Secan Ltd. v. Hsin Yieh Arthitects & Associates Ltd.
Read the full judgment text of HCCT69/2001 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 24 November 2001 before Hon Burrell J.
Procedure – Construction and arbitration proceeding – Delay in serving Statement of Claim – Writ issued near expiry of limitation period – Whether delay post-issuance inordinate and excusable – Whether delay caused real risk of prejudice to defendant – Application for extension of time granted and strike out dismissed by Master – Defendant appeals – Court applies principles from Costellow v. Somerset County Council confirming only delay after writ issue relevant and dismissal for want of prosecution requires real risk of prejudice – Delay of two years post-issue inordinate and inexcusable given possession of evidence and solicitors’ knowledge – Loss of insurance during delay does not amount to sufficient prejudice as major costs would not have been covered anyway and speculation on settlement unsupported – Prejudice from lateness and fading memories not sufficient to justify striking out – Appeal dismissed and costs of appeal ordered against plaintiff. The defendant’s subsequent appeal to Court of Appeal allowed (CACV004062/2001).
Legal issues: Delay and prejudice in proceeding
Outcome: Defendant's appeal dismissed; Master’s order upheld
Cited by 7 cases
|
HCCT000069/2001 HCCT69/2001 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO.69 OF 2001 ------------------------
------------------------ Coram: Hon Burrell J in Chambers Date of Hearing: 8 November 2001 Date of Decision: 24 November 2001 -------------------- D E C I S I O N -------------------- 1.This is an appeal against an order of Master Lung dated 8 May 2001. The learned master had granted the plaintiff two days in which to serve a Statement of Claim out of time. At the same hearing he dismissed the defendant's application to strike out for want of prosecution. 2.The brief history and chronology is important and it is as follows. 3.On 8 May 1993 a flood occurred in a building which had just been constructed. The defendant was the architect. The plaintiff was the developer. The material events, for the purposes of this appeal, thereafter were :
The defendant now appeals. 4.The correct approach when having such cross summons is set out in the Hong Kong White Book :
5.The Costellow case concludes with this passage :
6.On the particular facts of this case the court's task is to decide firstly, was there a delay which was inordinate and inexcusable and secondly, if so, has the delay caused at least a real risk of prejudice to the defendant? 7.A preliminary issue between the parties is what the period of delay actually is. Provided the Writ has been served within the limitation period the court is concerned with the post Writ delay. Mr Simon Westbrook SC for the plaintiff submits that the delay period is from the last day for service of Statement of Claim (29 May 2000) to the attempted service of the Statement of Claim on the defence solicitors without leave (mid January 2001) a total of 7½ months. Mr Geoffrey Shaw for the defendant submits that the delay period starts with the issuance of the Writ (May 1999) not its service (May 2000) and the delay period ends with the actual, not the attempted, service of the Statement of Claim (May 2001). By this method the delay is two years. 8.I agree with Mr Shaw. There is no real room for debate on the subject. The Hong Kong White Book states simply "only delay after the issue of the writ is relevant". The holding in the Costellow case includes the words "unless the delay complained of after the issue of proceedings had caused ...". In the case of Hymer v. M.T.R. Corp [2000] 2 HKLRD at p.606, Ribeiro JA said :
9.As for the argument about the end of the delay period (January 2001or May 2001) the latter date must be right. It is somewhat surprising, looking at the case in the round, that the plaintiff tried to serve its Statement of Claim without leave and without making an application for extension of time in January 2001. They could hardly have been surprised that it was not accepted and returned. The time it then took to get the two-day extension (January to May 2001) was additional delay which they caused. Thus, we are dealing in this case with a delay of two years after the issue of the Writ which itself was six years after the event. Apart from receiving the Writ the defendant had played no other part in this litigation. This is marginally longer than the delay in the Costellow case which was 22 months. Was the delay inordinate and inexcusable? 10.In my judgment it was both inordinate and inexcusable. Inordinate simply means not within the ordinary regulations. Plainly this delay has been excessive and irregular. As to whether it has been excusable the court is entitled to weigh in the balance the history of the action before the issue of Writ. An inordinate delay might, for example, be excusable if the plaintiff's solicitors were only instructed for the first time just before the expiration of the limitation period. Not so here. In this case the plaintiff had begun compiling its evidence immediately after the flood. Loss adjusters were engaged almost straightaway and produced reports in May 1993 and October 1994. The plaintiff's solicitors were engaged in May 1995. They commenced proceedings against ACE in May 1996. They have known of the defendant's potential liability for six years. They have known that ACE was blaming the architects for five years. Bearing in mind all this background the plaintiff delayed a further two years from May 1999 before providing the defendant (by proper service) with the particulars of its claim against them. It is impossible to discern why such time could have been needed . The plaintiff had been in possession of the evidence for years. It was not unduly complex. The Statement of Claim itself is relatively brief; most of it is a recitation of contractual terms, damages claimed and some non-controversial factual matters. In short, the plaintiff has not persuaded the court that the delay was excusable. The high water mark of their explanation is that an on going business relationship existed between the plaintiff and the defendant, which caused them to decide not to involve the defendant. The assertion is not accepted by the defendant and, even if true, provides little comfort or consolation to the defendant who ultimately and "out of the blue", does become involved eight years after the event. Has the delay caused at least a real risk of prejudice to the defendant? 11.This question is the more difficult to resolve. The defendant's submission is that they have been prejudiced or there is, at least a real risk that they will be for three reasons :
In this context I have considered the authority relied on by Mr Shaw, namely Antcliffe v. Gloucester Health Authority [1992] 1 WLR 1044 in which a claim for damages for medical negligence was struck out, on appeal, because -
It is I think distinguishable from the present case on two grounds. Firstly, it was a very different case factually. Secondly, the period of delay complained of in Antcliffe was 4½ years, a much longer period and, in the context of a medical negligence case, of much greater significance on the issue of prejudice. I think therefore, that the loss of insurance in this case, albeit a bitter blow to the defendant and albeit a matter to be taken into account, falls short of prejudicing the defendant from being ultimately able to do themselves justice in this case, or from creating a risk of such prejudice.
12.(b) and (c) can be considered together. After anxious thought and not without some misgivings I have come to the conclusion that these reasons, also, do not amount to sufficient prejudice or the risk of prejudice, so as to strike the plaintiff out. Matters of trial preparation and the dimming of memories have to be looked at in the context of the issues between the parties. The plaintiff's case, primarily, is that (i) the drainage pipes were too small to cope with the inflow and outflow pipes and (ii) the overflow pipe was deflectively designed in that it discharged water directly onto the floor. It seems to me that these are issues which will be substantially resolved by an examination of contemporary documentation. The expert evidence will be of particular significance. The experts will formulate their opinions from plans and other documents, not from having been there at the time and seen the flood. Moreover, it is not suggested that any material witnesses are unavailable. 13.The learned master had a difficult decision to make. In my judgment, although a borderline case, the decision was correct and accordingly the appeal will be dismissed. I make a costs order nisi that the costs of the appeal be the plaintiff's.
Representation: Mr Simon Westbrook, SC, instructed by Messrs Masons, for the Plaintiff Mr Geoffrey Shaw of Messrs Deacons, for the Defendant
|
Other judgments that cite this case