Tsang Yuk Ching t/a Tsang Ching Kee Eng Co v. Fu Shing Rush Door Joint Venture Co Ltd
Read the full judgment text of HCA 987/2003 on BabelCite. This High Court CFI judgment was delivered on 5 September 2003.
1. The plaintiff is suing the defendant for $1,182,703 being the balance of payments due to it for steel frame work done on a building project known as the Science Park at Pak Shek Kok. The defendant was a 3rd sub-contractor, and the plaintiff was a 4th sub-contractor in a contractual chain headed by the Architectural Services Department. The main contractor was Hong Kong Construction (Holdings) Ltd. Neither party to this action was a nominated sub-contractor.
|
HCA000987/2003 HCA987/2003 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO. 987 OF 2003 ---------------------
------------------- Coram: Hon Burrell J in Chambers Date of Hearing: 2 September 2003 Date of Decision: 5 September 2003 --------------------- D E C I S I O N --------------------- 1.The plaintiff is suing the defendant for $1,182,703 being the balance of payments due to it for steel frame work done on a building project known as the Science Park at Pak Shek Kok. The defendant was a 3rd sub-contractor, and the plaintiff was a 4th sub-contractor in a contractual chain headed by the Architectural Services Department. The main contractor was Hong Kong Construction (Holdings) Ltd. Neither party to this action was a nominated sub-contractor. 2.The defendant seeks a stay of these proceedings for the purpose of having the disputes settled by arbitration. The plaintiff opposes on the basis that the written sub-contract between them contains no specific arbitration clause. The main contract does however contain a standard valid arbitration clause. The issue is whether or not that arbitration clause is incorporated into the sub-contract between these two parties. 3.There is no challenge to the fact that there is a dispute between the parties; also, it is accepted that the arbitration clause in the main contract is not null and void, inoperative or incapable of being performed and would therefore trigger a mandatory stay by virtue of section 6(1) of the Arbitration Ordinance and Article 8 of the Uncitral Model Law, were it incorporated into the sub-contract. The sub-contract 4.The written Chinese sub-contract contains the following clause 3 (English translation) :
5.It is not disputed that Contract No. SSH363 includes Special Conditions of Contract Clause 81 (an amendment of the General Conditions of Contracts) sub-clause 14 of which is a standard arbitration clause. 6.The defendant submits that on a proper construction of clause 3 above, the parties bound themselves to the arbitration provision in the main contract. The defendant also relies on Article 7(2) of the Model Law which states as follows :
7.Quite simply, the defendant submits, the sub-contract contains a reference to the main contract which contains the standard arbitration clause. Conclusion 8.Before the parties can be bound by the arbitration clause in the main contract, the reference to it (by virtue of the reference to the main contract in the sub-contract) must be construed as an incorporation of the arbitration clause into the sub-contract. 9.The following factors combine to satisfy me that clause 3 is to be construed so as to bind the parties to the main contract arbitration provision :
10.I therefore grant the stay sought by the defendant pursuant to its summons dated 14 April 2003 together with an order for the costs of and occasioned by the summons.
Representation: Miss Rosanna Ng of Messrs Huen & Partners, for the Plaintiff Mr Lam Kin Hung of Messrs K.H. Lam & Co., for the Defendant |