Leon Engineering & Construction Co Ltd v. Ka Duk Investment Co Ltd
Read the full judgment text of HCA 7588/1983 on BabelCite. This High Court CFI judgment.
1. This matter arises out of a building contract dated August 18, 1982, pertaining to the construction of the basement of an hotel in Shatin.
Cited by 1 case
|
HCA007588/1983 1983, No. A7588 ----------------------- H E A D N O T E ------------------------ Where, first, there is adequate machinery under the contract between the employer and a contractor to enforce the contractor's rights thereunder and, secondly, there is no good reason at tender stage to suppose that such rights and machinery would not together provide the contractor with an adequate remedy, then, in general, a certifying architect or engineer does not owe to the contractor a duty in tort coterminous with the obligation in contract owed to the contractor by the employer. 1983, No. A7588 IN THE SUPREME COURT OF HONG KONG HIGH COURT ------------------ BETWEEN
------------------- Coram: Bokhary, J (Hearing in Chambers; delivery of judgment in open court at the request of the parties) Dates of hearing: June, 5-6, 1989 ----------------------- J U D G M E N T ------------------------ 1. This matter arises out of a building contract dated August 18, 1982, pertaining to the construction of the basement of an hotel in Shatin. 2. The Plaintiff - a company now in liquidation - was the Main Contractor. In 1983 it commenced the present action against the Employer, the patty with whom it entered into the contract, a bilateral one. Now it seeks to join - as a second defendant - the Architects, who were nominated by the Employer under the contract but are not themselves party thereto. 3. Such joinder is the principal thing with the Main Contractor seeks to achieve by its summons dated March 16, 1989, which comes before me as a result of it having been adjourned by the Master to a Judge in Chambers. 4. It is in the tort of negligence that the Main Contractors propose to sue the Architects. The case it seeks to make against them is, shortly stated, as follows: They, as the certifying architects under the contract, owed it a duty of care to give proper, timely and impartial consideration to its claims, and to issue all certificates in strict accordance with the terms of the contract. But they negligently failed to perform that duty. And, as a result, it has been kept out of moneys to which it was and remains entitled. 5. The contract, I should mention, incorporated the conditions of the Stardard Form of Building Contract Private Edition with Quantities 1976 Edition (May 1979 Revision). 6. Mr Scott, who appears on behalf of both the Employer and the Architects, opposes the application for joinder on the ground that the Architects did not owe the Main Contractor the duty which is essential to liability in the tort of negligence. He relies first and foremost on the recent decision of the Court of Appeal in Pacific Associates v Baxter [1989] 2 All E R 159. The ratio of the case, as stated in the headnote (at p 159f-h) is that:-
To this statement must be added the caveat that it remains necessary to consider the actual terms and surrounding circumstances of the contract in each case. That is not to deny the wide implications of the decision. This is how Ralph Gibson, L.J. put it (at p 183b-e):-
7. The case arose out of a contract for certain dredging and reclamation work in Dubai. Under the contract between the employer and the contractor be latter, would only be paid sums on account when they were certified by the engineers retained by the former. The contract also provided that the contractor would be entitled to additional payment if in the course of dredging it encountered hard material not reasonably foreseeable by even an experienced contractor. The repeated claims for such additional payments made by the contractor in the course of the work were consistently rejected by the engineers on the ground that the hard materials encountered were reasonably foreseeable. Eventually, the contractor sued the engineers alleging that they had acted negligently, or were in breach of their duty to act fairly and impartially in administering the contract, by their continual failure to certify its claim for additional payments for hard materials and their final rejection ion of those claim. The issue whether or not the contractor could recover damages from the engineers assuming the facts pleaded by the former was tried as a preliminary issue. The Official Referee decided the issue against the contractor and struck out the claim. His decision was upheld by the Court of Appeal. 8. The basis of the Official Referee's decision is the negative answer he gave to the question he set for himself as to "... whether it accords with good sense for the law to interest in a commercial relationship like this to impose on the agent of one party to the contract a duty of care towards the other party to the contract in respect of administrative acts for the consequences of which its principal would in any case be liable under the contract." (See p. 167f-g). In the present case, Mr Lewis, who appears on behalf of the Main Contractor, accepts that the duty which he submits that the Architects owe to the Main Contractor is coterminous with the Main Contractor's rights against the Employer under the contract. 9. Purchas, L.J., who delivered the first judgment in Pacific Associates v Baxter (supra) expressed his conclusion (at pp. 179j-180a) in these terms:-
10. Ralph Gibson, L.J., the second member of the Court of Appeal, also attached importance to the arbitration on clause by which the contractor was able to enforce his rights against the employer - rights conterminous with the duty which he argued that the architects owed him. The learned Lord Justice said (at p.187b-c):-
