Road and Fleming Road for the erection of which the Defendant, Shui On Construction Company Limited, were the main contractors.
|
HCA002270/1984
BETWEEN
___________ Coram: Hon. Power, J. Dates of Hearing: 19 & 20 June 1984 Date of Delivery of Judgment: 26 July 1984 __________ JUDGMENT __________ 1. The Plaintiff in this matter, Schindler Lifts (Hong Kong) Limited, was the sub-contractor for the installation of lifts and escalators in a building situated on the corner of Harbour Road and Fleming Road for the erection of which the Defendant, Shui On Construction Company Limited, were the main contractors. 2. The Sub-Contract provided in clause 11(b):-
3. Part IV of the Appendix to the Sub-Contract provided "Terms of Payment as described in Specification Preliminaries page 25". These Specification Preliminaries provided under the heading "Terms of Payment" that -
4. Given the use of the words "Unless otherwise agreed" in this term, I do not see how it can, in any way, qualify or limit the force of clause 11(b). I am satisfied that if there is any inconsistency between this term and clause 11(b) then, it having been "otherwise agreed", clause 11(b) prevails. 5. The architect having certified for certain work and no payment having been made in relation thereto the Plaintiff now sues for the amount involved. The Defendant has not made payment in this regard because it has not received payment from the Employer. The Defendant has not received this payment because the Employer, acting under clause 22 of the Main Contract, has deducted sums from the amount certified for by the architect. Clause 22 of the Main Contract reads:-
6. The architect certified under that clause and the employer, relying upon that certification, retained money which would be otherwise due because of the certification given under clause 11(b) of the Sub-Contract. It is the contention of the Defendant that, as he has never been in "receipt.....of payment" he is not bound by the terms of clause 11(b) to pay anything to the Plaintiff. 7. There are two summonses before me. One is brought by the Plaintiff for judgment under 0.14 and the other is brought by the Defendant for a stay pursuant to s.6 of the Arbitration Ordinance. 8. I will deal firstly with the O.14 application. Under that application this Court must decide whether in the circumstances there is an arguable case that the Main Contractor, the Defendant, has not been in receipt of payment from the employer in accordance with the meaning of that term as it is used in clause 11(b) of the Sub-Contract. 9. Mr. Wong, who appeared for the Plaintiff, submitted, at the outset, that all of the relevant facts are before the Court and that we are here dealing with the kind of circumstances referred to in European Asian Bank v. Punjab and Sind Bank (1983) 2 All E.R. 508. In that case Robert Goff L.J. said:-
10. Clause 35 of the Main Contract provides that in case any dispute or difference shall arise between the employer and the main contractor it shall be referred to arbitration. It goes on to provide in sub-clause (2) that except in certain circumstances, which Mr. Wong argues do not obtain in the present circumstances, a reference to arbitration shall not be opened until after the practical completion of the work. Mr. Wong submits that the only exception that might have had application to the present circumstances is contained in the following words:-
11. He contends, however, that there is no question here of a certificate having been improperly withheld and that the Defendant has never suggested that the certificate was not been issued in accordance with the conditions of the Main Contract. 12. It was the argument of Mr. Wong that, whom an Architect's Certificate as to non-completion is given under clause 22, the main contractor, by virtue of that clause, becomes liable for the sums calculated in accordance therewith. Mr. Wong submitted that, the moment the certificate is given, the liability arises. The clause sets out three ways in which the laibility can be meet;
13. Mr. Wong submits that, the parties having agreed to this procedure, there can be no suggestion from the Defendant that the deduction made by the Employer in our case was not consensual. He submits that, as the Defendant has agreed that the Employer will have power to deduct if certain conditions are met, once those conditions are met, a deduction made by the Employer must be regarded as having been made with the consent of the Defendant. This would, of course, be so only if the conditions stipulated were met. It is one of the submissions of Mr. Walker, who appeared for the Defendant, that these conditions were not met and I will turn, in due course, to consider that submission. 14. Mr. Wong submits that, once the liability arises, it becomes a lawful contractual debt. It is, he argues, not material in an application of this nature that the main contractor might, at some later time when an arbitration can be opened, be entitled to challenge the validity of the certificate. He argues that, as the employer is entitled, by virtue of clause 22, to set off the amount due under that clause against the amounts being held by him, the Defendant cannot say that he has not "received payment" from the employer. Mr. Wong concedes that he has not received the payment of cash but argues, upon the authority of Larocque v. Beauchemin (1897) A.C. 358, that a set off is, in the eyes of the law, in circumstances such as this, equivalent to a payment in cash. In that case Lord Macnaghten cited the following passage, from Spargo's case, L.R. 8 Ch.407, with approval at 365:-
