Swire Engineering Services Ltd. v. Hip Hing Construction Co. Ltd.
Read the full judgment text of HCCT 32/1996 on BabelCite. This HIGH COURT judgment was delivered on 30 July 1996 before The Hon. Mr. Justice Keith in Chambers.
Contract law – Construction sub-contract – Default judgment – Alleged agreement to stay contingent on payment – Effect of contemporaneous correspondence showing payment pre-condition – Clarification of terms of stay agreement – Sub-contract clauses – 'Pay when paid' clause (cl. 22) overridden by special condition setting payment stages – Liability to pay retained sums without employer's certification or release – Non-binding architect's determination on withholding payments – Variation works assessment – Absence of evidential basis for revised sum – No defence with real prospect of success – Application to set aside judgment dismissed. The defendant main contractor, Hip Hing Construction Company Limited, engaged Swire Engineering Services Limited as sub-contractor. Swire claimed unpaid sums, obtained default judgment; Hip Hing sought to set aside on grounds of irregularity based on stay agreement. Court found stay agreement was contingent on payment not made, so judgment regular. Defendant's reliance on a 'pay when paid' clause was rejected as overridden by a special condition regarding payment stages. Defences to withholding retained sums and dispute on variation works payments lacked evidential support and real prospects of success. Application to set aside default judgment dismissed by The Hon. Mr. Justice Keith in chambers on 30 July 1996.
Legal issues: Validity of judgment in default given alleged agreement to stay proceedings · Effect of 'pay when paid' clause in sub-contract on payment obligations · Liability to pay retained sums pending certification or release from employer · Defences related to variation works payment sum of $108,800
Outcome: Application to set aside judgment dismissed; default judgment stands
|
HCCT000032/1996 1996 No.Con.32 IN THE SUPREME COURT OF HONG KONG HIGH COURT ____________
____________ Coram: The Hon. Mr. Justice Keith in Chambers Date of hearing: 30 July 1996 Date of delivery of judgment: 30 July 1996 _______________ J U D G M E N T _______________ INTRODUCTION 1. The Defendant, Hip Hing Construction Company Ltd. ("Hip Hing"), were the main contractors for the construction of Times Square. It engaged the Plaintiff, Swire Engineering Services Ltd. ("Swire"), as sub-contractors to supply generators for the project. Swire claims that various sums due to it from Hip Hing under the sub-contract are still outstanding. It issued proceedings against Hip Hing for their recovery. No defence was filed, and Swire entered judgment in default for the sums claimed. Hip Hing now applies for the judgment to be set aside. WAS THE JUDGMENT IRREGULAR? 2. Hip Hing maintains that the judgment was irregular because it was entered in breach of an agreement between Mr. Richard Clement, a solicitor with W.K. To & Co. who were instructed by Hip Hing, and Mr. Gilbert Kwok, a solicitor with Simmons & Simmons who were instructed by Swire. According to an affidavit sworn by Mr. Clement, the agreement was that the action would be stayed, but that it could be reactivited by either party giving 7 days' written notice to the other. No such notice had been given. 3. In determining whether the judgment was irregular on that ground, I am faced with three problems:
4. If the evidence is anything to go by, the competing versions of the additional term relating to the payment of the sum of $594,025.00 are these. Swire maintains that it was agreed that the action would be stayed only when it had actually been paid the sum of $594,025.00. Since Swire had never been paid that sum, the action had never been stayed. Hip Hing maintains that the payment of the sum of $594,025.00 was not a pre-condition of the stay. The stay was agreed because Swire knew that the sum of $594,025.00 was going to be released to it. 5. What Hip Hing maintains the agreement was is not borne out by the contemporaneous correspondence. The sequence of events which the correspondence reveals is as follows:
