Aoki Construction Co Ltd v. Attorney General
Read the full judgment text of HCMP 994/1980 on BabelCite. This High Court CFI judgment.
1. By a PWD contract No. 413 of 1977 dated 20th December, 1977, the plaintiff company undertook to construct a railway tunnel through Beacon Hill with a view to providing double tracking for the Kowloon-Canton Railway. Construction was to be completed in about 2 ½; years, and the whole project would involve over $78,000,000. The PWD contract incorporated what is known as the standard Conditions of Contract for Civil Engineering Construction (1971 edition) which is taken from the I.C.E. General C
|
HCMP000994/1980
----------------- Coram: Liu, J. in Chambers. Date of Judgment: 2nd December, 1980 ----------------- JUDGMENT ----------------- 1. By a PWD contract No. 413 of 1977 dated 20th December, 1977, the plaintiff company undertook to construct a railway tunnel through Beacon Hill with a view to providing double tracking for the Kowloon-Canton Railway. Construction was to be completed in about 2 ½; years, and the whole project would involve over $78,000,000. The PWD contract incorporated what is known as the standard Conditions of Contract for Civil Engineering Construction (1971 edition) which is taken from the I.C.E. General Conditions of Contract. The relevant clauses of the General Conditions in the PWD contract are set out below:
2. After the commencement of work on the 3rd January, 1978, six water mains were located near the North Portal to the tunnel some three metres below ground level. Subsidence was detected, and the safety of these water mains responsible for the supply of all the drinking water for Kowloon was threatened. 3. In November, 1978, work stopped so as to avoid causing further deflection of these water mains. Differences arose between the Engineer and the plaintiff contractor. Remedial and protective measures were designed. Between the 29th November, 1978 to the 17th March, 1979, six written instructions were issued by the Engineer to the plaintiff contractor who was thereby ordered to carry out the remedial and protective works. The works so ordered by the Engineer took several months to complete and allegedly incurred some $20,000,000. 4. By a letter to the Engineer dated the 30th March, 1979, pursuant to Clause 120(1) of the General Conditions the plaintiff contractor referred the liability for and quantum of these remedial and protective works to the Engineer for his decision in the following terms
5. On the 24th March, 1980, the Engineer gave his decision, whereby most of the plaintiff contractor's claims to payment certificates for the value of the remedial and protective works ordered were rejected. The plaintiff contractor had persisted in including the value of these works in the monthly payment applications, but the Engineer had continued to exclude these items from the payment certificates with equal determination. 6. Being dissatisfied with the Engineer's decision, by a letter dated the 6th June, 1980 the plaintiff contractor required the Director of Public Works to refer the dispute to arbitration. Government refused to give its consent to arbitrate before the completion of the entire PWD contract. 7. Works under the PWD contract are not expected to be wholly completed before April, 1981. It is common ground that there is a substantial and genuine dispute between the parties within the ambit of Clause 120(1) and that ultimately the plaintiff contractor may refer the matter decided by the Engineer to arbitration. The only issue in these proceedings is whether the plaintiff contractor is entitled to have the matter arbitrated as of now without the written consent of Government prior to the completion of the PWD contract; in another words, whether the dispute falls within one of the exceptions in Clause 120(6) of the General Conditions. 8. By these proceedings, the plaintiff contractor sought a judicial interpretation of Clause 120(6), two consequential declarations and the appointment of an arbitrator pursuant to section 12 of the Arbitration Ordinance. 9. There are other proceedings which, by consent, will abide by and be disposed of in accordance with the determination on the plaintiff's originating summons in these proceedings. 10. Mr. Nunn on behalf of the defendant submitted that on the proper construction of the PWD contract, the plaintiff contractor was not entitled to payment and had shown no right to a certificate; hence there had been no withholding of any certificate as there was no certificate due to the contractor. 11. Mr. Tang for the plaintiff contractor relied heavily on the case of A.E. Farr Limited v. The Ministry of Transport(1). Counsel directed my attention to the very fact that identical arguments advanced before Buckley, J. in the Farr case were rejected. The Farr case is, in my judgment, directly in point. It was an action for the construction of a similar clause in a building contract in I.C.E. form for the excavation of a vehicular underpass. Disagreement arose in which the contractors claimed to be entitled to payment for excavation not only of the space to be occupied by the retaining walls of a tunnel but also of the necessary working space. It was contended by the employer that the contractors could not refer the dispute to arbitration under a similar clause, Clause 66, until the works had been completed. Clause 66 in that building contract is identical in terms with our Clause 120(6) and reads as follows:
