Weltime Hong Kong Ltd. v. Ken Forward Engineering Ltd.
Read the full judgment text of HCCT73/2000 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 5 December 2000 before Hon Burrell J in Chambers.
Arbitration — Arbitration Clause Construction — Validity of Arbitrator Appointment — Jurisdiction — Arbitration Ordinance Cap 341 s.12 and s.23(4) — Contractual Clause Requiring Co-joint Appointment by Two Bodies One of Which Ceased to Exist — Whether Appointment by HKIAC Valid — Existence of Dispute for Arbitration purposes. The case concerns two arbitration proceedings between Ken Forward Engineering Ltd and respondents Weltime Hong Kong Limited and Healthy Sun Limited arising under contracts containing an arbitration clause providing for appointment of an arbitrator co-jointly by HKIA and RICSHK. RICSHK ceased to exist in 1997 and was replaced by HKIS, a distinct body. The claimants failed to obtain respondent's consent and proceeded to HKIAC nomination under s.12 Cap.341. The respondents challenged the validity of the arbitrators' appointments and jurisdiction. The Court confirmed that the appointment mechanism under clause 35 was technically inoperable due to the dissolution of RICSHK; HKIA acting alone did not satisfy the clause; and substitution of HKIS was not agreed or appropriate. Resort to HKIAC under s.12 was upheld as proper. The Court applied the PT Dover test to find no strong prima facie case that the arbitrators were plainly wrong. The Court also held that there was a valid dispute for arbitration since respondents disputed the liability despite admitted non-payment. The summonses for leave to appeal were dismissed with costs.
Legal issues: Validity of arbitrators' appointment under clause 35 · Existence of a dispute for arbitration purposes
Outcome: Leave to appeal the arbitrators' awards was refused; the summonses were dismissed with costs.
Cites 1 case
|
HCCT000073/2000 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NOS.73, 97 AND 108 OF 2000 ------------------------ HCCT73/2000
------------------------
------------------------
------------------------
------------------------
------------------------
------------------------ Coram : Hon Burrell J in Chambers Date of Hearing: 27 November 2000 Date of Decision: 5 December 2000 ------------------------- D E C I S I O N ------------------------- 1. There are four summonses before the court, only two of the four (the two substantial matters) have been argued and this decision only related to those two. They are applications by the plaintiff (who is the respondent in the arbitration proceedings between the same parties) for leave to appeal two arbitrator's interim awards which deal with an issue of jurisdiction. 2. There are two arbitrations under way. The claimant is the same in both (Ken Forward Engineering Ltd). The respondents are Weltime Hong Kong Limited and Healthy Sun Limited. The contract documents are the same in each case. 3. Two different arbitrators have been appointed. They have both been asked to make a ruling on a question of jurisdiction. They have both done so and made the same decision. The issue 4. The issue concerns whether or not the arbitrators have been validly appointed under the provisions of the arbitration clause in the contract, clause 35. The relevant part of clause 35 reads as follows :
5. Thus the contract provides for the appointment of an arbitrator (a) by consent; or (b) if not by consent, by the Hong Kong Institute of Architects' President or Vice-President ("HKIA") co-jointly with the Royal Institute of Chartered Surveyors' (Hong Kong Branch) Chairman or Vice Chairman. Failing an appointment by (a) or (b), then the provisions of the Arbitration Ordinance, Cap.341, namely section 12, would be applicable. 6. The problem which arose came about because on 1 September 1997, the Royal Institute of Chartered Surveyors ("the RICSHK") ceased to exist. The Hong Kong Institute of Surveyors ("the HKIS") which had been in existence since 1993 took over its functions. The problem in relation to each arbitration is similar but not identical because of the chronology of events. I therefore outline the problems separately. The "Healthy Sun" contract 7. This was entered into in 1995 using a standard form of contract which referred to the RICSHK. The arbitral issues arose in 1998 when the RICSHK had ceased to exist. The claimant failed to get the respondent's consent to the appointment of an arbitrator ((a) above) and ignored (b) above because there was no such body as the RICSHK at the time. It therefore went to the Hong Kong International Arbitration Centre ("HKIAC") under section 12 of Cap.341 and an arbitrator was appointed. 8. The respondent submitted to the arbitrator that he had not been validly appointed because the claimant should have applied to the HKIA co-jointly with the HKIS, as successor to the RICSHK before resorting to section 12. The learned arbitrator disagreed. The "Weltime" contract 9. This was entered into in about November 1997 after the RICSHK had ceased to exist. Nonetheless the standard form of contract which the parties used and which they both signed was a pre-1997 out of date form which did refer to the RICSHK in clause 35. Again, when the arbitral issues arose in 1998, the claimant went straight to the HKIAC for the appointment of an arbitrator, having failed to appoint one by consent under (a) above. (b) was again passed over because the claimant could not apply to a non-existent body. 10. When asked to rule on the matter, the learned arbitrator came to the same conclusion, namely that her appointment was valid. 11. Before setting out the relevant parts of the two interim awards which deal with the issues, it is useful to set out the chronology of events since 1998 (I only set out the Weltime chronology, although the Healthy Sun chronology is similar).
