Shing Fat(A Firm) v. Chan Sum

Case No.HCA 7419/1980
Court
High Court CFI
Date24 Feb 1982
Judge—
Case Document
100%

HCA007419/1980

IN THE HIGH COURT OF HONG KONG

1980 No. 7419
(Civil)

BETWEEN

SHING FAT (a firm)

Plaintiff

AND

CHAN SUM

Defendant

-------

Coram: Penlington J.

Date: 24 February 1982

___________

JUDGMENT

___________

1. The Plaintiff Company in this action alleges that the Defendant failed to complete a contract which he had entered into to cut-up a steel dry-dock gate at the old Taikoo Dockyards, thus requiring it to re-contract the work at much higher cost.

2. The Defendant's case is that it was agreed between himself and the Plaintiff that he was only to be responsible for cutting work above water and that the Plaintiff agreed that it would raise the gate above the water so he could do his work. That was not done. He is not a diving contractor and knows nothing about cutting steel under-water.

3. I believed the Defendant's evidence and I did not find the Plaintiff's evidence to be satisfactory. I am satisfied there was such a collateral agreement as alleged by the Defendant. The Defendant is entitled to the sum still owing on the contract, $27,000, less the sum of $7,000 advanced to him and the sum of $19,257, the value of scrap steel be removed. That leaves a balance of $743. The Defendant is also entitled to the return of the tools detained by the Plaintiff, to be handed over on the 25th February.

4. The Defendant to have his disbursements.

(R. G. Penlington)
Judge of the High Court

Representation:

Mr. R. E. Mayne (Kao, Lee & Yip) for the plaintiff.

Defendant in person.

Summaries and metadata are generated from the judgment. Report an error

Shing Fat(A Firm) v. Chan Sum [HCA 7419/1980] | BabelCite