12. Buckley, J. was unconcerned with the merits. Having emphasized that interim certificates were subject to final adjustments in the usual provisions of the I.C.E. General Conditions of Contract, the learned judge observed that "a bona fide difference of opinion between the engineer and the contractor about measurements" could hardly be a matter for and was in fact not referable to arbitration. Such dictum does not find favour with the learned editor of Hudson's Building and Engineering Contracts 10th Edition(2). That observation of Buckley, J. was obiter and can be of no assistance to us in these proceedings. However, the criticisms so unhesitantly made in Hudson's may not be wholly justified, particularly when an employer's decision on measurements must be accepted as final under a clause in the I.C.E. form equivalent to Clause 118 of our PWD contract in this case. I have been assured by counsel of the existence of such an equivalent. 13. The oblique reference to "withholding of a certificate" in cases involving dissimilar clauses in building contracts offers little real guidance. In F.R. Absalom Limited v. The Great Western (London) Garden Village Society(3), the question of withholding a certificate was never directly in issue. It seemed to have been only too readily assumed that if ever the contractor was right on his figures (i.e. the employers were wrong on theirs), a certificate had been withheld. R.B. Burden Limited v. Swansea Corporation(4) is a case in which the focal point was whether a local authority as employer had interfered with or obstructed the issue of any interim certificates. 14. At p.966 in Farr case, Buckley, J. addressed himself to the issues before the court from more standpoints than one:
15. The learned judge was stating the obvious. Granted that if good faith and the principles applied are not impugned, no employer can be accused of withholding a certificate where clearly none is due. Incidents of this kind must be rare, and evidently Buckley, J. must have been highlighting the simplest of the strict measurement cases. But if, for ulterior motive, an employer either refuses a certificate altogether or refuses to certify the proper amount, he must then be withholding a certificate. If an employer, acting on wrong legal principles, refuses a certificate altogether, or refuses to certify the proper amount, he must again be withholding a certificate. 16. At p.967, the learned judge continued:
17. It is conceded that there is a genuine and substantial dispute between the parties as to the remedial and protective works. It is alleged by the plaintiff contractor that the Engineer had misdirected himself about the law as to the true nature of the contractor's claim. The refusal of the Engineer to certify the balance must therefore, in my view, be a withholding of a certificate within the meaning of Clause 120(6). 18. Mr. Nunn submitted that the judgment in the Farr case was plagued with contradictions and should be perused with sustained caution. It was charged that no clear guiding principle evolved from a mass of inconsistencies and that the decision should not be accorded its usual respect. On a fair reading of the judgment, I am unable to draw myself close to Mr. Nunn's misgivings. Counsel further contended that on a proper construction of Clause 120(6), no "withholding" could arise except in a case of an established right to payment. If a claim for payment and thus a certificate had been conclusively substantiated, the refusal to issue a certificate would have been blatently wrong. On Mr. Nunn's suggested interpretation, Clause 120(6) would become meaningless as hardly any arbitration need be initiated for an entitlement already proven. 19. As Buckley, J. categorically stated at p.967:
20. It is quite unnecessary for me to consider if the clause "to which the Contractor claimed to be entitled" also qualifies the first exception in Clause 120(6). 21. In my judgment, the exception of "withholding by the Engineer of a certificate" in Clause 120(6) of the General Conditions in the PWD contract must include the situation in which a genuine dispute has arisen as to whether payment and thus a certificate is due for works executed. 22. Subject to the deletion of the words "to which the Contractor claims to be entitled" which are unnecessary for my decision, I would and do grant the declarations sought. I would appoint Mr. Severn as arbitrator if he consents to act. Costs must follow the event in favour of the plaintiff contractor. The summons of the defendant in High Court Action No. 4250 of 1980 be accordingly disposed of in terms supplemental to this decision.
Representation: (1) [1976] 1. W. L. R. 956 (2) See p. 495 (3) [1933] A. C. 592 (4) [1957] 1 W. L. R. 1167 |