15. He submits that the deduction by the Employer was a set off which must be regarded as a payment in cash to the Defendant and that the Defendant has, therefore, no answer to a claim being made by a sub-contractor under clause 11(b). 16. Mr. Wong finally referred to the unreported decision of Hunter J. in Hong Kong Teakwood Works Ltd. v. Shui On Construction Co. Ltd., Civil Action No. 10969 of 1983. In that case the learned judge, dealing with the words which concern us in clause 11(b), said "I think that I must give those words their normal meaning. To me their normal meaning is receipt of actual payment, receipt of money. This seems to me to accord with the other phrases that one finds in these contracts. 'Pay or allow' is one in the main contract, paragraph 22, which is followed by the words 'the employer may deduct such sum from any monies due'. I think that all these words contemplate a simple piece of arithmetic, and that the prima facie meaning of receipt of payment is receipt of money." Having taken this view, the learned judge refused to give judgment under 0.14. Mr. Wong urged me not to take the same view and pointed out that Hunter J. had not been referred to Larocque v. Beauchemin. 17. Mr. Walker first argued that clause 11(b) has no application as no payment has ever been made. He pointed out that, both in the Main Contract in clause 27(vi) and in clause 22, and in the Sub-Contract in Clause 8(a), the draftsman had used the words "pay and allow". He submitted that this clearly indicated that when the draftsman used the word "pay" or "payment", as he did in clause 11(b), he did not intend to include the making of an allowance within the meaning thereof. He further argued that the meaning could not be extended to cover the making of a deduction. 18. It must be borne in mind, when considering the above there clauses, that in each case a right was being given either to the mail contractor or sub-contractor. In each case the main contractor or sub-contractor was being given the right to elect to either pay on make an allowance. Clause 11(b) is on the other hand not concerned with the giving of any right. It is concerned primarily with the fixing of a time within which payment must be made. It fixes this time by referring to the point when there has been a receipt of payment by the main contractor. I am satisfied that this is an important distinction and one that must be borne in mind when construing the meaning of the word "payment" in clause 11(b). 19. Under clause 22 the main contractor becomes liable for a sum of money. It is true that this liability can be met in any one of three ways, other by the main contractor paying or indicating that he is prepared to have an allowance made or by the employer simply making a deduction. Whichever method is used, the liability is removed and the main contractor is given credit for money's worth. 20. Mr. Walker went on to argue that, even if he was not right in his contention that there had been no payment, it was for the Plaintiff to establish that the set off was one to which the employer was entitled. He contended that, unless the Plaintiff showed that the employer was entitled to make the deduction, there could not be said to be any liability resting upon the Defendant and that, if there was no liability, it could not be said that there had been any receipt of payment by the Defendant under clause 11(b). 21. Mr. Walker referred to clause 35, the arbitration clause, arguing that Mr. Wong had been wrong when he submitted that the issue of an Architect's Certificate created a liability which was not open to challenge and which was, until after practical completion, a contractual debt which the main contractor was required to meet. He referred to the reservation in clause 35(2) which allowed a challenge to be made prior to practical completion when what was called in issue was "whether or not a certificate has been improperly withheld or is not in accordance with these conditions. He submitted that, where a certificate was challenged, as it was in the present case, the Plaintiff could only rely upon the validity of the certificate if he proved it was issued in accordance with the conditions. It was his submission that it was implicit in clause 22 that the certificate be a valid certificate, i.e. not simply in formal accord with the conditions but also valid, i.e. truthful, as to the matters dealt with therein. 22. Where is, in my mind, no doubt that the intention of clause 35 is to prevent multiple arbitrations. The section endeavours to ensure that, except in the circumstances specified, there will be only one arbitration and that this will take place after completion. It is true that if a certificate has been improperly withheld", an immediate challenge can be made. That this should be so is clearly right as, if certificates are improperly withheld, what Lawton L.J. in Ellis v. Wates (1976) 2 BIR 57 at 63 called "the lifeblood of the building trade, namely money" will not paid. 23. The certificate can also be challenged where it is "not in accordance with these conditions". Mr. Walker argues that this that a certificate can be challenged on the ground that it does not correctly state the position, i.e. that it is not true as to its contents. Is this correct? The words "is not in accordance with these conditions" must be looked at with particular care. Mr. Walker, referred to Building and Civil Engineering Standard Forms, 1st Edition, where the author, at 159, without citing any authority for the proposition, states that a reference to arbitration can be opened at any time before completion upon the basis that a certificate was not in accordance with the conditions where the only contest is as to a simple dispute of valuation. The author was, of cause, dealing there with certificates which certified as to amounts for payments. He was not referring to certificates issued under clause 22. Mr. Walker also referred to dicta of Viscount Dilhorne, in Gilbert-Ash (Northern) Ltd. v. Modern Engineering (Bristol) Ltd. (1974) A.C. 689 at 709. Viscount Dilhorne was, in this passage, also dealing with payment certificates, I do not consider that the above citations are of any real assistance when one is dealing with a certificate under clause 22 whatever may be the arguments to support the contention that payment certificates, if theyset out an incorrect figure, are not in accordance with the conditions, I am satisfied that the position, as regards certificates of non compliance, is as is set out hereunder. 