Hong Kong Institute of Education v. Aoki Corporation
Read the full judgment text of HCCT74/2002 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 29 January 2003 before Hon Burrell J.
Arbitration — Construction contracts — Two arbitrations involving same parties and related contracts on same project — Application for consolidation or concurrent hearing under Arbitration Ordinance (Cap.341) s.6B(1) — Court adopts three-stage test from Linfield Limited v. Brooke Hillier Parker — Common questions of law and fact and transactional connection found — Shared arbitrator, overlapping witnesses, similar legal issues including delay and valuation — Differences outweighed by common features — Court orders hearings to proceed concurrently — Costs order nisi made in applicant's favour.
Legal issues: Application of section 6B(1) Cap.341 to consolidate or hear arbitrations together
Outcome: The court ordered that the two arbitrations be heard at the same time under section 6B(1) of Cap.341.
|
HCCT000074/2002 HCCT74/2002 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS -------------------------
-------------------------
---------------------- Coram: Hon Burrell J in Chambers Date of Hearing: 21 January 2003 Date of Decision: 29 January 2003 -------------------- D E C I S I O N -------------------- 1.The applicant and respondent are currently involved in two sets of arbitration proceedings. They are the only parties in those proceedings. The same arbitrator, namely Mr John Blackburn QC, has been appointed for both. On 29 August 2002, he made certain directions in respect of both arbitrations. Firstly, he set out a timetable for the service of pleadings. The timetable is similar but not identical for each arbitration. Secondly, he made the following direction in respect of both arbitrations :
2.By this application, the applicant seeks an order, which the arbitrator does not have power to make, under section 6B(1) of Cap.341. Section 6B(1) provides as follows :
3.I have been advised, in the course of this application, that if the two arbitrations were heard separately but consecutively the five weeks provided for would be sufficient time although one arbitration might last a little longer than the other. Thus, as the situation presently stands, the arbitrations will follow one immediately upon the other and should be completed within five weeks. 4.By this application therefore, if section 6B(1) is applicable they will be either consolidated or heard together, as contended for by the applicant, or, if it not applicable, they will be heard one immediately after the other, as contended for by the respondent. 5.In Linfield Limited v. Brooke Hillier Parker, HCA7693/2000, Ma J (as he then was) made the following observation concerning the application of section 6B(1) with which I agree and adopt :
6.I make two additional comments. Firstly, it is not necessary when considering stage 2 to consider sub-paragraphs (a), (b) and (c) of section 6B(1) in relation to each ground as a separate self-contained exercise. Secondly, when considering sub-paragraph (b) namely :
an over narrow approach should be avoided. It is not the relief claimed which has to appear to be the same, but the rights to that relief. Thus, Rhind J in R.v. Shui On Construction Co. Ltd v. Schindler Lifts (HK) Ltd [1986] HKLR 1177 observed that an order under section 6B(1) could be made even before the pleadings in the arbitrations had been closed. If there is a sufficiency of commonality the court may make an order. Even though there may be significant factual differences, if these differences are plainly outweighed by the common factors then, again, the court may make an order. It may well be that if an order is made on this basis, it will have been under sub-paragraph (c) namely that "it is desirable to do so" because of an accumulation of relevant considerations. 7.In my judgment, this is just such a case. Mr T. Hill, on behalf of the respondent, has carefully pointed out differences. Differences in the terms of the two contracts, differences in the timing of performance and chronology of events and differences in the issues to be resolved. These differences are noted but I am satisfied that they are outweighed by the similarities and common features to such an extent that the discretion should clearly be exercised in the applicant's favour. 8.Examples of such factors, upon which Mr D. Boyle, who appears for the applicant, relies and with which the court agrees, are as follows :
9.I am thus satisfied that there is a sufficiency of commonality in the transactions, the issues and the proceedings to merit an order that the two arbitrations be heard at the same time and I so direct. It is always open to the learned arbitrator, as master of his own tribunal, to make such directions as he deems necessary to ensure that the proceedings are heard smoothly and fairly. Mr T. Hill, correctly, asked the court, at the end of the day, to do a balancing act. I have endeavoured to do so. 10.I make a costs order nisi in the applicant's favour on this application.
Representation: Mr David Boyle of Messrs Johnson Stokes & Master, for the Applicant Mr Timothy Hill of Messrs Lovells, for the Respondent |