11. Equal importance was attached to the arbitration clause by the third member of the Court of Appeal, Russell, L.J., who said (at p.191b-e):-
12. The arbitration clause in that case empowered the arbitrator to '… open up review and revise any decision opinion direction certificate or valuation of the Engineer...' (see p 163d-e). In the case before me, the arbitration clause clause 35 - confers similar powers on the arbitrator. It empowers him to '... open up, review and revise any certificate, opinion, decision, requirement or notice...'. 13. The material circumstances of the present case a so akin to those in Pacific Associates v Baxter (supra) that it is, in my view, impossible to avoid the application to this case of that one by distinguishing it. Realistically, Mr Lewis recognises this. Boldly, however, he invites me not to follow Pacific Associates v Baxter (supra). He supports that invitation by an able submission in the course of which cited a number of authorities and developed a number of points. Naturally, I have given anxious consideration to everything which he has advanced. He will, I trust, forgive me for not analysing all of it here. 14. Among the most formidible matters relied upon by Mr Lewis are a dictum of Lord Salmon in Arenson v Casson Beckman Rutley & Co [1977] AC 405 at p 438 and Hunter, J. 's judgment in Shui On Construction Co. Ltd v Shui Kay Co. Ltd. (1985) 1 Const L.J. 305. 15. The casein which Lord Salmon made the observation in question was, of course, the one in which the House of Lords held that mutual valuers did not enjoy the immunity from liability for negligence which the law accorded to judges and arbitrators. It had been argued that public policy required that such an immunity be accorded to mutual valuers so as to prevent them from being exposed to the danger of being 'shot at from both sides'. In the course of rejecting that argument, Lord Salmon said (at p 438):-
16. It goes without saying that nothing said by Lord Salmon can be ignored. But that dictum of his was drawn to the attention of the Court of Appeal in Pacific Associates v Baxter (supra); and the Court of Appeal nevertheless decided as it did. Purchas L.J., after citing what Lord Salmon said, continued (at p.175b-g):-
17. Not even a judgment of the Court of Appeal can remove the diffidence I feel in questioning anything said albeit obiter, by Lord Salmon. But I am bound to say this: A refusal to accord an architect immunity from suit at the instance of his client - with whom he is by definition in contractual relations - is one thing. It is, however, a far stronger thing to hold that the architect owes a contractor - with whom he has not entered into any contract - a duty in tort coterminous with his contractual duty to his client. I can readily see why, in fairness to the client, the courts should refuse the architect immunity from his contractual liability, whether that would or would not leave the architect exposed to being 'shot at from both sides'. That is not to say that a certifying architect or engineer is invariably so exposed. Depending on the circumstances, he may or may not be. If he enter into a tripartite contract to which the contractor is party, then - subject to the terms of the contract and its surrounding circumstances - he may well be. What, if any duty, is owed by an architect or engineer to a contractor with whom he is in contractual relations would depend on the construction, in its factual matrix, of the contract. Where the contractor is not in contractual relations with the architect or engineer the approach to the question is necessarily different. 18. In Shui On Construction Co Ltd v Shui Kay Co Ltd (supra) Hunter, J. - who took the view that certifying architects owed duty of care in tort to contractors- said ((at p 306) :-
19. Since then, however, Lord wilberforce's two-stage test - against which criticism had been mounting steadily - has been considered by the Privy Council in an appeal from Hong Kong, Yuen Kun Yew v Attorney General [1988] AC 175. Lord Keith of kinkel, delivering the advice of the Board, said (at p 194E) that :-
In one sense at least, this development of the law is a vindiction of Hunter, J. Although he considered the guidance given by Lord Wilberforce's two questions to be the best available at the time, he did (at p.307) express his doubts as to the ultimate adequacy of such guidance. 20. In my judgment, there is much to be said for the approach favoured by Brennan, J. in the High Court of Australia in Sutherland Shire Council v Heyman [1985] 59 ALJR 564. He said (at p 588):-
This is not to deny for one moment the accuracy of the statement by which Lord Atkin introduced the 'neighbour' principle in Donoghue v Stevenson [1932] A.C. 562, namely, that there '... must be, and is, some general conception of relations giving rise to a duty of care, of which the particular cases found in the books are but instances'. (p 580). There most certainly is such a general conception. That is why the Common Law develops by analogy. As can be seen, Brennan, J. uses the term 'analogy'. He also speaks, as can be seen, of 'categories'. Properly approached, proceeding by way of analogy and resorting to categories does not stultify the development of the law. Rather it ensures that such development will be orderly. The very concept that the categories of negligence are never closed recognises the existence of categories. 21. There is another material respect in which the law has been clarified since Hunter, J's judgment in Shui on Construction Co Ltd. v Shui Kay Co Ltd (supra) - a judgment to which tribute was paid in Pacific Associates v Baxter (supra) although the Court of Appeal ultimately reached a different conclusion as to the law. Hunter, J. said (at p.307):-