6. There has today been a shift in Mr. Clement's position. He now accepts that the express terms of the agreement were that the action would only be stayed once Swire had received the sum of $594,025.00. He asserts, however, that it was "understood" that no steps would be taken by Swire in the action in the meantime. I have not seen any basis for implying into the agreement such a term. Mr. Kwok told me that it had not been his understanding. If that had been Mr. Clement's understanding, he would not have allowed Simmons & Simmons' notice under Ord. 19 r.8A of 12th July (which is date-stamped as having been received by W.K. To & Co. on 13th July) to go unanswered. His letter of 15th July would have added that entering judgment in default would have been contrary to what had been the common understanding of his conversation with Mr. Kwok on 27th June. 7. For these reasons, therefore, the agreement to stay the action had not taken effect by 18th July when the judgment in default was entered, because the sum of $594,025.00 had not been paid to Swire. The judgment, therefore, was a regular one. THE SUMS CLAIMED BY SWIRE 8. Swire claimed two sums from Hip Hing:
HIP HING'S PRIMARY DEFENCE 9. Hip Hing's primary defence to these claims is that this was a "pay when paid" sub-contract. Cl. 22 of the sub-contract provided that Hip Hing's obligation to pay the sums due to Swire, including the sums retained by Hip Hing, only arose when Hip Hing had been paid by the employer. Hip Hing claims that the employer had not yet paid to it either of the sums claimed by Swire. However, cl. 22 does not lie easily with a special condition which was agreed between Swire and the architect on behalf of Hip Hing during the tendering stage. That special condition laid down the stages for the payment of sums due under the sub-contract. It did not state that these stage payments would not be made until Hip Hing had been paid the relevant sums by the employer. 10. Mr. Anthony Houghton for Hip Hing argued that these provisions could be reconciled with each other on the basis that cl. 22 related to payment, whereas the special condition related to the certification of the work done for the purposes of payment. I do not think that that argument has a real prospect of success. The language of the special condition is not consistent at all with its subject-matter being concerned only with certification. 11. The only other question, therefore, is whether Hip Hing's argument that cl. 22 overrides this special condition has a real prospect of success. I do not think that it does. It is true that the sub-contract which contains cl. 22 was concluded well after the agreement of the special condition at the tendering stage, but cl. 1(1) of the sub-contract provided that any special conditions were included in the sub-contract. Unless a contrary intention is apparent, special conditions, especially those expressed in language selected by the parties, override conditions in a standard form. No such contrary intention is apparent, and it follows that the provision in the sub-contract making it a "pay when paid" sub-contract was superseded by the special condition. Hip Hing's primary defence, therefore, does not have a real prospect of success. HIP HING'S OTHER DEFENCES TO THE CLAIM FOR $637,500.00 12. Hip Hing denies that it is liable to pay Swire the sums retained on three further grounds:
HIP HING'S OTHER DEFENCES TO THE CLAIM FOR $108,800.00 13. Hip Hing denies that it is liable to pay the sum of $108,800.00 to Swire on two further grounds. First, although the sum of $108,800.00 represented the sum originally assessed by the architect as due to Swire for variation works, the architect has had second thoughts on the matter since the issue of these proceedings. The architect now assesses the variation works in the sum of $56,825.00 only. No evidence has been filed as to the basis upon which the architect has changed its view. In the absence of such evidence, it is simply not possible for me to say that Hip Hing has a real prospect of success in establishing that the original assessment of $108,800.00 was erroneous. Secondly, Mr. Houghton argued that cl. 22 of the sub-contract prevented Swire from claiming the sum of $108,800.00 until Hip Hing had been paid that amount by the employer. I do not think that that argument has a real prospect of success. If cl. 22 applied to the variations, then in my view so too did the special condition. CONCLUSION 14. For these reasons, none of the defences which Hip Hing claims to have have a real prospect of success. It follows that its application to set aside the judgment must be dismissed.
Representation: Mr. Gilbert Kwok, of Messrs. Simmons & Simmons, for the Plaintiff Mr. Anthony Houghton, instructed by Messrs. W.K. To & Co., for the Defendant |