Chun Wo Foundations Ltd v. Bpl (HK) Private Ltd
Read the full judgment text of HCCT 59/2002 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 13 February 2003 before Recorder J Leong, SC in Chambers.
Construction Law — Arbitration — 'Pay when paid' clause — Interpretation of contract terms — Application for leave to appeal arbitration award — Stringent test for leave to appeal under Arbitration Ordinance s.23(3)(b). The Applicant subcontracted foundation works to the Respondent with a contract containing 'pay when paid' provisions requiring payment to the subcontractor within 14 days of the Contractor receiving payment from the Employer. Disputes arose relating to alleged repudiation and wrongful termination. The Arbitrator upheld the Respondent's position, finding the Applicant in repudiatory breach and interpreting the payment provisions as 'pay when paid' relating both to timing and amount, disallowing Applicant's set-off claims. The Applicant sought leave to appeal, arguing errors in interpretation and law. The Court emphasized the strong presumption of finality in arbitration, particularly in one-off contractual disputes, applying principles from The Nema, The Antaios, and PT Dover decisions. The Court concluded no clear or obvious error existed in the Arbitrator's factual or legal findings, and the Applicant failed to meet the high threshold for leave to appeal. Leave was refused, and costs awarded to the Respondent.
Legal issues: Leave to appeal on arbitration award
Outcome: Application for leave to appeal refused; costs awarded to Respondent
|
HCCT000059A/2002 HCCT 59/2002 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION & ARBITRATION PROCEEDINGS ___________
____________
_____________ Coram: Recorder J Leong, SC in Chambers Date of Hearing: 19 December 2002 Date of Handing Down Judgment: 13 February 2003 _______________ J U D G M E N T _______________ 1.By a re-amended Notice of Originating Motion dated 6 June 2002 the Applicant applied under section 23(2) of the Arbitration Ordinance, Cap. 341 ("the Ordinance") to set aside an arbitration award made on 17 May 2002 by Mr. Anthony Houghton. The Applicant sought leave to appeal under section 23(3)(b) of the Ordinance. 2.The arbitration concerned a contract between the Applicant and the Respondent to build foundation work ("the Contract"). 3.The Kowloon-Canton Railway Corporation engaged the Chun Wo-Fujita-Henryvicy Joint Venture ("the Joint Venture") to construct Tin Shui Wai Station. The Applicant was a sub-contractor to the Joint Venture, having been engaged to construct foundation works for the project. 4.The Applicant then engaged the Respondent as its sub-contractor (i.e. sub-sub-contractor to the Joint Venture) to undertake part of those foundation works by the Contract in December 1999. The Contract was based substantially upon the Applicant's standard form of contract but was varied in several respects by agreement, of which particulars are set out under 8 below. 5.Disputes arose between the Applicant and the Respondent as to inter alia the quantity and quality of work done by the Respondent. The Respondent left the site on 29 September 2000 before completion of the work. The Respondent alleged that the Applicant had repudiated the Contract and accepted the repudiation. The Applicant alleged that the Respondent had wrongfully terminated the Contract. The dispute was referred to arbitration as provided for in the Contract. 6.By agreement between the parties, Mr Anthony Houghton, a barrister and chartered quantity surveyor, was appointed to arbitrate the dispute ("the Arbitrator"). 7.The Interim Award and Reasons for Award were issued on 17 May 2002. 8.The Contract contained specific terms as to payment by the Applicant to the Respondent of the contract sums. Those terms, some of which, were supplemental to those appearing in the Applicant's standard form of contract, were set out in the following parts of the Contract:-
9.The Applicant claimed these to be standard terms known as "pay when paid" provisions in the industry. The Respondent claimed that they were not and that they differ in substantial respects from such standard clauses. 10.It is apparent from:
11.The Arbitrator found in favour of the Respondent on the "pay when paid" issues and found the Applicant to have been in repudiatory breach of the Contract. 12.On those issues, the Applicant's grounds of appeal are that:-
13.It was submitted on behalf of the Applicant that although the matters raised by Paragraph 1(3) - (11) of the re-amended Notice of Originating Motion may fall outside the ambit of matters of general and public importance, leave should nevertheless be granted to pursue such grounds in the appeal. 14.Leave is required to appeal against an arbitration award - section 23(3) of the Ordinance. The test of whether leave should be granted is stringent. Where parties decide to submit to arbitration, they must bear the consequences of that choice and any intervention by the courts should only be in exceptional and minimal circumstances. The presumption that the parties desire finality by arbitration should be upheld. Pioneer Shipping Limited v. BTP Tioxide Limited ("The Nema") 1982 AC 724 Antaios Compania Narvera SA v. Salen Rederierna AB ("The Antaios") 1985 AC 191 Lee Chang Yung Chemical Industry Corp v. PT Dover Chemical Co. ("PT Dover") 1990 1 HKC 132 Section 2AA of the Ordinance 15.The presumption of finality in arbitration is measured on a spectrum or sliding scale, the high point being one-off situations and the lowest point being situations that are commonplace or are of general public importance. 16.The test is much higher for cases falling within the one-off situation. In The Nema (supra) Diplock LJ said at 742H - 743A:
This was re-affirmed in the Hong Kong case of PT Dover (supra) at 140 A-E as follows:-
In the simpler and more homely language of Lord Donaldson in The Kelaniya at p. 32:
17.In cases falling within the lower end of the spectrum, the presumption is far less and the court takes a more lenient view. In The Nema (supra) it was said at 743D that:
and at 743F:
This was confirmed in The Antaios (supra) at 203G-H and dealt with at some length in PT Dover (supra) at 140F:
But the Court was careful to caution that there are clear limitations to this exercise at 140I:
The Applicant's submission that a definitive judgment on "pay when paid" clauses in construction contracts is important for the industry generally and has long been called for in cases before the courts, must be seen against that warning by Hunter JA. 18.Paragraphs 1(1) and (2) of the re-amended Notice of Originating Motion are relevant to the application for leave to appeal. They deal with the "pay when paid" provisions of the Contract and, in my judgment, are the only grounds of appeal that fall for proper consideration in a leave application. The other grounds deal with factual issues arising out of the first two grounds e.g. paragraphs 1(3) and (4) depend upon whether the Applicant succeeds on its "pay when paid" argument, and paragraphs 1(4A) and (4B) depend upon whether the Applicant fails on that argument. 19.The Applicant contends that:-
20.It was not in dispute that the Applicant had received payment from the Joint Venture in respect of work done by the Respondent. The Applicant set-off from that sum amounts which it claimed represented loss caused by the Respondent's failure to fulfill its obligations under the Contract. The Applicant then paid the balance to the Respondent. 21.The Respondent claimed that:
The Applicant claimed that it was entitled to make relevant deductions and that the "pay when paid" provisions related to time but not amount. The Arbitrator found in favour of the Respondent. 22.The Respondent produced at the hearing of the leave application the industry's printed standard form of building contract for Hong Kong between contractors and sub-contractors. Clause 11(b) deals with interim payments to sub-contractors. Whilst the language is not identical to the terms in 8 above, the terms are very similar (but not identical to) the terms of Clause 11.3 and the Sixth Schedule of the Contract. But the Applicant's contention that the terms of the Contract entitled it to make the deductions that it did, in my judgment, clearly extended the ambit of interpretation of the terms to include the right of set-off. In so doing it seeks to upset the Arbitrator's findings of law and fact. In my judgment this brings the issues squarely within the "one-off" situation and therefore puts them at the higher end of the spectrum. 23.Applying the principles on that basis in The Nema (supra) and PT Dover (supra), I am not satisfied:
In my judgment, the Applicant, therefore, fails to meet the threshold requirements for leave to appeal. 24.Even if I were satisfied that the matter fell purely within the ambit of construction of a standard term contract where less strict criteria apply to lower spectrum situations, "leave should only be granted if a strong prima facie case of error is made out" - PT Dover at 141C. 25.It was submitted on behalf of the Respondent that the Arbitrator had open to him four potential interpretations of the relevant provisions of the Contract (paragraph 8 of the Skeleton Submission on behalf of the Respondent). I agree and I am unable to conclude for the purposes of this application that these are without merit i.e. "leave should not be given ...... unless the judge considered that a strong prima facie case had been made out that the arbitrator had been wrong in his construction" - The Nema (supra) at 743F. 26.In low spectrum cases involving standard form contracts and/or commonplace disputes the expertise of the arbitrator may be relevant to considerations of the applicable scale level for consideration. In this case, the Arbitrator was a barrister and chartered quantity surveyor with extensive arbitration experience who was chosen and agreed upon by the parties. 27.In my view there is no basis upon which to grant leave to appeal and the application is therefore refused. 28.I make an order nisi for the costs of the application to the Respondent.
Representation: Mr M Thomas, SC and Mr J Harris instructed by Messrs Lovells for the Applicant Messrs Deacons (G. Shaw) for the Respondent |
Further hearings and rulings under HCCT 59/2002