The banking case referred to went on further appeal to the Privy Council. That appeal succeeded. Lord Scarman, delivering the advice of the Privy Council in that case (Tai Hing Cotton Mill Ltd v Lit Chong Hing Bank [1986]AC 80) said (at p.107) that:-
In arriving at its decision in Pacific Associates v Baxter (supra) the Court of Appeal had the benefit of considering Hunter, J.'s judgment, and it had the added benefit of being able to consider it in light of the way in which the relevant law has developed since then by way of a number of decisions, including the two decisions of the Privy Council on appeal form Hong Kong to which I have referred. 22. After a review of all the authorities, the Court of Appeal adopted this approach to the determination of whether or not a duty of care existed: The duty exists if - but only if – three requirements are fulfilled. Foreseeability and proximity are the first two. The third is that it would be just and reasonable to impose the duty. 23. What I have to decide is whether or not the Main Contractor should be allowed to amend to plead a claim which depends on the existence of a duty of dare owed to it by the Architects. That requires me to take a view on the question of the duty's existence. Both counsel have invited me to treat that question as if were before me as a preliminary issue. Thus treating it, I would have no hesitation in holding that the Architects did not owe the Main Contractor any duty such as the one it asserts, and refusing joinder accordingly. Nor - I should add - would I arrive at a different result approaching the matter oh the basis that joinder should be permitted unless the argument that the duty exists is plainly and obviously one which cannot succeed. Had Hunter, J. and the Court of Appeal arrived at opposite conclusions at the same time and therefore at the same stage of the law's development, it might have been difficult for anyone to suggest that the view taken by Hunter, J had no chance of prevailing. However, as I have noted, that is not the situation. The principle which I extract from the Court of Appeal's decision in Pacific Associates v Baxter (supra) is one which I would state in these terms: Where, first, there is adequate machinery under the contract between the employer and a contractor to enforce the contractor's rights thereunder and, secondly, there is no good reason at tender stage to suppose that such rights and machinery would not together provide the contractor with an adequate remedy, then, in general, a certifying architect or engineer does not owe to the contractor a duty in tort coterminous with the obligation in contract owed to the contractor by the employer. The present case comes, in my judgment, fairly and squarely within that principle, and is concluded thereby. 24. On this question of whether or not a duty exists, I refuse the Main Contractor's application to join the Architects. 25. It is unnecessary, therefore, to decide whether or not the Main Contractor's claim against the Architects would be time - barred (if it existed). 26. As I have heard full argument on limitation, however, I will deal with it. In my judgment, it is at least arguable that the Main Contractor could avoid a defence of limitation by relying on the last certificate issued by the Architects, which is one dated August 24, 1983, and seems to supersede all the earlier certificates, each of which were issued more than 6 years before today. 27. Having disposed of the question of the Architects being joined, I turn to the Employer's objections to the proposed amendments. The Employer has no objection to the substance of the proposed amendments shown in that part of the draft Amended. Statement of Claim which ends at paragraph 16. Thereafter, the Employer contends, the proposed amendments advance a new cause of action after the expiration of the period of limitation for the same. Without accepting this, the Main Contractor says that the matters set out in paragraph 17 onwards of the draft Amended Statement of Claim are already in the Reply. It does not seem to concern the Main Contractor whether or not those matters also go into the Statement of Claim as against the Employer. 28. In any event, it is accepted by the Main Contractor that if I am against it on joinder, the summons before me must be dismissed. It is of course at liberty to prepare another draft Amended Statement of Claim including matters contained in the draft Amended Statement of Claim accompanying the present Summons but not adjudicated upon by this judgment. Both counsel felt that there was a reasonable chance that such fresh amendments could be made by consent. If not the matter can be brought before the Court for determination. 29. Although the matter was heard before me in chambers, I am - at the request of both. counsel - delivering judgment in open court a question of considerable importance to the building industry is involved. 30. Before parting with the case, I would like to express my indebtedness to both counsel for their assistance. 31. In the result, the Main Contractor's summons is dismissed. I will now hear counsel on costs and any ancillary matters which may arise. [Argument as to costs] Court: Costs of the summons and the hearing thereof, including those of today, to the Defendant and the proposed Defendant.
Representation: Mr K. Lewis for Official Receiver Mr J. Scott (McKenna & Co.) for Defendant & Proposed Defendant |
Other judgments that cite this case