Skk (H.K) Co. Ltd. v. Ip Kin Keung t/a Asia Contracting Co.
Read the full judgment text of HCCT22/2001 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 19 July 2001 before Hon Burrell J.
Procedure – Setting aside default judgment – Whether defendant showed real prospect of success – Application governed by The Saudi Eagle test – Defendant’s contract dispute over payment conditions, measurements, and defects raised real prospects of success on part of claim – Court refused to set aside entire default judgment but set aside part exceeding 50% of contract sum – Conditional leave granted to defend balance subject to payment into court – Interest and costs orders made accordingly.
Legal issues: Setting aside default judgment
Outcome: Application to set aside whole judgment refused; part of judgment amount not set aside; leave to defend balance granted conditional on payment.
|
HCCT000022/2001 HCCT22/2001 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS ----------------------
----------------------- Coram: Hon Burrell J in Chambers Date of Hearing: 17 July 2001 Date of Decision: 19 July 2001 --------------------- D E C I S I O N ---------------------- 1.In this action a defence should have been served on 4 April 2001. In default, the plaintiff entered a regular judgment on 10 April 2001. By this summons, the defendant seeks to set aside the judgment and defend the action. 2.There is no dispute between the parties as to the legal test to be applied. In Hong Kong, the proper test is as laid down by Sir Roger Ormrod in The Saudi Eagle [1986] 2 Lloyd's Report 221 which is helpfully elaborated upon in the Hong Kong Civil Procedure 2001 in the following terms :
3.I regard the word "real" to mean genuine or actual. It is not necessary to demonstrate a likelihood of success but the defendant must show more than a remote chance of winning. The word "success" must encompass partial success. If the defendant has a real prospect of reducing the plaintiff's claim, it would be unjust to deprive him of that opportunity. In such circumstances an order setting aside part of the judgment may be appropriate. 4.The plaintiff was the defendant's sub-contractor carrying out external renovation work at the Matilda Hospital. The plaintiff sub-sub-contracted all the work to "Hon Fung". The defendant has paid invoices totalling $898,052.95. The plaintiff claims $2,390,703.81 remains due and owing. All works have been completed. 5.In outline the defendant says either that the sums are not due or if any sums are due, the claim is premature. It relies on four grounds. 6.Firstly, according to clause II of the agreement (as pleaded in the draft defence), the plaintiff is only entitled to 50% of the contract sum prior to the issuance of the certificate of practical completion, which has not yet been issued. 7.Secondly, clause VI of the agreement states :
As yet there has been no agreement. 8.Thirdly, there is a significant disagreement as to the appropriate measurements. A report on which the defendant relies ( a four-page report) certifies an area of 7,229.2 sq.metres. The plaintiff's report (over 200 pages including photographs) calculates a figure of over 16,000 sq.metres. 9.Fourthly, there is an issue as to alleged defects in Hon Fung's work. It is unnecessary to list the defects. They are pleaded in the draft counterclaim. 10.Mr Thomas Lee, for the plaintiff goes some way in taking the shine off these points. He submits :
11.These are the arguments for and against there being real prospects of success. The court must look at the whole case and endeavour to take a common sense view. The plaintiff's criticism of the defendant's conduct in the litigation may also be weighed in the balance. 12.The court's starting point is that if judgment for the full amount were allowed, then there is a real prospect that it would be an unjust outcome for the defendant. I am not inclined therefore, in spite of the merit in the points made by Mr Lee, to simply refuse the application to set aside. 13.The second stage in the court's approach is to state that the defendant has no prospect of resisting the plaintiff's claim to 50% of the contract sum, at the very least. I consider it safe and fair to rely on the Chong report in determining what 50% amounts to. The fact that the Chong report was not commissioned pursuant to contract is neither here nor there for these purposes. The court can and does use it to assess a minimum figure of the plaintiff's entitlement. 50% of the invoiced sum is $1,644,378.38 of which $898,052.95 has been paid. The difference, namely, $746,325.43 will therefore not be set aside from the sum entered in default. However, the rest of the judgment sum, $1,644,378.38 will be set aside. 14.The third stage is to decide what if any conditions should be made when giving leave to defend, limited to this sum. 15.I am satisfied that this is a case in which a payment into court should be made. The criticisms of the reasons advanced by the defendant as to why the judgment should be set aside cannot be overlooked. In the court's judgment the real "real prospects" in this case are those of the plaintiff ultimately being awarded a sum in excess of that already allowed. The counterclaim is shadowy and the award of 50% to the plaintiff is by no means intended to reflect their ultimate entitlement, once the dispute as to measurements has been either agreed or adjudicated upon. 16.In my judgment about half the remaining sum claimed should be paid into court, namely $800,000. Order
Representation: Mr Thomas Lee, instructed by Messrs Simmons & Simmons, for the Plaintiff Mr Matthew C.S. Chong, instructed by Messrs George Tung, Jimmy Ng & Valent Tse, for the Defendant |