Asia Rock Art Ltd. v. W. Hing Construction Co. Ltd.
Read the full judgment text of HCCT10/2000 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 29 March 2000 before Hon Burrell J.
Arbitration — Construction Contract — Implied Terms — Contractual Entitlement to Damages on Termination — Leave to Appeal — Arbitration Ordinance s.23 — Threshold for Leave — Contractual Clauses 22 and 29 — Whether failure to follow payment certification or claim procedure barred recovery under Clause 29 — Held: No question of law fit for leave as contract lacked any condition precedent requiring certification or claim submission for Clause 29 claims. The arbitrator’s finding that the respondent was entitled to recover damages under Clause 29 was not obviously wrong. Implied term obliging possession and access to site confirmed as not obviously wrong, and breach finding a factual matter. The court applied the high threshold test from Lee Chang Yung Chemical Industry Corp v. PT Dover Chemical Company, affirming the primacy of arbitration finality and party autonomy. Leave to appeal was refused, and costs awarded to the respondent on the appeal application.
Legal issues: Leave to appeal on contractual entitlement under Clause 29 · Implied term requiring possession and access to site · Breach of the alleged implied term
Outcome: Refusal of leave to appeal against the Second Interim Award on liability
|
HCCT000010/2000 HCCT10/2000 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO.10 OF 2000 ----------------------
----------------------
----------------------- Coram: Hon Burrell J in Chambers Date of Hearing : 29 March 2000 Date of Judgment : 29 March 2000 Date of Reasons for Judgment : 31 March 2000 ---------------------- J U D G M E N T ---------------------- 1. On 29 March 2000 having heard submissions from Mr Ronny Wong, SC, for the appellant, and Mr Michael Thomas, SC, for the respondent, I refused leave to appeal against the Second Interim Award on liability of the arbitrator Ms Teresa Cheng dated 12 January 2000. These are my brief reasons. 2. The questions posed in the originating motion (as amended) are as follows :
3. In the consideration of whether leave should be granted, question (3) above is of particular importance. Mr Thomas contends that if question (3) gives rise to no question of law which would substantially affect the rights of one or more of the parties then, by virtue of s.23 of the Arbitration Ordinance, leave should be refused. If leave is refused on question (3), questions raised under questions (1) and (2) become academic and, again because of s.23, should not be addressed. 4. It is therefore necessary to start with question (3) as amended and set out clauses 22 and 29 of the contract :
5. An analysis of question (3) does not, in my judgment, give rise to a question of law which would be appropriate for determination by this court on an appeal from the learned arbitrator. The question falls into three parts :
6. What the appellant would seek to argue on appeal is that because the losses claimed were not certified by the engineer, there is no liability on the appellant under the contract. It would be argued that the respondent is not entitled to any relief where it failed to comply with the contractual mechanism for being so compensated. However, as submitted by Mr Thomas in reply, the contract does not lay down a mechanism for making a claim under clause 29. The arbitrator found that the respondent was liable under clause 29 and specifically made the point in her award that she rejected the argument being advanced again in this application for leave. She stated :
7. The appellant conceded in the arbitration that the claims properly come within clause 29 but argues that the learned arbitrator made a "glaring" error of law in failing to determine that there was no liability to pay them because a contractual mechanism had not been followed. 8. This issue, which was fully canvassed in the arbitration and carefully dealt with in the award, falls short of being a question of law fit for consideration on an application for leave to appeal. Quite simply, it was found that the express terms of clause 29 entitled the respondent to recover its losses and there was no provision in the contract which prevented the arbitrator from enforcing those rights. Such a ruling does not give rise to a moot point as to how a particular clause of the contract should be constructed. 9. If this decision, that there is no question of law as provided by s.23 of the Arbitration Ordinance, is unduly harsh, then the appellant would fail to get leave in any event, on the application of the "PT Dover" test. In Lee Chang Yung Chemical Industry Corp v. PT Dover Chemical Company [1990] 1 HKC 132, Hunter JA set the criteria which the court must apply on leave applications. In this application, the appellant acknowledges that the appropriate test is the one applicable to "one-off" cases, which is as follows :
10. It is high threshold for good reason. The parties agreed to arbitrate their differences before a single arbitrator, and further agreed that her award should be final and binding upon them. The award has been made, and the mutual interest in speedy finality in the resolution of disputes would be defeated if an appeal through the courts were too readily permitted. 11. Because the courts uphold the principle that the parties have autonomy over their own affairs and that their agreement to arbitrate their differences should be respected, a losing party cannot appeal to the court merely to reargue a case that the arbitrator has rejected, or to maintain that the arbitrator was in error because she failed to accept its arguments on the law or on the facts. 12. Applying the test to each of the three questions posed, it seems to this court that the arguments that the learned arbitrator was right are preferable to those that she was wrong. It is not necessary, for the purpose of this judgment, to make a ruling but the following observations in relation to each of the three questions are apposite. 13. Concerning question (1), she held that the appellant was obliged to give the respondent possession of and access to the site for the work they had contracted to do. It is frankly difficult to understand the argument that she was obviously wrong to imply such a term. 14. Concerning question (2), on any view this involves only a finding of fact. 15. Concerning question (3), as already dealt with, the arbitrator found that, contrary to the appellant's contention, there was no contractual bar which prevented recovery of those losses claimed in the arbitration which, as conceded by the appellant, came within the scope of clause 29. A mere perusal of the contract and the reasons in the award suggests she was right. 16. Having declined to grant leave to appeal, the costs of resisting the application shall be the respondent's (in the appeal), to be taxed if not agreed.
Representation: Mr Ronny F.H. Wong, SC, instructed by Messrs W.M. Lo & Company, for the Respondent/Appellant Mr Michael Thomas, SC, instructed by Messrs Masons, for the Claimant/Respondent |