24. The condition which Mr. Walker submitted that the certificate in the present case was "not in accordance with" was clause 22. His submission was that, because of what had occurred prior to the issue of the certificate, the real position was that time was at large and that the date of completion was no longer material. He submitted, that being so, that the Architect's Certificate saying that the works ought reasonably to have been completed by the date of completion did not correctly and truthfully state the position. He submitted that the Plaintiff could only succeed in this application if he showed that the Architect's Certificate was right and that, as the Plaintiff had not attempted to do so, he must fail. 25. Mr. Wong contends that the interpretation of the word "is not in accordance with these conditions" suggested by Mr. Walker is wholly incorrect. He submits that it need only be shown, in order to comply with the words, that the certificate has formally complied with the conditions, i.e. it must be shown, as regards Clause 22, that it is the certificate of the architect, that it is in writing, that it states the opinion of the architect and that the opinion is that the work ought reasonably to have been completed by the date of completion. Mr. Walker did not argue that the certificate was not in formal accord with the provisions clause 22. His argument, as set out above, was that the certificate had to be not only for dally correct, but also had to be a true statement of the facts contained therein. During the course of the hearing in front of he, an affidavit was filed by Mr. Walker to which was annexed a copy of a certificate dated the 2nd June 1984, certifying that practice completion of the whole of the works was achieved on the 1st March 1984. This does not, however, seem to me to affect the matter, as given the view I have taken above of the effect of the certificate of non-completion, the contractual debt arose at the time when that certificate was given and the fact that it can now, a certificate of practical completion having been issued, be challenged does not seem to me to be material. 26. The point involved in this application, although a short one, is not without difficulty. I am satisfied, however, that the present applicant has raised a clear out issue, that full argument has been addressed to the Court and that the only result of my not deciding will be that the case will go for trial and that the argument will be rehearsed all ever again before a judge with the possibility of another appeal. Suck being the case, I am satisfied, following the decision in the European Asian Bank case, that I should decide the matter in this hearing. I am satisfied that the meaning of the word "payment" in Clause 11(b) is wide enough to include a deduction made under Clause 22 of the Main Contract. I am satisfied that once a formally correct architect's statement has been issued under Clause 22, no challenge can be made thereto until after practical completion. I am satisfied, therefore, that in the present case, the Defendant did receive a payment within the meaning of that term as is used in Clause 11(b) and that he failed within 14 days to pay the sub-contractor the amount which is now being claimed against him. There must, therefore, be judgment for the Plaintiff in that amount. 27. I turn now to the application for a stay. Before me, the Defendant has not disputed that he owes the Plaintiff the amount claimed. The only dispute before me was as to a matter of interpretation affecting the time of payment which, I am satisfied, must be resolved in the Plaintiff's favour. 28. The only argument advanced by Mr. Walker when urging that a stay be ordered was upon the basis of the unreported decision in Northern Regional Health Authority v. Dereh Crouch Construction Co. Ltd. C.A. 2557 of 1983 which, he submitted, established that, if there was an arbitration clause and the parties take the matter to litigation, the Court does not have the power to open up and review the architect's certificate. That may be so but for the reasons which I have set out above, I am satisfied that no question of opening up and reviewing the architect's certificate arises in the present case. 29. Mr. Wong on the other hand relied on the following statement in Keating on Building Contracts, 4th Ed., at p.242:-
30. The learned author goes on to discuss various matters which will be considered when the Court is determining whether or not to exercise its discretion and at p.243, the following passage appears:-
31. Authority for the proposition that the Court may refuse a stay where the only point alleged is one of law is Bristol Corporation v. Aird (1913) A.C.241. In that case Lord Parker said at p.261:-
32. It is true that this passage has been subjected to modifying comment in later cases. In Metropolitan Tunnel and Public Works, Limited v. London Electric Railway Company (1926) 1 Ch. 371 at p.386 Lord Hanworth N.R. said:-
33. In that case the majority upset the decision of Lawrence J. who had exercised his discretion by refusing to grant a stay. However the words of the Master of the Rolls, cited above, make it clear that there was "the possibility of a number of engineering questions arising". That being so, there were clearly circumstances which indicated the desirability of referring the matter to an arbitrator with specialized knowledge. 34. In Heyman and Another v. Darwin, Limited (1942) A.C. 356, Viscount Simon L.C. said :-
35. Lord Wright, at p.389, also referred to the statement of Lord Parker saying:
36. As can been seen the dictum of Lord Parker has not escaped unscathed down the years and I bear in mind the reservations set out above when coming to my decision herein. 37. I am satisfied, in the present case, that there is nothing that calls for the specialized knowledge of an arbitrator. I bear in mind also there has never been any issue raised as to the entitlement of the Plaintiff to be paid. The only issue is whether the Plaintiff should, because of a dispute between the Employer and the Main Contractor, with which he is wholly unconnected be, for the time being, kept out of his money. I am satisfied that, in all of the circumstances, the Plaintiff has discharged the burden of showing why he should not be bound by his agreement and I refuse to order a stay. I make an order nisi that the Defendant pay the Plaintiff's costs of both applications to be taxed.
Representation: Messrs. Ronny Wong (Deacons) for Plaintiff Messrs. A. Walker of Levell, White & King for Defendant | |||||||||||||||||||||||||||||||