12. I now set out the reasons given by each arbitrator when finding against the respondent on the preliminary point of jurisdiction. Weltime 13. On 6 September 2000, the interim award was published. The relevant part is as follows :
Healthy Sun 14. On 11 August 2000, the Healthy Sun arbitrator, Mr Daniel Lam JP, published his interim award which stated :
15. It is against these findings which leave to appeal is sought. With the consent of the parties, I have decided that this is an appropriate case to deal with the question of leave and the substantive appeal together. The test to be applied in application for leave to appeal arbitrators' awards 16. In order to obtain leave, the plaintiff/respondent in arbitration must show :
(In re PT Dover Chemical Company v. Lee Chang Yung Chemical Industry Corporation [1990] 2 HKLR 257). 17. Mr Chain for the plaintiff submits that as the point in issue is one of pure construction, the PT Dover test has no application. He submits this court must decide simply if the arbitrators' decision on construction is right or wrong. If the arbitrator got it wrong, the appeal must succeed. 18. I do not agree with this initial approach. Whether the question of law being appealed is a point of "pure construction" or the interpretation of a term of a contract makes no difference. The fundamental principle that the onus is on the plaintiff to show at least a strong prima facie case that the arbitrator was wrong still applies. I do not accept that the reasoning behind the PT Dover test, for some reason, does not apply in this case. The fact remains that the parties agreed to an arbitration clause. That clause is but one in a lengthy contract document. All clauses, including the arbitration clause itself, may be subject to legal argument by the parties before the arbitrator. The threshold is a high one in this as in any other application for leave to appeal an award. 19. Moreover, the PT Dover test provides for a sliding scale. The issue before me is neither at the top nor the bottom of that scale. It is not at the bottom of the scale because it does not concern the interpretation of a clause which regulates the conduct of the parties which will regularly arise and be of importance to the industry generally. Neither is it at the top because it may not be a one-off situation which only concerns these parties. It is possible that the same situation will arise again where an arbitration issue arises post-1997 which contains a reference to the pre-1997 RICSHK. However, such a situation has not occurred in this court before and the likelihood of it arising again diminishes with the effuxion of time. I therefore judge the point to be towards the top of the scale. The plaintiff must, therefore, reach a threshold which is close to demonstrating that the arbitrators, both of them, could not possibly have been right. 20. That threshold has not been reached. Both arbitrators found favour with the tenable argument that as the RICSHK did not exist at the material time, the second limb of clause 35 ((b) above) could not be performed. In support of this approach, it is emphasized that the change from RICSHK to HKIS in September 1997 was not a change in name only in the sense that the same body carried on albeit under a different name. The HKIS was a different body which had co-existed with the RICSHK for four years prior to 1997. HKIS was patently not the body which the parties had agreed to approach in trying to appoint an arbitrator. It is unnecessary to repeat, for the purposes of individual analysis, each of the points referred to by the learned arbitrators. It is sufficient to say they are cogent, relevant and not plainly wrong. 21. The plaintiff's submission is premised on the contention that the parties must have intended to have the arbitrator selected by the HKIA and the successor to the RICSHK. This is an assumption which cannot be made. Moreover, even concerning the Weltime contract (which had been signed post the dissolution of the RICSHK, using an out of date version of the standard form of contract) the learned arbitrator determined, that clause 35 required an appointment by two bodies co-jointly. One of those bodies did not exist. The appointment mechanism did not provide for the appointment by the HKIA alone and the agreed co-joint appointment mechanism was impossible to perform. I reject the submission that this approach was plainly wrong. 