Kailey Engineering Co. (HK) Ltd. v. Yau Lee Construction Co. Ltd.
Read the full judgment text of HCCT 74/99 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 16 August 1999 before Deputy Judge Li in Chambers.
Construction law — Contract dispute — Summary judgment — Order 14 application — Sub-contract for hospital refurbishment — Plaintiff sought recovery of unpaid contract sum — Defendant claimed damages for alleged incomplete and defective work — Late affirmation filed by defendant alleging outstanding works costing about $1.7 million — Court applied threshold test from Bhagwandas Kewaleram Murjani v. Bank of India requiring credible triable issue on balance of probabilities — Defendant's affidavit found incredible and inconsistent with project completion certificates, final payments, and defendant's pleadings — Clause 18 of Sub-Contract requiring reasonable notice and actual remedial work to claim costs not satisfied — Plaintiff entitled to partial summary judgment for amount not disputed — Defendant granted leave to defend other claims — Costs awarded to plaintiff in relation to summonses. Partial summary judgment granted for $1,756,004.95 with liberty to continue remaining claims; order nisi on costs payable by defendant.
Legal issues: Applicability of Order 14 summary judgment test · Claim for damages under Clause 18 of the Sub-Contract
Outcome: Partial summary judgment for the plaintiff for $1,756,004.95; defendant granted leave to defend remaining claims
|
HCCT000074/1999 HCCT 74/99 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO. 74 OF 1999 ____________
____________ Coram: Deputy Judge Li in Chambers Dates of Hearing: 9 and 10 August 1999 Date of Handing Down Judgment: 16 August 1999 _________________ J U D G E M E N T _________________ This is an application by summons for finial judgment under Order 14 for $2,751,953.91 together with interest and costs. However, when the Plaintiff's case was actually presented, the claim is for $2,338,535.18. 2.It is common ground that the Plaintiff and the Defendant are bound by a contract ("The Sub-Contract") under which the Plaintiff performed heating, ventilation and air-conditioning plant installation work as sub-contractor for the Defendant who was the main contractor for the refurbishment and improvement of the Kwong Wah Hospital in Kowloon. As a result of variations the details of which are irrelevant for present purposes the Plaintiff undertook more work under the Sub-Contract and the contract sum was increased to over $60 million. The bulk of the contract sum has been paid. By the action herein, the Plaintiff seeks to recover the outstanding amount under the Sub-Contract. The accounting differences may be seen from the summary below taken from the written skeleton arguments of counsel for the Defendant:-
3.It would, therefore, appear that even if the Defendant succeeds on the contra charges and amounts received by the Plaintiff, there is still $1,756,004.95 due to the Plaintiff. This amount forms one component of the $2,338,535.18 being sought by the Plaintiff by way of summary judgment, the other two components again relate to disputed contra charges and amount already received by the Plaintiff. The $1,756,004.95 being the lowest common factor, I would have thought that it is the least the Plaintiff should be entitled to under the Order 14 summons. But it is not so simple. 4.The Defendant belatedly filed an affirmation by one Mr. Luk ("the Luk Affirmation") with massive supporting exhibits to show that there are three items of outstanding work under the Sub-Contract for which the Defendant is entitled to claim damages to the tune of nearly $1.7 million against the Plaintiff. If this evidence is admitted and accepted as showing a viable defence, obviously the Order 14 summons must fail. After hearing arguments, I decided to admit the Luk Affirmation as evidence but ordered the Defendant to pay costs for obtaining leave to introduce such evidence. The focus of the matter is then turned to the force and effect of this evidence. 5.According to the Luk Affirmation, numerous aspects of the work performed by the Plaintiff under the Sub-Contract are unsatisfactory. In particular, the Plaintiff failed to do:-
As a result, the Defendant will have to follow-up and that would cost in total $1.7 million approximately. 6.Mr. Shaw for the Plaintiff reminded me of the case of Bhagwandas Kewaleram Murjani and Others v. Bank of India [1990] 1 HKLR 586. I think it is only necessary to refer to the headnotes of the case report for guidance on the approach I am bound to take in the present instance:-
7.Mr. Shaw then went on to point out the following incontrovertible facts gleaned from the documents disclosed by the Defendant:-
8.The points made by Mr. Shaw are that first, if the Plaintiff has left work to the value of $1.7 million undone, the independent authority - the Architectural Services Department and the owner - the Hospital would not have acted as if the project has been satisfactorily completed. Certificates of Completion would not be issued, Surety Bonds would not be returned, the final contract sum would not be paid and the retention monies as security would not be released. Secondly, if there are glaring and costly defects, the Defendant would have pleaded them unambiguously at the first opportunity in its Defence instead of initially replying on the defence of set-off for amounts due under some other contract which is the subject of litigation in HCCT 22 of 1999. Thirdly, the Luk Affirmation shows clear attempt to grossly inflate the costs and charges to complete one item of alleged outstanding work to reach a figure that would effectively wipe out the otherwise indisputable unpaid balance of $1,756,004.95. 9.Applying the test adopted by the Court of Appeal, I have no difficulty at all to find that the Luk Affirmation is incredible, the claim or counterclaim for damages by the Defendant is implausible and the assertion of triable issues on outstanding work is inconsistent with the Defendant's own documents and conduct. 10.Mr. Liu for the Defendant suggested that the claim for damages for outstanding work is based on implied contractual term or Clause 18 of the Sub-Contract. In my view, once the claim or counterclaim has been rejected as incredible, the legal basis for the claim or counterclaim is plainly irrelevant. In any event, Mr. Liu did not elaborate on why, if Clause 18 of the Sub-Contract can be the basis of claim, the court should find it necessarily to imply a contractual term. It is trite law that the court should be extremely slow to imply a term when the situation is covered by an express term of the contract. 11.As to Clause 18 of the Sub-Contract, it reads:-
Mr. Shaw contended that the Defendant would be entitled to mount a claim for damages only after giving reasonable notice, after the Plaintiff has refused to comply with the notice and after the Defendant has in fact done the remedial work and incurred costs and charges. None of these conditions has been fulfilled. 12.There is no dispute that the Defendant has not done the work allegedly left behind by the Plaintiff. The reason given by the Defendant is that such work cannot be conveniently done now. It has to wait until some future time when the Hospital schedule a shut down of the operation theatre and other facilities. This being the case, if the allegation of outstanding work is true, the Plaintiff still has the opportunity to do the outstanding work and get payment. In any event, the Defendant cannot claim costs and charge not yet incurred. 13.In a nutshell, I find a transparent attempt on the part of the Defendant to stall payment due. The Plaintiff is immediately entitled to at least $1,756,004.95. 14.As to the issues of contra charges and amount received by the Plaintiff, I see that they are inextricably bound with real factual disputes which cannot be resolved without trial. 15.In the premises, there must be partial judgment for the sum of $1,756,004.95 for the Plaintiff with liberty to the Plaintiff to prosecute its remaining claims and leave to the Defendant to defend on those remaining claims. There is also order nisi that the Defendant pays the Plaintiff's costs of and occasioned by all summonses before me to be taxed if not agreed and to be paid forthwith. The order nisi is to become absolute unless either party applies within 14 day from the day of handing down this judgment for variation of the order nisi.
Representation: Mr. Geoffrey Shaw of Messrs Deacons, Graham & James for the Plaintiff. Mr. Michael Liu instructed by Messrs T. H. Koo & Associate for the Defendant. |