Wong Hung Chun and Another v. Tsao Chin Lan
Read the full judgment text of DCCJ 4386/2002 on BabelCite. This District Court judgment was delivered on 7 January 2004.
1. The Plaintiff claims against the Defendant for $176,979.00 being the balance of the decoration and renovation services rendered by the Plaintiff to the Defendant at apartment D804, 8th floor, Block CD of Oriental Garden. The said sum was pursuant to an agreement dated 18 November 1998 and additional work less cancellation of certain items.
|
DCCJ004386/2002 DCCJ4386/2002 IN THE DISTRICT COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION CIVIL ACTION NO. 4386 OF 2002 --------------------
--------------------- Coram: His Honour Judge Wong in Court Dates of Hearing: 3, 4, 5 & 8 December 2003 Date of Handing Down Judgment: 7 January 2004 _______________________ JUDGMENT _______________________ The Plaintiff's claim 1.The Plaintiff claims against the Defendant for $176,979.00 being the balance of the decoration and renovation services rendered by the Plaintiff to the Defendant at apartment D804, 8th floor, Block CD of Oriental Garden. The said sum was pursuant to an agreement dated 18 November 1998 and additional work less cancellation of certain items. Defence and counterclaim 2.The defence is that the Plaintiff was in breach of the agreement in that
3.The Defendant counterclaims the following items:-
The Plaintiff's case 4.The Plaintiff's case is that the Plaintiffs entered into a written agreement dated 18 November 1999 in which the Plaintiff undertook decoration and renovation work for the Defendant at $370,000 to be paid in 4 instalments. The 1st and 2nd instalments in the sums of $111,000.00 & $86,334.00 had been paid. The Plaintiff now claims the 3rd and 4th instalments of $86,334.00 each totalling $172,668.00. 5.After commencement of work there were variations to the agreement in that there were the following additional works:-
And the following deductions:-
6.The Defendant has therefore to pay an extra of $(20,650 - 19,337) = $1,313 7.The Plaintiff further claims $3,000 being the balance of the money paid by the Defendant for use of enamel paint instead of emulsion paint particulars of which are as follows:-
The Defendant's case 8.The Defendant agreed that she had entered into the said agreement and that the Plaintiff agreed to complete the work by 18 January 1999. But the Plaintiff did not finish work in time hence the Defendant had to rent a flat until 31 March 1999. 9.The Defendant further called the Surveyor to support her claim. THE ISSUES 10.The issues are simply that on finding of fact which items the parties were entitled to claim and if so what is the reasonable amount.
11.The agreed contract sum is $370,000. 12.The Defendant has paid the Plaintiff the 1st instalment in the sum of $110,000, 2nd instalment in the sum of $86,334 another sum of $33,600, less deduction of certain items in the contract in the sum of $19,337.00. The Defendant has to pay an extra sum of $6,240 being addition work for flower-bed. 13.The Defendant subject to counterclaim is liable to pay the Plaintiff $370,000 - 110,000 - 86,334 - 33,600 - 19,337 + 6,240 = $126,969.00. The Defendant's counterclaim 14.The Defendant has filed a surveyor's report in respect of the Plaintiff's defective works. The investigation by the surveyor is of microscopic detail. Some items were cancelled by the Defendant before the work started. Although the surveyor had given a break down figure for carrying out the individual items of remedial work but most of the items had been used by the Defendant and many items have minor defects and the estimation or breakdown figures are unreasonable.
15.There is no evidence of the Plaintiff having overcharged in respect of the front door. 16.Apart from that I also allow the Defendant's claim in respect of $780 for handles, $1,085 for locks, 94 for hinges, $68 for shringes, totalling $2,027. 17.In the premises I find that the Defendant is entitled to counterclaim
18.In the premises I give judgment for the Plaintiff in the sum of $126,969 and judgment for the Defendant in respect of the counterclaim in the sum of $151,027. Interests in respect of the Plaintiff's claim and the Defendant's counterclaim at 1% above prime rate per annum. 19.Order nisi : costs to the Plaintiff in respect of the Plaintiff's claim and costs to the Defendant in respect of the Defendant's counterclaim
Representation: Miss Hui Ying Ying instructed by Messrs. C.H. Chan & Co. for Plaintiff. Mr. Wong Colin instructed by Messrs. W.S. Szeto & Lee for Defendant. |
Further hearings and rulings under DCCJ 4386/2002