Hero Profit Enterprises Ltd v. Kadesy Development Ltd and Others
Read the full judgment text of HCMP 790/1995 on BabelCite. This High Court CFI judgment.
1. By a Sale and Purchase Agreement dated 3rd June 1994 ("the Agreement"), the premises on the 23rd Floor ("the Property") of the yet to be constructed building to be known as King Kong Commercial Centre ("the Building") was agreed to be sold by the Defendants as Vendor to the Plaintiff as Purchaser for the price of $69 million. The Property is to be part of a building to be constructed. Under Clause 3.1.3 of the Agreement, the Vendor has an obligation to complete the Building on or before the 3
|
HCMP000790/1995
-----------------
-----------------
----------------- Coram: The Hon. Mr. Justice Waung in Court Date of Hearing: 29th June 1995 Date of Handing Down of Reasons for Judgment: 10th July 1995 --------------------------------------------------- REASONS FOR JUDGMENT --------------------------------------------------- 1. By a Sale and Purchase Agreement dated 3rd June 1994 ("the Agreement"), the premises on the 23rd Floor ("the Property") of the yet to be constructed building to be known as King Kong Commercial Centre ("the Building") was agreed to be sold by the Defendants as Vendor to the Plaintiff as Purchaser for the price of $69 million. The Property is to be part of a building to be constructed. Under Clause 3.1.3 of the Agreement, the Vendor has an obligation to complete the Building on or before the 31st day of October 1995. Under Clause 4.1 of the Agreement completion of the purchase was to take place:-
By Clause 15, time was made in every respect of the essence of the Agreement. By First Schedule Part 3 of the Agreement, the Purchaser was required to make the 4th Part Payment in the sum of $2,761,728.00 on the 6th of February 1995. By Clause 16 of the Agreement, upon failure to make payment in accordance with Part 3, the Vendor is given the right to serve a notice on the Purchaser to make good the payment default and the right 21 days after such notice to terminate the Agreement. 2. The chronology of what then happened is briefly as follows:-
3. At the hearing before me, Mr. Warren Chan, Q.C. for the Defendant took a preliminary point by raising two issues, namely:-
4. In support of his two issues of preliminary point, Mr. Chan put forward 6 propositions of law which are applicable to this case:-
5. These 6 Propositions of Mr. Chan were expressly agreed to be correct by Mr. Alan Leong for the Plaintiff who quite properly even in the course of the submissions of Mr. Chan informed the Court that these Propositions were all accepted to be correct. 6. The importance of these Propositions is that this is a case where the time for answering requisitions had not expired when the Plaintiff issued the present application. The evidence shows that both parties knew that completion was going to be many months away and there was no evidence that in March 1995 the Plaintiff believed or asserted that completion was going to be imminent. 7. The essence of Mr. Chan's case is that the Court should only entertain the Summons whether requisitions have been sufficiently answered when either an answer had been given and the time for answering requisition had expired or that the time for answering requisitions had not yet expired but the vendor informed the purchaser that he was not going to improve the answer or to anything further. At the time of the issue of this Summons, on any view, it cannot be argued that time for answering requisitions had expired or that there was an incurable defect of title. The Vendor had not told the Purchaser that he could not or would not do anything before completion and it cannot be doubted that there were still many months before completion. The evidence in fact shows that the Vendor expressed every willingness to do anything it could to give proof if only it knew what were the specific queries raised by the Purchaser. The argument of Mr. Chan on the first issue is that the Court should not in these circumstances entertain the Originating Summons as it was premature. 8. On the second point, the case of the Defendant is that it was common ground that the Agreement had been discharged by reason of Purchaser's default in making the February payment. This being so and in the light of the concession by Mr. Leong, there was no contract left. In any event this had nothing to do with title. In the circumstances. it would be a waste of time to go into the question as to whether the answers given were sufficient. 9. These submissions of Mr. Chan are logical, powerful and unanswerable and in fact there was practically no answer from Mr. Leong. In a submission which took no more than 3 minutes and touching only on the first issue. Mr. Leong sought to say his case is more like A-Mayson. It was then pointed out to Mr. Leong by the Court that in A-Mayson, because of the 6 days left before completion, the purchaser terminated the contract on the ground of bad title, but this did not happen here and there was no termination by the Plaintiff. Mr. Leong had no answer to this and said he had nothing further to advance. The case of the Plaintiff collapsed and Mr. Chan was accordingly not called upon. 10. This is yet another chapter in the still unfolding story of the recent collapse of the property market in Hong Kong. It is clear in this case that the Purchaser had let the 6th February 1995 slip by without making the required payment. This is at a time when it had not even raised any requisition. On 3rd March 1995 when being pressed for payment and upon being served the notice to make good the default, the Purchaser served the unusually elaborate 19 page requisitions, perhaps in the hope that an escape could be found with these requisitions. The ridiculously short 7 day time limit to answer the requisitions, when construction work was still going on and a completion date was nowhere in sight, could only reinforce the inference that the Plaintiff was looking for a way out. 11. The only way out however had to be paid for, if the Plaintiff wanted to remain a player in the game so to speak. The Plaintiff had to pay the 4th instalment. This it did not do and after the 21 day notice period had elapsed, the Vendor as it was quite entitled to do terminated the Agreement. There was therefore nothing left for the Plaintiff or for the Court. The second issue of Mr. Chan is really wholly unanswerable and Mr. Leong, very sensibly did not even make an attempt to do so. I have no doubt that the Vendor was entitled to terminate the Agreement and in the circumstances, accepting wholly as I do the submissions of the Defendant, it is right and proper that I dismiss the Originating Summons with costs.
Representation: Mr. Alan Leong instructed by Messrs Vivien Chan & Co. for the Plaintiff Mr. Warren Chan, Q.C. and Miss Alice Mok instructed by Messrs Livasiri & Co. for the Defendants. |