Yeung Wai Yung t/a Wai Hop Construction Eng v. Bolton Construction Co Ltd

Read the full judgment text of HCA 16822/1999 on BabelCite. This High Court CFI judgment was delivered on 19 January 2000.

1. These are brief reasons for judgment given in the defendant's favour on 19 January 2000 on its application to stay HCA16822/1999 proceedings pursuant to s.6 of the Arbitration Ordinance, Cap.341 and judgment dismissing the plaintiff's application for judgment to be entered in its favour for part of the sum claimed.

Case No.HCA 16822/1999
Court
High Court CFI
Date19 Jan 2000
Judge
Case Document
100%Judiciary

HCA016822/1999

HCA16822/1999

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

ACTION NO. 16822 OF 1999

-----------------

BETWEEN
YEUNG WAI YUNG trading as WAI HOP CONSTRUCTION ENG. Plaintiff

AND

BOLTON CONSTRUCTION COMPANY LIMITED Defendant

-----------------

Coram: Hon Burrell J in Chambers

Date of Hearing: 19 January 2000

Date of Decision: 19 January 2000

Date of Handing Down Reasons for Decision: 21 January 2000

---------------------------------------------------

REASONS FOR DECISION

---------------------------------------------------

1. These are brief reasons for judgment given in the defendant's favour on 19 January 2000 on its application to stay HCA16822/1999 proceedings pursuant to s.6 of the Arbitration Ordinance, Cap.341 and judgment dismissing the plaintiff's application for judgment to be entered in its favour for part of the sum claimed.

2. The plaintiff served a Statement of Claim dated 26 October 1999 for $890,468.00 for works done and materials supplied. On 9 December 1999 the defendant issued its summons for a stay invoking the arbitration clause in the subcontract between the parties. The defendant also included a counterclaim in which it sought to set off the sum of $1,266,232.00 in extinction of the plaintiff's claim. In addition, paragraph 3(iii) of the Defence stated :-

"Pursuant to the subcontract, the Defendant subsequently issued, inter alia, the following Works Orders to the Plaintiff under which but for the Defendant's counterclaim herein, the amounts of the balances which would otherwise be payable to the Plaintiff are as follows:- (total, $287,865.00)"

3. Originally the plaintiff's submission as outlined in the skeleton argument dated 18 January 2000 made two points. The first point, which it is unnecessary to recite herein because it was abandoned on the day of the hearing, was misconceived as it relied on pre-1996 law and paid no heed to s.6 of the Arbitration Ordinance, Cap.341 and Article 8(1) of the Model Law.

4. What remained was the contention that the scope of the Arbitration Clause did not extend to the sum of $287,865.00 because the applicant had failed to show that a dispute existed in relation to this sum. It was conceded that the balance of the claim and the amount of the counterclaim were in dispute.

5. In order even to get the argument above ground level it must be shown that there had been an admission by the Defence. Paragraph 3(iii) contains the words "but for ..." and "would otherwise be payable...". The court does not construe these as admissions in the context of the overall picture. Put simply, arising out of the one and only subcontract between these parties a dispute exists as to what one party is liable to pay the other following works done and materials supplied by the plaintiff. The question is, does such a dispute fall within the scope of the arbitration clause. The clause states as follows :-

"12.1 In the event of any dispute concerning the interpretation of or performance under this Sub-Contract between the contracting parties, the dispute shall be resolved by negotiation or mediation. If mediation or negotiation fails, either party can refer the difference or dispute to arbitration which shall be conducted by a sole arbitrator in accordance with the Short Form Arbitration Rules of the Hong Kong International Arbitration Centre in force at the time of the arbitration."

6. To suggest that a relatively small portion of the sums in dispute should be separated off either by judgment being entered or by an order for a payment into court and then refer the balance to arbitration, when the so-called "admission" in relation to the relatively small portion is plainly conditional on the outcome of the defendant's defence of set-off is both unrealistic and misconceived.

7. These are the reasons for the decisions made at the conclusion of the hearing. In addition, there will be an order as to costs in the defendant's favour on both summonses.

(M.P. Burrell)
Judge of the Court of First Instance
High Court

Representation:

Ms Catherine K.K. Wong, inst'd by M/s Wong & Chu, for the Plaintiff

Mr Francis Ip of M/s K.F. Wong & Co., for the Defendant