22. Finally, the submission that the claimant should first of all have attempted to perform the contract by applying to a non-existent body is without merit. It is not possible to apply to a body which does not exist. Fortunately, this is not a situation whereby the contract becomes unworkable because of a term, the performance of which is impossible. Normally in such a situation a court would strive to give the words of such a clause some meaning so as to make the contract work. Here, however, the parties have section 12 of the Arbitration Ordinance, the application of which does result in the appointment of an arbitrator, whereas limb (b) of clause 35 does not. The parties chose to arbitrate their differences. In order to give effect to that choice, section 12 of Cap.341 has been applied properly. 23. In assessing the merits of the respondents' submissions, which were skillfully advanced by Mr Chain, some regard must be had to the fact that the point was first made some 19 months after the appointments were made and only after attempted settlement negotiations had broken down. Had his submissions succeeded, the only consequence would be that the parties go back to square one and start again. No dispute? 24. In respect of the Weltime contract, Mr Chain, for the plaintiff, make a separate additional submission. Although not specifically referred to in the application for leave to appeal, it is brought under the general argument that the arbitrator has no jurisdiction. 25. It is submitted that the matter referred to in the notice of arbitration (in the claimant's letter to the respondent dated 14 September 1998) is not a dispute which can be referred to arbitration. In short, the letter gives notice of two disputes :
26. Mr Chain submits that interim certificates represent an estimated value of work done and as such are only of provisional validity. If, he submits, the contract comes to a premature end, the provisional validity of the certificates comes to an end. Then, clause 25 or 26 (depending on who terminated the contract) governs the parties' rights and liabilities. He submits that it was never in dispute that the interim payments were not made. Furthermore, once the contract is determined, the liability to pay on the interim certificates disappears because such disputes as there may be then arise under clause 25 or 26. 27. It is well settled that the definition of a dispute for arbitration purposes is very wide indeed. The simple definition is :
28. A mere glance at the realities reveals an obvious dispute. The dispute is not whether or not the interim payments were actually made, it is common ground that they were not; the dispute concerns the reasons for and consequences of their admitted failure to pay. The arbitration notice defines the dispute as the loss and damage arising from the failure to pay. It is plainly arguable that the failure to pay creates a debt which is in dispute. It is true that after termination of the contract, the claimant's claim is for the value of the works completed and unpaid for. It is open to the claimant to rely on the architects certificates as prima facie evidence of the value of those works. It is for the arbitrator to decide the difference, if any, between the value of the works done and value of the certificates. In my judgment, the submission that the claimants are prevented from pursuing their claim simply because the respondents have admitted that the interim payments were never paid is misconceived. The respondents admit the certificates were never paid but they do not admit that the sum claimed is due and payable. If they did, they would have paid it. 29. On the issue of jurisdiction raised in the plaintiff's summons, concerning the validity of the arbitrators' appointments and the existence or otherwise of a dispute between Weltime and Ken Forward, I find in favour of the defendant (the claimant in arbitration) and dismiss the plaintiff's summons with costs.
Representation: Mr Benjamin Chain, instructed by Messrs Sit, Fung, Kwong & Shum, for the Plaintiff Mr Jeevan Hingorani, instructed by Messrs Fung, Wong, Ng & Lam, for the Defendant |
Cases cited in this judgment
Further hearings and rulings under HCCT73/2000